LIM technical report on iron ore projects
Anglesey Mining plc LSE:AYM
18 March 2011
LIM files Technical Report on its DSO iron ore projects in Labrador and Quebec
Anglesey Mining plc's 41% owned associate Labrador Iron Mines Holdings Limited
("LIM") or (the "Company") (TSX: LIM) reports the filing on SEDAR (the official
website that provides access to most Canadian public securities documents and
information filed by public companies) of a Technical Report addressing the ongoing
exploration and development of its DSO iron ore projects on the Company's various
deposits in Western Labrador and North Eastern Quebec.
The Technical Report has been prepared as a result of additional metallurgical
testwork and process design and following the completion of the construction of
the Silver Yards processing plant facility and other associated infrastructure
and the commencement of initial mining at the James deposit.
The Report proposes various additions to the Silver Yards plant as a result of
the recent metallurgical testwork and discusses a preliminary production
schedule for the current resources together with the future development of the
further twelve deposits containing historic resources through to the year 2028.
The Report also makes recommendations for further exploration on the various
deposits and other associated work required to advance the deposits towards
production.
The Technical Report notes the recent new resource estimates for the Houston
and Denault deposits as a result of additional exploration drilling carried out
in 2010. [See LIM Press Release dated February 11, 2011 and Houston Technical
Report filed on SEDAR February 21, 2011. See also LIM Press Release dated
March 4, 2011 and Denault Technical Report filed on SEDAR March 14, 2011].
LIM has now defined 37 million tonnes of current NI 43-101 compliant direct
shipping hematite iron ore resources at the first four deposits that it intends
to develop. In addition, a further 125 million tons of historical resources
exist on LIM's other properties that were defined by IOC during their
historical operations in the area.
The current resource estimates for the James, Redmond, Houston and Denault
deposits are summarized in following table.
Total NI 43-101 Compliant Resources, Labrador and Quebec
Area Classification Tonnes (x1000) Fe% P% Mn% SiO2% Al2O3%
James1 Indicated 8,098,000 57.7 0.027 0.7 14.1 0.5
James1 Inferred 111,000 53.6 0.036 0.1 19.9 0.5
Redmond 2B1 Indicated 849,000 59.86 0.12 0.37 5.05 2.09
Redmond 2B1 Inferred 30,000 57.27 0.133 0.64 5.87 4.09
Redmond 51 Indicated 2,084,000 54.95 0.048 1.17 10.97 0.81
Redmond 51 Inferred 78,000 52.34 0.068 1.95 10.84 0.96
Houston2 Measured 10,439,000 58.93 0.060 0.91 11.34 0.78
Houston2 Indicated 9,060,000 57.55 0.060 0.96 13.48 0.68
Houston2 Inferred 1,024,000 55.8 0.055 1 16.5 0.5
Denault3 Measured 4,456,000 55.1 0.077 2.4 7.5 1.1
Denault3 Indicated 1,928,000 54.2 0.074 2.3 9.0 1.0
Denault3 Inferred 369,000 53.9 0.069 2.7 9.4 0.9
Total Measured & Indicated 36,914,000 57.41 0.06 1.09 11.71 0.75
Total Inferred 1,612,000 55.07 0.06 0.76 14.64 0.68
"Technical Report Resource Estimation of the James, Redmond 2B and Redmond 5
Mineral Deposits Located in Labrador, Canada for Labrador Iron Mines Limited"
by Maxime Dupéré, geo, of SGS Geostat Ltd. dated December 18, 2009; [SEDAR
filed December 23, 2009].
See Technical Report on the Houston Iron Ore Deposit Western Labrador, Province
of Newfoundland and Labrador, Canada" by T. N. McKillen, B.A.(Mod), M.A.,
M.Sc., P.Geo, D. William Hooley, B.Sc(Eng.), FAusIMM and Daniel Dufort,
(P.Eng.) concerning the Houston property in Labrador dated February 21, 2011;
[SEDAR filed February 21, 2011].
"Technical Report and Resources Estimate on the Denault Iron Ore Deposit
Province of Québec Canada" by T. N. McKillen, B.A.(Mod), M.A., M.Sc., P.Geo;
dated March 11, 2011 [SEDAR filed March 14, 2011].
The historical resources referred to in this document are based on work
completed and estimates prepared by the Iron Ore Company of Canada ("IOC")
prior to 1983 and were not prepared in accordance with NI 43-101. These
historical estimates are not current and do not meet NI 43-101 Definition
Standards. A qualified person has not done sufficient work to classify the
historical estimate as current mineral reserves. These historical results
provide an indication of the potential of the properties and are relevant to
ongoing exploration. The historical estimates should not be relied upon.
Preliminary Development Schedule
LIM intends to develop all these resources in five separate stages. The first
four stages will see the various deposits treated in three beneficiation
plants, to be built adjacent to several of the deposits that comprise the
Central, South Central and North Central Zones.
Stage 1 incorporates the James and Redmond deposits at the Silver Yards plant
which is now constructed and where production is expected to commence in the
spring of 2011. This stage also contemplates the treatment of other nearby
deposits (Central Zone) and is expected to continue until 2021.
Stage 2 contemplates a new plant at the Redmond Mine site initially treating
Houston ore, commencing in 2013, and will continue until about 2022 (South
Central Zone). Stage 3 is based on a third plant near Howse, (North Central
Zone) which will treat ore from Barney and Howse, commencing in 2015 and will
continue until about 2028. Stage 4 treating ore from the southern deposits
Sawyer Lake and Astray Lake (South Zone) through the Redmond plant will
continue until about 2028. Stage 5 based on ore from the Northern deposits
(North Zone) will follow the first 4 stages.
