Quarterly Activities Report

ASX, AIM and Media Release 7 April 2014 Quarterly Activities Report March 2014 HIGHLIGHTS: * Maiden shipment of 25,000 tonnes of ilmenite departed port in February bound for China. * First product sales proceeds were received in March. * Zircon production through the mineral separation plant commenced in February with containerized zircon sales commencing in April. * Fifth and final US$25 million drawdown on the Kwale Project Debt Facility completed in January. * The Kwale Project has now made the transition to the Kwale Operations. Base Resources Limited (ASX & AIM: BSE) ("Base") ("Base" or the "Company") is pleased to provide a quarterly production and commissioning update at its Kwale Mineral Sands Operations ("Kwale Operations") in Kenya, East Africa. All work packages are now complete and operational with only minor defect list items remaining outstanding. The shiploader successfully underwent `load on' commissioning during the quarter and regular bulk shipments of finished products have commenced. KWALE OPERATIONS Following the commissioning of the ilmenite and rutile circuits of the mineral separation plant ("MSP") in December 2013, first production from the zircon circuit occurred in February. The main focus is now on balancing and debottlenecking the zircon circuit as well as the metallurgical optimisation of the remaining MSP circuits in order to progress the ramp-up to achieve design throughput, recoveries, availability and runtime. Mining activities proceeded according to plan with a number of dry mining unit ("DMU") moves successfully carried out. Mining rates increased steadily averaging over 1,200tph with nameplate tonnages being demonstrated. Valuable heavy mineral ("VHM") recovery in the wet concentrator is nearing design performance. Heavy mineral concentrate ("HMC") production was in line with ramp up expectations and the grade of ore mined. Slime and sand deposition proceeded according to plan and sealing of the upstream sand wall face of the tailings storage facility with bitumen impregnated geotextile commenced. MSP commissioning proceeded well and by the end of the quarter debottlenecking of the ilmenite and rutile circuits was virtually complete. Design ilmenite recoveries have been achieved and by the end of the quarter rutile recoveries were steadily improving with the implementation of some design modifications. Further planned design modifications, seeking to address the remaining identified areas of recovery losses, are currently underway and are expected to result in achievement of design rutile recoveries over the coming months. The wet and dry zircon circuits were commissioned during February and optimisation of throughput and recovery is in progress. A focus on debottlenecking and defect rectification, prior to the EPCM engineer demobilising from site at quarter end, meant that zircon production was sacrificed in the short term. With the areas of concern now addressed, our efforts are now concentrated on ramping up the zircon circuits and optimising production which, due to the complexity of these circuits, will take place over the next 12 months as planned. The Likoni Port bulk loading facility was successfully commissioned with two ships loaded during the quarter and the first shipment of containerised zircon was despatched to Mombasa Port. SUMMARY PHYSICAL DATA Oct-13 Nov-13 Dec-13 Q4-13 Jan-14 Feb-14 Mar-14 Q1-14 Total Total Ore mined (dmt) 105,304 275,315 451,373 831,992 583,928 661,725 695,298 1,940,951 HMC produced(dmt) 4,080 10,163 28,229 42,472 28,746 42,998 41,452 113,196 Production (dmt) Ilmenite 0 0 5,539 5,539 15,686 24,872 27,635 68,193 Rutile 0 0 152 152 1,969 2,902 3,972 8,843 Zircon 0 0 0 0 0 37 319 356 Sales (dmt) Ilmenite 0 0 0 0 0 25,300 22,000 47,300 Rutile 0 0 0 0 0 0 0 0 Zircon 0 0 0 0 0 0 0 0 SAFETY PERFORMANCE Kwale Operations suffered its first Lost Time Injury (LTI) when a trainee operator suffered a hand injury in a conveyor incident. The injury was non-life threatening and the employee is back at work on alternate duties. The incident investigation recommended a number of corrective actions, including design changes, which have been fully implemented. COMMUNITY AND ENVIRONMENT Rehabilitation of construction areas following contractor demobilisation is ongoing, with successful revegetation and indigenous tree planting continuing to take place across all areas. Road