BASE RESOURCES LIMITED
Board approves Kwale Phase 2 mine optimisation project to deliver enhanced economics
KEY BENEFITS
FEATURES
IMPLEMENTATION MILESTONES
[Graphical representations referenced in this release have been omitted. A full PDF version of this release, including all graphs, is available from the Company’s website: www.baseresources.com.au.]
African mineral sands producer, Base Resources Limited (ASX & AIM: BSE) (“Base Resources†or the “Companyâ€) is pleased to announce that, following completion of the Definitive Feasibility Study (“DFSâ€), the Board has approved implementation of the Kwale Phase 2 project (“KP2â€) at its Kwale Mineral Sands Operations (“Kwale Operationsâ€) in Kenya, East Africa. The DFS confirmed the opportunity for significant improvement in the financial returns for Kwale Operations through further optimisation of the remaining mine life. The DFS was completed internally by Base Resources’ project development team, supported by several specialist consulting firms, and included an independent peer review process.
The objective of the KP2 project is to maximise the overall Kwale Operations economic returns by implementing a solution to maintain maximum concentrate feed to the Mineral Separation Plant (“MSPâ€), and therefore final production volumes, in the face of declining ore grades expected from mid-2018 onwards. The KP2 DFS has established that this objective can be effectively and efficiently achieved.
The key results and underlying assumptions for both the current mine plan (referred to as Kwale Phase 1 or “KP1†mine plan) and the outcomes of the KP2 DFS are outlined in the table below:
Description | KP2 DFS Mine Plan | KP1 Mine Plan |
Mining method | Three HMUs | DMU + one HMU |
Maximum mining rate | 2,400tph | 1,800tph |
Total tonnes mined (from April 2018) | 85.4 million tonnes | 85.4 million tonnes |
End of mine life (based on current Ore Reserves) | November 2022 | November 2024 |
WCP maximum spiral starts (currently 1,180) | 1,992 spiral starts | 1,360 spiral starts |
Capital cost estimate to increase to maximum mining rate (includes mining equip, WCP and tails upgrade and additional infrastructure) |
US$25.3 million | US$13.3 million |
Capital cost estimate to transition mining from Central Dune to South Dune | US$8.4 million | US$7.3 million |
Average full year production from July 2018 – Rutile | 93,000 tonnes | 68,000 tonnes |
Average full year production from July 2018 – Ilmenite | 414,000 tonnes | 307,000 tonnes |
Average full year production from July 2018 – Zircon | 34,000 tonnes | 25,000 tonnes |
The above average full year production forecasts are based on the following assumptions:
1. The Ore Reserves estimates underpinning the above production forecasts were prepared by Competent Persons in accordance with the JORC Code (2012 edition). The above production targets are the result of detailed studies based on the actual performance of the Kwale mine and processing plant. These studies include the assessment of mining, metallurgical, ore processing, environmental and economic factors.
A comparison of the forecast production profile of the KP1 and KP2 mine plans is shown in the graph below [omitted – refer to the full PDF version of this release available from the Company’s website].
Mining optimization
Mining at the Kwale Operations was originally based on a conventional dozer trap mining unit (“DMUâ€), using Caterpillar D11T dozers to feed the DMU. Historically, when mining the high-grade areas of the Kwale Central Dune, DMU mining rates of up to 1,400tph have been required to ensure the wet concentrator plant (“WCPâ€) is fully utilised. To offset the declining ore grades expected from mid-2018, the KP1 mine plan assumed an increase in the mining rate to 1,800tph. To achieve this higher mining rate, with the DMU alone, requires the addition of a third D11T dozer.
The KP2 pre-feasibility study determined that the optimal mining rate to maximise the economic returns of Kwale Operations was 2,400tph. The KP2 pre-feasibility study identified hydraulic mining as the preferred method to compliment the DMU to achieve the targeted 2,400tph mining rate. Operating dual mining units has the additional benefit of being able to concurrently mine both the high and low grade ore, which assists in smoothing the grade profile to create a more consistent feed to the WCP.
