Pan African Resources PLC
("Pan African" or “the company" or “the groupâ€)
(Incorporated and registered in England and Wales under Companies Act 1985 with registered number 3937466 on 25 February 2000)
Share code on AIM: PAF
Share code on JSE: PAN
ISIN: GB0004300496
OPERATIONAL UPDATE FOR THE SIX MONTHS ENDED 31 DECEMBER 2018
Pan African is pleased to provide an operational update for the six months ended 31 December 2018 (“current reporting periodâ€).
Key highlights for the current reporting period
Pan African has made good progress in repositioning the group as a long-life, low cost and focused gold producer.
Gold production from the group’s continuing mining operations (note 1) increased by 54.2% to 81,014oz (2017: 52,548oz), with robust operational performances from Barberton Mines’ underground operations and also from the group’s tailings retreatment plants.
Gold production from the Barberton complex significantly increased by 24.5% to 50,556oz (2017: 40,611oz); and
The new Elikhulu tailings retreatment plant (“Elikhuluâ€) contributed 15,292oz (2017: nil) of incremental low-cost ounces. Elikhulu reached nameplate throughput capacity in October 2018 and its optimisation is continuing.
The group’s continuing focus on safety and ongoing safety improvements yielded encouraging results, with material improvements in safety statistics during the current reporting period.
The improved production performance, curtailment of large scale underground mining operations at Evander Mines and the contribution of incremental low-cost ounces from Elikhulu has resulted in a marked reduction in the group’s all-in sustaining cost of production. Further detail on costs will be provided as part of the 31 December 2018 interim results.
Barberton’s three year wage agreement is expected to assist with stability at the operation in the coming years.
Note 1: The continuing mining operations include: Barberton Mines’ operations, Evander Mines’ Elikhulu and Evander tailings retreatment plant (“ETRPâ€) as well as the mining and vamping of the remnant high grade stopes as part of the phased closure of the underground mining operation. The continuing mining operations excludes the discontinued Evander Mines’ large-scale underground mining operation, which produced 32,734oz in the corresponding six months period ended 31 December 2017 (“corresponding reporting periodâ€). The group’s corresponding reporting period gold production including discontinued operations was 85,282oz.
Pan African CEO Cobus Loots commented:
“The operational and safety performance during the current reporting period demonstrates the progress in repositioning our group as a low-cost, long-life producer, with the safety of our employees and contractors always being of paramount importance. We are very pleased with the commissioning of Elikhulu during the period under review, notwithstanding the challenges associated with delivering a project of this magnitude and complexity on time and within budget. We now look forward to Elikhulu’s growing contribution to the group’s results in forthcoming reporting periods.
In the period ahead, management will continue to focus on further improving our mining operations. The group remains on track to produce 170,000oz for the full financial year to 30 June 2019.
As previously communicated, the drilling programme on Barberton Mines’ Royal Sheba prospect was completed, indicating a near surface mineral resource of 0.37Moz with a 900m strike and 150m down dip extension. The total mineral resource is now 0.76Moz (8.97Mt at 2.62g/t) comprising the near surface resource of 0.37Moz (5.85Mt at 1.96g/t) and the underground mineral resource of 0.39Moz (3.12Mt at 3.87g/t).
We have a demonstrable record of replenishing our mineral resources through effective exploration and look to organic growth projects, such as Royal Sheba, to further enhance the sustainability of the group’s operations and to continue to deliver attractive returns to all our stakeholders.â€
Safety
The group has significantly improved its safety performance in the current reporting period. We remain committed to ensuring the safety of all our employees, while we continue to strive towards a zero harm environment.
The group suffered no fatalities during the current and corresponding reporting periods
The group’s lost-time injury frequency rate improved significantly to 1.77 (2017: 4.05)
The reportable injury frequency rate improved to 0.53 (2017: 0.62)
Fairview Mine achieved its one-million fatality-free shift milestone on 15 July 2018
Elikhulu
As previously communicated, Elikhulu was successfully commissioned ahead of schedule and within budget, and achieved a throughput of 1-million tonnes per month during October 2018.