safety remains an important feature of our community sensitisation programme and 37 schools were visited along the transport corridor to discuss the hazards, with an emphasis on heavy vehicles including Base's mineral haul trucks. Plans are well advanced with respect to the preliminary agricultural trials for a series of projects being conducted in conjunction with Business for Millennium Development aimed at significantly improving agricultural livelihoods in the region. Several community construction programmes have been completed in the quarter including a training centre in Bwiti, emergency repairs to Matuga Girls Secondary School, construction of new ablution facilities for Mwapala Primary School and work commenced on replacing a Likoni primary school roof blown off by high winds. Base's collaboration with Little Sports Organisation in providing after school sports to primary school children has shown very positive results. This programme has recently expanded from 6 schools to 11 schools in nearby communities and is focussed on teaching life skills through play and sports activities. BUDGET The estimated cost at completion for the Kwale Project remains at US$310 million. FINANCING In January, the additional US$25 million project finance facility executed in December 2013 was drawn, bringing the total debt facilities drawn to US$215 million. MARKETING Base completed two bulk shipments of ilmenite during the March quarter (a total of 47,300 tonnes) and have vessels booked for three further bulk ilmenite shipments during April and May. A bulk shipment of rutile and a container shipment of zircon were previously scheduled for the latter part of March but vessel availability has resulted in the bookings for these shipments falling into the early part of April. Reports from major pigment producers indicate continued improvement in pigment demand, with inventory levels and plant utilisation rates normalising in the early part of 2014. Producer inventory of titanium dioxide feedstock remains at elevated levels which is maintaining pressure on feedstock prices. However, as the excess inventory position is run down, the pricing position of titanium dioxide feedstock is expected to improve. Recent industry results commentary points towards possible feedstock price improvement (including rutile and ilmenite) during the second half of 2014. Demand for zircon has remained firm through the March quarter with reports of good trade activity. Stocks of zircon held by producers continued to be run down and prices stabilised through the March quarter with some major zircon producers increasing their offered pricing for zircon sales in the June quarter. CORPORATE In summary, at 31 March 2014: • Cash and cash equivalents were A$27.8 million. • Debt drawn of US$215.0 million. • 561,840,029 shares on issue. • 16,600,000 unlisted options. A full PDF version of the announcement is available at the Company's website: www.baseresources.com.au. ENDS For further enquiries contact: Base Resources Limited Tim Carstens Managing Director Email: tcarstens@baseresources.com.au Phone: +61 (0)8 9413 7400 RFC Ambrian Limited (Nominated Adviser and Broker) As Nominated Adviser As Broker Andrew Thomson or Trinity McIntyre Jonathan Williams Phone: +61 (0)8 9480 2500 Phone: +44 20 3440 6800 Africapractice (East Africa) (Kenyan Media Relations) David Maingi/ James Njuguna/Joan Kimani Phone: +254 (0)20 239 6899 Email: jkimani@africapractice.com Tavistock Communications (UK Media Relations) Jos Simson / Emily Fenton / Nuala Gallagher Phone: +44 (0) 207 920 3150 Cannings Purple (Australian Media Relations) Annette Ellis / Warrick Hazeldine Email: aellis@canningspurple.com.au whazeldine@canningspurple.com.au Phone: +61 (0)8 6314 6300 TENEMENT SCHEDULE: Tenement Number Interest Location Special Mining Licence 23 100% Kwale - Kenya Exploration Licence 173 100% Kwale North - Kenya CORPORATE DETAILS Board of Directors: Andrew King Non-Executive Chairman Tim Carstens Managing Director Colin Bwye Executive Director Sam Willis Non-Executive Director Michael Anderson Non-Executive Director Trevor Schultz Non-Executive Director Michael Macpherson Non-Executive Director Winton Willesee Company Secretary Principal & Registered Office: Contacts: Level 1 Email: info@baseresources.com.au 50 Kings Park Road Phone: +61 (0)8 9413 7400 West Perth Fax: +61 (0)8 9322 8912 WA 6005
UK 100

Latest directors dealings