3rd Quarter Results for LIM and outlook
LIM Reports Third Quarter Results and Outlook for First Year of Production
15 February 2011
Anglesey Mining's 41% owned associate Labrador Iron Mines Holdings Limited
(TSX: LIM) is pleased to report that it has filed its unaudited financial
statements and MD&A for the third quarter and nine months ended December 31,
2010. The documents are available under the Company's profile at www.sedar.com
and on LIM's website at www.labradorironmines.ca.
During the quarter and nine months ended December 31, 2010, LIM invested
C$5,040,338 and C$8,334,887 respectively in its mineral property interests,
compared to C$1,607,373 and C$5,911,071 respectively in the prior year, the
increase relating to significant mine development activities in anticipation of
the commencement of production in 2011. For the same periods, LIM also saw
increased investment in property, plant and equipment of C$5,022,643 and
C$15,227,374, compared to C$2,598,817 and C$4,209,769 in the prior year, due to
the significant investment in processing plant equipment, rail spur line and
related construction costs.
LIM reported a loss of C$995,200 or C$0.02 per share in the quarter ended
December 31, 2010, compared to net income of C$2,356,601 or earnings of C$0.06
per share for the same quarter in the prior year in which an income tax
recovery had been recognized.
At December 31, 2010, LIM had cash and cash equivalents of C$27,949,904 and no
debt. LIM had 43,927,514 common shares outstanding at December 31, 2010.
Subsequent to the end of the quarter, LIM granted additional stock options on
132,500 shares to new employees exercisable at C$11.65 per share for a period
of five years vesting over a two-year period.
Project Update and Outlook
Mining Activities Underway
Waste stripping at the James North deposit commenced in January 2011 and by the
second week of February about 300,000 tonnes of material had been moved. Most
of the James North pit area has now been stripped of overburden and the orebody
is exposed along the first production bench.
Development of the first mining bench in the north end of the James pit has
begun to prepare a mining face in the higher grade blue ore, which will be the
first ore to be mined, and some of which may be directly shipped with only
minimal crushing and without further processing. The waste rock has proved to
be free digging and mine development is currently ahead of schedule.
The ore haul road from the James Mine to the Silver Yards processing site has
been completed and is operational. The various ore and waste rock stockpile
areas have been prepared, as have the temporary and permanent ore storage pads.
Ore mined from the initial development, together with the stockpiles of ore
from previous bulk sampling programs, will be delivered to the plant ahead of
the primary crusher ready for processing.
The first James mine settling pond has been constructed to collect water pumped
from the pit. Two additional dewatering wells will be drilled to supplement the
wells drilled in 2009. Pump and piping installation and dewatering of the James
pit is to commence in the spring of 2011. Site clearing and grubbing at the
James South pit is also being completed during the winter months.
Full scale mining operations are planned to commence in April 2011, and will
continue for eight months until November, at an anticipated initial mining rate
starting at 6,000 tonnes of ore per day, increasing to over 10,000 tonnes of
ore per day, using conventional open-pit mining methods and eventually
employing standard drilling and blasting operations as required.
Plant Commissioning on track for April 2011
The beneficiation plant and associated facilities were structurally complete at
the end of 2010. The remaining fabrication, piping, electrical and other
mechanical installation will be completed in the next few weeks. Conveyor belts
will then be run in readiness for commissioning. Once installation of the plant
is completed, dry run stockpiled ore will be fed to the plant to allow
commissioning to take place, which, subject to weather conditions, is scheduled
to begin in April 2011.
The accommodation camp at Bean Lake consisting of 72 units has been completed
and will be ready for occupation by the end of February.
Plant Upgrades and Expansion
The Silver Yards plant as currently installed has a design capacity to process
10,000 tonnes per day and the equipment to crush, wash and screen to recover
about 65% of the contained iron in the blue ore, which will produce two
products, the first a coarse lump ore and the second a sinter feed. It is
expected that initially the lump ore will represent about one third of the
product.
Once the basic processing plant is commissioned, a series of plant upgrades and
expansions will be undertaken. LIM plans to install a fines recovery system
during 2011. This will include installation of a hydrosizer and pan filter.
This system will be installed during the summer months and is expected to be
operational by September 2011. The installation of this system is expected to
increase overall recoveries to about 75% and the plant output by approximately
13% by the production of a third product - sinter extra fines, which can be
sold separately or blended with the coarse sinter fines product.
As well an additional process to beneficiate the lower grade and -100 µm ore is
being considered for installation in the fall of 2011 towards commissioning in
the spring of 2012 to produce a fourth ultra-fine product which would be sold
as pellet feed. Installation of that additional equipment would improve the
grade of the lump and coarse sinter feed products, while at the same time
improving recoveries to over 80% and increasing the capacity of the plant by
approximately 6%.