Overall production of saleable iron ore product is planned to commence at
around 1.5 million tonnes annually (mta) in 2011 and will build up to about 5
mta by 2015 and, based on the future development of all other deposits, stages
1 to 4 will continue at this level until about 2028 when stage 5 is expected to
commence.
Only the James and Redmond Deposits and the Silver Yards plant have completed
environmental assessment and permitting. Further environmental assessment and
permitting will be required for all the other deposits. Detailed mine design
and metallurgical testwork has been carried out on those deposits that will
form the basis of production for the initial years but further exploration,
testwork and design is required for all the remaining resources. A Feasibility
Study has not been completed on any of these Projects.
The first plant at Silver Yards and mine construction at James are essentially
complete and initial production is expected in the spring of 2011.
Plant Upgrade and Expansion
Based on the current testwork, a program of plant enhancement on the Silver
Yards plant is now planned for 2011 and 2012 with the objective to increase
both the plant throughput and recovery.
The current Silver Yards plant installation (Phase I) consists of a washing and
screening plant to produce lump and sinter fines. The plan for the first year
is to only wash and screen the higher grade blue ore material, while higher
silica blue and yellow ore will be stockpiled for later treatment.
It is intended that the Silver Yards plant will be upgraded and expanded to
improve recoveries, treat lower grade and higher silica ores and increase
throughput and output.
Phase II will consist of the installation of a fines recovery system and pan
filter. This installation will be completed during the summer of 2011 and
should commence operation in September 2011.
Phase III of the Silver Yards Plant will be the installation of an additional
line which will increase the plant throughput capacity and improve recoveries.
This work is currently being planned and will entail the installation of jigs
to upgrade the final products and the installation of a magnetic separation
stage on the slimes fraction to produce ultra-fines. Testing and design of the
Phase III expansion is currently in progress and, dependent on the results of
that program, the Phase III expansion should be installed for operation in
mid-2012. The additional line when installed will initially be used to process
the higher silica ore and the yellow ore will also be processed when the
equipment in Phase 3 is fully installed.
South Central Zone
The South Central Zone comprises the Houston and Malcolm deposits. The Houston
deposits located in Labrador some 20kms south-east of Silver Yard currently
comprises 19.5 million tonnes of compliant resource.
It was originally planned to treat Houston ore at the Silver Yards plant but
the increased Houston resource suggests that a new stand-alone plant to treat
Houston and other nearby deposits should be constructed. Subject to completion
of environmental assessment and permitting, this plant is now planned to be
built adjacent to the site of the currently permitted Redmond mine and to
commence production in 2013.
The Houston deposits remain open and an additional drill program will take
place in 2011 with the aim of increasing the size of these deposits and
enhancing the resource estimate.
Capital Costs Estimate
The additional capital costs for the Silver Yards plant projects are estimated
to be $3 million in 2011 for additional processing equipment to improve fines
recovery and approximately $35 million in 2012 for plant expansion and
enhancement.
The initial capital cost of the Houston Mine Project for mine site preparation,
overburden removal and road construction is estimated to be approximately $5
million in 2012/2013.
The capital cost of the new Redmond Plant is estimated to be approximately $35
million in 2012/13 based on the actual cost incurred by LIM on the construction
of the Silver Yard plant but modified to incorporate the single line design now
planned for the Redmond plant. An additional $8 to $10 million is estimated for
the cost of re-laying the Redmond rail spur line. These cost estimates are
subject to final permitting and detailed engineering and design.
Operating Cost Estimates
The average operating costs for the James-Redmond Silver Yards Project are
estimated to be in the range of approximately CAD$50 per tonne, with all mining
and processing activities carried out by contractors, and with rail
transportation and port handling costs collectively accounting for
approximately half of the total operating costs. The year 2011 is considered
to be a start-up year and initial unit operating costs are expected be about
10% higher than average.
Qualified Persons
The authors of the Technical Report (T.N. McKillen, D.W. Hooley and D. Dufort)
are either directors and/or officers of LIM and/or its subsidiaries. The
authors are "qualified persons" within the meaning of National Instrument
43-101 - Standards of Disclosure for Mineral Projects of the Canadian
Securities Administrators and have approved this Press Release. The authors are
not independent as described in section 1.4 of NI 43-101. D.W. Hooley approves
the contents of this Press Release.
About Labrador Iron Mines Holdings Limited (LIM)
LIM's Schefferville Area project involves the development of twenty direct
shipping iron ore deposits in western Labrador and north-eastern Quebec near
Schefferville, Quebec. The Company's properties are part of the historic
Schefferville area iron ore district where mining of adjacent deposits was
previously carried out by the Iron Ore Company of Canada from 1954 to 1982.
Labrador Iron Mines contemplates mining in stages, the first phase of Stage 1
comprising the James and Redmond deposits, which are located in close proximity
to existing infrastructure, and for which all operating permits have been
issued and plant construction and mine development is nearing completion.
For further information, please view the Company's website at
www.labradorironmines.ca.
About Anglesey Mining plc
Anglesey Mining with its LSE main board listing is primarily focused on its 41%
interest in Labrador Iron Mines (TSX:LIM). In addition to any new projects that
may be brought forward the company owns 100% of Parys Mountain in North Wales
with an historical resource in excess of 7 million tonnes at over 9% combined
copper, lead and zinc.
For further information, please contact:
Bill Hooley, Chief Executive +44 (0) 1492 541981
Ian Cuthbertson, Finance Director +44 (0) 1248 361333
Emily Fenton / Charlie Geller,
Tavistock Communications +44 (0) 20 7920 3155 / +44 (0) 7788 554035