In August 2016, as part of the DFS, a 400tph hydraulic mining unit (“HMUâ€) was commissioned to trial the concept. The HMU has proven to be extremely well suited to mining Kwale ore, achieving higher availabilities and at lower unit operating costs than the DMU. Following the success of the HMU trial, the DFS concluded that the optimal mining setup for Kwale Operations was three HMUs mining at an average rate of 800tph each to give a combined total of 2,400tph.
A comparison of the mining profile of the KP1 and KP2 mine plans is shown in the graph below [omitted – refer to the full PDF version of this release available from the Company’s website].
Wet concentrator plant upgrade
At the lower ore feed grades and higher mining rates anticipated from mid-2018, the WCP must be upgraded to maintain optimal heavy mineral recoveries. A comprehensive pilot plant program and spiral modelling work undertaken by mineral sands industry specialist consultants, Mineral Technologies, was employed to determine the optimal equipment configuration for different mining rates and ore grades. The modelling established that an increase in the number of spirals is required to accommodate the mining rates contemplated under the KP1 (15% increase) and KP2 (69% increase) mining plans. In addition, modifications and equipment upgrades are required to the primary screens, feed de-sliming circuit, tailings cyclones, various pumps and piping. Other than increasing the capacity of the overflow pipework, tests confirm the capability of the two existing thickeners to manage the increased solids loading at the higher KP2 mining rate.
Changes to the WCP process flow sheet are minimal. No changes are required to the MSP.
Infrastructure requirements
Existing off-site and on-site infrastructure is sufficient to support operations under the KP2 mine plan, with the exception of the water supply infrastructure. The water supply constraints of the KP2 mine plan are largely the product of the daily extraction limits from the Mukurumudzi Dam imposed by licence conditions. To overcome this constraint, the existing Gongoni borefield will be expanded and a further borefield constructed near the tailings storage facility (“TSFâ€), both of which are fully permitted.
The cost to develop the TSF borefield is included in the KP2 capital estimate. However, the decision to develop this infrastructure will be subject to further assessment following recently implemented water saving initiatives.
Project execution and timeline
The KP2 project will be executed on an owner-implementation basis, as the Company has the requisite internal capability to do so, realising significant cost savings on EPCM indirect costs and contractor installation costs.
Front end engineering and design (“FEEDâ€) is currently underway and scheduled for completion by the end of June 2017. Whilst the FEED is in progress, the main mechanical, structural and piping contract will be awarded, based on the comprehensive tenders received during the DFS, and long lead items ordered.
Construction is scheduled for completion in the June quarter of 2018 after a one month shut of the WCP to tie in the plant modifications and equipment upgrades. Ahead of the WCP shut, heavy mineral concentrate stock levels will be managed to ensure that MSP production continues without interruption.
The implementation schedule will see the second of the 800tph HMU units commissioned in the June quarter of 2018, with the third commissioned in mid-2018. The three HMUs will ramp up to full capacity (2,400tph) through the course of 2018, with the DMU gradually being phased out over the same period.
Engineering and design work for the transition of mining from the Central Dune to the South Dune will commence in mid-2018, with construction completion scheduled for the second half of 2019.
Capital cost estimate
The estimated capital cost to complete the transition from the Central Dune to the South Dune and implement KP2 is US$33.7 million, US$13.1 million more than the estimated capital required for KP1. A breakdown of capital cost estimate by area of expenditure for both KP1 and KP2 is shown below (in US Dollars):
Area | KP2 | KP1 | Variance |
Mining operations (KP2: 3 x HMUs less sale of D11Ts and DMU; KP1: mobile equipment) |
$0.9m | $2.7m | -$1.8m |
Wet concentrator plant (plant modifications and equipment upgrades, incl. additional spirals) |
$10.5m | $3.0m | $7.5m |
Field services (additional water and tailings pumping systems and piping) |
$7.4m | $4.5m | $2.9m |
Indirect costs (EPCM labour and expenses) |
$3.3m | $1.0m | $2.3m |
Contingency | $3.2m | $2.1m | $1.1m |
Total capital cost estimate to implement KP2 | $25.3m | $13.3m | $12.0m |
Mining transition from Central Dune to the South Dune (including contingency) |
$8.4m | $7.3m | $1.1m |
Total capital cost estimate | $33.7m | $20.6m | $13.1m |
Anticipated timing of KP2 capital expenditure is shown below (in US Dollars):
FY17 | FY18 | FY19 | FY20 | Total |
$1.1m | $24.0m | $4.1m | $4.5m | $33.7m |
The capital cost will be fully funded from operating cashflows.