The ore which contains the higher levels of silica will not be processed in the
first year of operations but will be stockpiled for treatment later when the
plant is expanded with the addition of a further processing line. Subject to a
planned metallurgical test program, this is expected to have an approximate
recovery of 67% of high silica ore and will increase the total Silver Yards
plant treatment capacity by an additional 1 million tonnes per year to over 3
million tonnes per year. This expansion line is expected to be in operation for
the 2012 operating season.
2010 Exploration Program
The 2010 exploration program completed 4,500 metres of drilling and 1,400
metres of trenching at the Denault, Ruth 8, and Houston properties.
Exploration drilling at Houston during 2010 has significantly increased the
size of the resources to 19.49 million tonnes of measured and indicated
resources which represents a significant increase over previous estimates. The
Houston deposits remain open along strike particularly to the southeast and
further drilling is planned on Houston 3 during 2011 - see press release of 11
February 2011.
As a result of this significant increase, the Houston deposits are now of
sufficient tonnage that merits evaluation of a stand-alone operation. LIM
intends to evaluate the development of a new separate South Central Zone, as
Stage 2 of its Schefferville Area Projects, possibly with its own dedicated
processing plant which, subject to environmental assessment, permitting and
detailed engineering, could be brought into production in 2013 at a rate of 2
to 3 million tonnes of iron ore per year.
Drilling at Denault has indicated some extensions to that deposit which will be
incorporated into revised resource estimates for the Denault deposit when the
results have been analysed.
During the 2010 exploration season an airborne gravity and magnetic survey was
flown over four claim blocks of LIM's Schefferville area properties centred on
the Howse, Houston/Redmond, Astray and Sawyer Lake areas. High gravity
anomalies associated with lower magnetism are considered prospective for DSO
deposits. In total 1895.7 line kms was flown for the gravity and magnetic
surveys. A total of 473.6 line kms were surveyed over the Howse area, 851.8 kms
over Houston/Redmond areas, 354.6 kms over Astray and 215.7 line kms over the
Sawyer Lake area.
An interim interpretation and evaluation of the processed and plotted airborne
gravity gradiometer and magnetic data has confirmed the utility of the survey
in detecting and outlining iron deposits and identified a number of new drill
targets with the potential to expand currently known resources. Several of the
new targets identified will be tested in 2011 using reverse circulation or
diamond drilling.
Rail Transportation
LIM is in advanced negotiations with each of the railroad companies that will
transport LIM's ore to port with regard to the transportation of its iron ore
products in 2011 and future years. These consist of Tshiuetin Rail
Transportation (TSH) for haulage over the 130 mile main line track between
Schefferville and Emeril Junction; the Iron Ore Company of Canada's Quebec
North Shore and Labrador Railroad ("QNS&L") for the remaining approximately 225
miles to Sept-Iles; and Wabush Mines-owned Arnaud Railway (Chemin de fer Arnaud
(CFA)) for the approximately 21 miles around the Sept-Iles bay to the terminal
at Pointe-Noire. To date LIM has not yet concluded agreements with the relevant
rail companies for the transportation and handling of its planned production of
iron ore.
LIM plans to lease rotary gondola ore cars each with a capacity of 100 tonnes
with a car body suitable for a gross rail load of about 130 tonnes (286,000
lbs). Three car sets, each consisting of 120 railcars, are estimated to be
required to transport LIM's iron ore tonnage for the eight month period in
calendar 2011. The total LIM railcar fleet will range from approximately 360 to
400 railcars. The total railcar cycle time from the Silver Yards site to
Pointe-Noire for the loaded movement and empty return of a train is expected to
be approximately 68 hours.
The locomotives between the Silver Yards and Emeril Junction will be shared
with TSH in a run through operation. These trains will be powered by two SD40
locomotives equipped with Locotrol and proximity detection devices, which
locomotives will also be leased by LIM.
LIM has not yet concluded leasing agreements with the equipment leasing
companies for the leasing of railcars or locomotives.
Port - Shipping Facilities
In February 2010 LIM signed an agreement with the Sept-Iles Port Authority for
the use of the Pointe-Noire facilities at the Port to ship LIM's iron ore
products. LIM agreed to a base fee schedule with the Port Authority regarding
wharfage fees for iron ore loading for LIM's shipping operations.
LIM is evaluating a number of different options for its Sept-ÃŽles operations
including use of the facilities of Wabush Mines or other facilities of the
Sept-ÃŽles Port Authority. LIM is in negotiations with Wabush Mines and with the
Sept-Iles Port Authority, and with other port operators, with regard to
transportation, storage, handling and loading of LIM's iron ore products at
Pointe-Noire.