The incorporation of the existing ETRP throughput capacity of 0.2 million tonnes per month into Elikhulu was completed in December 2018, which increased Elikhulu’s processing capacity to 1.2-million tonnes per month.
Elikhulu processed 3,534,278 tonnes in the four months from September 2018 to December 2018 at a recovered grade of 0.135g/t with 15,291oz (475.6kg) of gold sold, not accounting for August 2018 pre-production gold capitalised of 22.9kg (736oz) and gold inventory held in the Elikhulu circuit.
Optimisation of the enlarged Elikhulu is continuing, with throughput of 1.1 million tonnes expected in January 2019 and the full 1.2 million tonnes of throughput expected from February 2019.
Barberton Mines
Barberton Mines produced 50,556oz (2017: 40,611oz) during the current reporting period, comprising:
Underground mining operations which contributed 38,550oz (2017: 32,159oz); and
Barberton tailings retreatment plant (“BTRPâ€) which contributed 12,006oz (2017: 8,452oz).
Barberton Mines produced 100,574oz during the 2018 calendar year and remains on track to achieve the market guidance of approximately 100,000oz for the full 2019 financial year.
Barberton Mines’ period-on-period increase in production benefitted from:
Increased underground mining flexibility at both the Fairview Mine high-grade 272 and 358 platforms; and
BTRP production increased significantly due to improved tonnages and recoveries, following the successful commissioning of the BTRP regrind mill during May 2018.
Barberton Mines successfully concluded a three-year wage agreement during September 2018 with no industrial action.
Evander Mines
Evander Mines’ surface operations and the mining and vamping of the remnant high-grade stopes produced 15,166oz (2017: 11,937oz) and positively contributed to the group’s earnings before interest, taxation, depreciation, and amortisation during the current reporting period.
The feasibility study into the merits of mining the 8 Shaft pillar and high-grade areas in proximity to the pillar will be completed by the end of February 2019, after which a decision will be made on whether to commence mining in these areas.
The financial and other information contained in this announcement has neither been reviewed nor audited by the company’s external auditors. The group’s unaudited interim results for the current reporting period will be released on 20 February 2019.
For further information on Pan African, please visit the company’s website at www.panafricanresources.com.
Rosebank
25 January 2019
Contact information | |
Corporate Office The Firs Office Building 2nd Floor, Office 204 Cnr. Cradock and Biermann Avenues Rosebank, Johannesburg South Africa Office: + 27 (0) 11 243 2900 Facsimile: + 27 (0) 11 880 1240 |
Registered Office Suite 31 Second Floor 107 Cheapside London EC2V 6DN United Kingdom Office: + 44 (0) 207 796 8644 Facsimile: + 44 (0) 207 796 8645 |
Cobus Loots Pan African Resources PLC Chief Executive Officer Office: + 27 (0) 11 243 2900 |
Deon Louw Pan African Resources PLC Financial Director Office: + 27 (0) 11 243 2900 |
Phil Dexter St James's Corporate Services Limited Company Secretary Office: + 44 (0) 207 796 8644 |
John Prior/Paul Gillam Numis Securities Limited Nominated Adviser and Joint Broker Office: +44 (0) 20 7260 1000 |
Marian Gaylard Questco Corporate Advisory (Proprietary) Limited JSE Sponsor Office: + 27 (0) 11 011 9200 |
Ross Allister/James Bavister/David McKeown Peel Hunt LLP Joint Broker Office: +44 (0) 207 418 8900 |
Julian Gwillim Aprio Strategic Communications Public & Investor Relations SA Office: +27 (0)11 880 0037 |
Jeffrey Couch/ Thomas Rider/ Neil Elliot BMO Capital Markets Limited Joint Broker Office: +44 (0) 207 236 1010 |
Bobby Morse and Chris Judd Buchanan Public & Investor Relations UK Office: +44 (0)20 7466 5000 paf@buchanan.uk.com |
Website: www.panafricanresources.com |