Community and environment
Implementation of KP2 is not expected to impact the community to a greater extent than the current operations. The impact of current mining operations on the community primarily relate to household resettlement required at the southern end of the South Dune and temporary relocation for households close to the mining lease boundary north of the Central Dune.
The main environmental impact from implementation of the KP2 mine plan is increased water demand, which will require enhanced groundwater monitoring. The Mine Site Environmental and Social Management Plan and Water Resources Environmental and Social Management Plan will be reviewed and revised as required, with mitigation controls implemented and monitored. Aside from the increased water demand, no other significant environmental impact is expected from implementation of KP2.
Forward Looking Statements
Information in this report should be read in conjunction with other announcements made by Base Resources. No representation or warranty, express or implied, is made as to the fairness, accuracy or completeness of the information contained in this report (or any associated presentation, information or matters). To the maximum extent permitted by law, Base Resources and its related bodies corporate and affiliates, and their respective directors, officers, employees, agents and advisers, disclaim any liability (including, without limitation, any liability arising from fault, negligence or negligent misstatement) for any direct or indirect loss or damage arising from any use or reliance on this report or its contents, including any error or omission from, or otherwise in connection with, it.
Certain statements in or in connection with this report contain or comprise forward looking statements. By their nature, forward looking statements involve risk and uncertainty because they relate to events and depend on circumstances that will occur in the future and may be outside Base Resources’ control. Accordingly, results could differ materially from those set out in the forward-looking statements.
Nothing in this report constitutes investment, legal or other advice. You must not act on the basis of any matter contained in this report, but must make your own independent investigation and assessment of Base Resources and obtain any professional advice you require before making any investment decision based on your investment objectives and financial circumstances. This document does not constitute an offer, invitation, solicitation, advice or recommendation with respect to the issue, purchase or sale of any security in any jurisdiction.
ENDS.
CORPORATE PROFILE
Directors
Keith Spence (Non-Executive Chairman)
Tim Carstens (Managing Director)
Colin Bwye (Executive Director)
Sam Willis (Non-Executive Director)
Michael Anderson (Non-Executive Director)
Michael Stirzaker (Non-Executive Director)
Malcolm Macpherson (Non-Executive Director)
Company Secretary
Chadwick Poletti
NOMINATED ADVISOR & BROKERS
RFC Ambrian Limited
As Nominated Adviser:
Andrew Thomson / Stephen Allen
Phone: +61 (0)8 9480 2500
As Joint Broker:
Jonathan Williams
Phone: +44 20 3440 6800
Numis Securities Limited
As Joint Broker:
John Prior / James Black / Paul Gillam
Phone: +44 20 7260 1000
SHARE REGISTRY: ASX
Computershare Investor Services Pty Limited
Level 11, 172 St Georges Terrace
PERTH WA 6000
Enquiries: 1300 850 505 / +61 (3) 9415 4000
www.computershare.com.au
SHARE REGISTRY: AIM
Computershare Investor Services PLC
The Pavilions
Bridgwater Road
BRISTOL BS99 6ZZ
Enquiries: +44 (0) 870 702 0003
www.computershare.co.uk
AUSTRALIAN MEDIA RELATIONS
Cannings Purple
Annette Ellis / Andrew Rowell
Email:aellis@canningspurple.com.au /
arowell@canningspurple.com.au
Phone: +61 (0)8 6314 6300
UK MEDIA RELATIONS
Tavistock Communications
Jos Simson / Emily Fenton
Phone: +44 (0) 207 920 3150
KENYA MEDIA RELATIONS
Africapractice (East Africa)
Evelyn Njoroge / James Njuguna/Joan Kimani
Phone: +254 (0)20 239 6899
Email:jkimani@africapractice.com
PRINCIPAL & REGISTERED OFFICE
Level 1, 50 Kings Park Road
West Perth, Western Australia, 6005
Email: info@baseresources.com.au
Phone: +61 (0)8 9413 7400
Fax: +61 (0)8 9322 8912