LIM has not yet concluded agreements with the relevant rail companies or port
operators for the transportation and handling of LIM's planned production of
iron ore.
Marketing - iron ore markets
Marketing discussions have continued with potential customers, both in Europe
and in Asia. Chinese consumers, in particular, are showing a growing interest
in seeking iron ore from Canada, driven by continued strong demand and a desire
to diversify from their traditional sources of supply.
LIM continues to review its options for marketing its planned iron ore
production and is evaluating the optimum route to achieve these sales, while
still maintaining maximum flexibility and independence. In particular LIM has
had detailed discussions with a number of internationally recognized commodity
traders with specialist knowledge of the iron and steel industry and expects to
finalize marketing arrangements with one of these for the sales of its initial
2011 ore production in the near term. To date, LIM has not yet concluded any
agreements for the sale of iron ore. It is expected that iron ore products
produced in 2011 will be sold into the spot market on a "FOB Sept-Iles" basis.
As LIM nears commencement of production in the next quarter, the global iron
ore market remains very positive with recent prices for 62% Fe sinter fines
approaching US$190 per tonne CFR China. Despite efforts by the Chinese
government to slow down some aspects of growth of the Chinese economy, demand
for iron continues to grow. This demand, coupled with some interruptions in
supply from Australia and Brazil, has driven iron ore prices to an all-time
high.
The current increases in iron ore costs will inevitably lead to increases in
steel prices, which may lead to reduced levels in steel demand in subsequent
periods. In the short to medium term, demand is expected to remain strong and
prices are forecast to retract only marginally. In the longer term, as major
new production capacity comes online in Brazil and Australia, the balance
between supply and the continuing increasing demand is likely to remain close.
The consensus of current forecasts is that iron ore supply and demand will
remain generally in balance until around 2015, with prices only dropping 10-15%
in that period, followed by a supply surplus with prices declining somewhat
thereafter. LIM is of the opinion that iron ore prices will remain strong for
both calendar 2011 and calendar 2012.
Outlook
LIM believes it is on track to conclude the required rail transportation and
port related commercial agreements in the near term and to commence mining and
processing activities in April 2011, followed shortly thereafter by sales into
a robust iron ore market. It is also actively working on finalizing IBA
agreements with the Innu Community of Matimekush-Lac John (Schefferville) and
with the Innu of Uashat (Sept-Iles), the two remaining First Nations groups in
which it does not already have IBA agreements.
LIM currently expects to mine in excess of 2 million tonnes of ore in 2011,
which is partially a construction/start-up year. Assuming satisfactory plant
commissioning and smooth start-up, and based on projected recoveries (expected
to start initially at about 65% and increasing to about 75% with the
installation of the fines recovery equipment), and assuming an operating season
of about 210 days, (subject to weather conditions) this is expected to yield
shipments of about 1.5 million tonnes of iron ore, prior to seasonal shutdown
of operations at the end of November 2011.
With the high level of iron ore prices currently prevailing, the progress made
to date in constructing the mine and beneficiation plant, and with mine
operations expected to commence in April 2011, the outlook for LIM is positive.
There are still a number of commercial agreements to be concluded, including
final rail and port arrangements. Provided these remaining agreements are
resolved in a timely and satisfactory manner, LIM can look forward to achieving
commercial production around the middle of calendar 2011.
About Labrador Iron Mines Holdings Limited (LIM)
LIM's Schefferville Project involves the development of twenty direct shipping
iron ore deposits in western Labrador and north-eastern Quebec near
Schefferville, Quebec. The properties are part of the historic Schefferville
area iron ore district where mining of adjacent deposits was previously carried
out by the Iron Ore Company of Canada from 1954 to 1982.
Labrador Iron Mines contemplates mining in stages, the first phase of Stage 1
comprising the James and Redmond deposits, which are located in close proximity
to existing infrastructure, where construction is being completed and mine
start-up is planned to commence in April 2011.
For further information, please view LIM's website at www.labradorironmines.ca
About Anglesey Mining plc
Anglesey Mining with its LSE main board listing is primarily focused on its 41%
interest in Labrador Iron Mines (TSX:LIM). In addition to any new projects that
may be brought forward the company owns 100% of Parys Mountain in North Wales
with an historical resource in excess of 7 million tonnes at over 9% combined
copper, lead and zinc.
For further information, please contact:
Bill Hooley, Chief Executive +44 (0) 1492 541981
Ian Cuthbertson, Finance Director +44 (0) 1248 361333
Emily Fenton / Charlie Geller,
Tavistock Communications +44 (0) 20 7920 3155 / +44 (0) 7788 554035