Pan African Resources PLC
(Incorporated and registered in England and Wales under Companies Act 1985 with registered number 3937466 on 25 February 2000)
Share code on AIM: PAF
Share code on JSE: PAN
ISIN: GB0004300496
ADR ticker code: PAFRY
(Pan African or the Company or the Group)
OPERATIONAL AND GROWTH PROJECTS UPDATE
Pan African is pleased to provide shareholders with an update on the Company’s operations and growth projects.
HIGHLIGHTS
Pan African CEO Cobus Loots commented:
“ We are pleased with the robust operational performance for the year to date, and that we again expect to exceed our original full year production guidance.
We are encouraged by the outcome of the recently completed concept study for the Mintails Transaction, which confirms our initial assessment of the asset’s potential. Our team is now focussed on completing the pre-feasibility study early in our next financial year.
The Evander 8 Shaft pillar project is now performing in line with our expectations, and generating the anticipated returns on this capital investment.
We have re-evaluated our capital expenditure priorities following the receipt of the positive Mintails concept study and the 24 Level project study, resulting in a more phased approach for the development of the Egoli project. This approach will extend the life of Evander 8 shaft and reduce our reliance on debt funding for Egoli’s development, enabling the Group to maximise the value of our assets and also returns to our shareholder.
The successful completion of the Evander Solar Plant in the next months will pave the way for further renewable energy initiatives, so as to further reduce our carbon footprint and further increase operating margins”
INCREASED PRODUCTION GUIDANCE FOR 2021 FINANCIAL YEAR
The Group now expects to produce ca. 195,000oz for the 2021 financial year, representing an increase of 5,000oz relative to the previous production guidance of 190,000oz.
Based on current planning, the Group expects to maintain similar production levels for the 2022 financial year.
COVID-19 UPDATE
The Group remains vigilant in its efforts to prevent and mitigate the impact of the COVID-19 virus on its people and operations. It continues to diligently implement operating procedures and protocols and to monitor the impact of COVID-19 on our operations and surrounding communities.
UPDATE ON GROWTH PROJECTS
Mintails Transaction
1. Transaction background and rationale
As announced on 6 November 2020, Pan African entered into conditional sale-of-shares agreements (Sale Agreements) to acquire the total share capital and associated shareholder loans and other claims of Mogale Gold Proprietary Limited (Mogale Gold) and Mintails SA Soweto Cluster Proprietary Limited (MSC), collectively Mintails SA.
2. Initial fatal flaw analysis and concept study update
In January 2021, Pan African commissioned DRA Global to complete a fatal flaw analysis on Mintails SA’s assets to be acquired which identified no fatal flaws on either the Mogale Gold or MSC assets.
Following the positive findings of the fatal flaw analysis, a concept study was conducted on the Mogale Gold assets, including a high-level financial evaluation. This study indicated an optimal tailing throughput feed of ca. 800,000 tonnes per month, with anticipated recoveries of ca. 53%. The anticipated upfront capital required of ca. ZAR1 000 million and ZAR1,700 million capital over the LoM will be confirmed during the next stage of the project planning.
The concept study did, however, identify areas that would require further evaluation during the pre-feasibility stage of the project, including:
Key inputs used in the concept study’s financial evaluation include:
*Real after-tax internal rate of return
?3. Future development
Pan African and its subsidiaries have a proven track record of successfully commissioning and operating tailings retreatment projects, as demonstrated by the Barberton tailings re-treatment plant, the Evander tailings re-treatment plant and most recently its flagship Elikhulu operation.
A pre-feasibility study will be completed during the third quarter of the 2021 calendar year, and, if positive, will be progressed to a definitive feasibility study, expected to be completed during the first quarter of the 2022 calendar year.
Evander Mines underground strategy
8 Shaft pillar
Following technical challenges experienced during the initial phases of the 8 Shaft pillar mining, production levels anticipated in the original feasibility study have now been achieved. This operation is expected to produce an average of 34,000 oz per year over its remaining LoM of two years and five months, measured from end of the 2021 financial year.
The Group reassesses the respective merits of its growth opportunities and its capital expenditure priorities on an ongoing basis. This process, together with the early-stage attraction of the Mintails Transaction, has resulted in the reappraisal of the current Egoli project development plan, as well as a re-evaluation of existing underground mining opportunities at Evander Mines’ 24 level.
This capital expenditure reprioritisation is expected to result in improved cash returns and will require a substantially reduced capital outlay and commensurate reduced debt levels, when compared to the previous Egoli development plan.
The table below details the available Mineral Reserves and Resources as at 30 June 2020 (prepared in accordance with SAMREC Code), accessible through existing 8 Shaft infrastructure, at Evander’s Underground operations.
Category | Tonnes | Grade (g/t) | Gold (kg) | Gold (oz) |
Evander 8 Shaft Pillar | ||||
Proved Mineral Reserves | 342 068 | 9.83 | 3 362 | 108 000 |
Phase 1 (Evander 8 Shaft 24 level) | ||||
Measured Mineral Resources* | 301 788 | 10.46 | 3 158 | 101 523 |
(Possible Phase 2) (Evander 8 Shaft 25-26 level) | ||||
Measured Mineral Resources | 759 781 | 11.99 | 9 110 | 292 878 |
Indicated Mineral Resources | 698 700 | 12.63 | 8 827 | 283 790 |
Inferred Mineral Resources | 328 950 | 12.93 | 4 252 | 136 715 |
Egoli Project | ||||
Proved Mineral Reserves | 447 163 | 5.90 | 2 640 | 85 000 |
Probable Mineral Reserves | 2 987 864 | 6.72 | 20 076 | 645 000 |
Total Mineral Inventory | 5 866 315 | 8.77 | 51 424 | 1 652 907 |
*The Phase 1 Mineral Resources can be converted to a Proved Mineral Reserve at 30 June 2021.
8 Shaft decline
Following the cessation of deep level underground mining at Evander during May 2018, after a decline in the Rand gold price at the time, the Group has continued to maintain the infrastructure’s integrity, to preserve the mineral resources, and conduct limited vamping operations.
As part of its medium-term capital deployment strategy, an internal technical and economic study, to assess merits of mining the number 2 decline on 24 Level project (Phase-1). This study will be followed by a Phase-2 study that will assess the merits of extending mining to 25 and 26 levels. Phase-2 will also be designed to utilise a proven on-reef mining layout, minimising waste and significantly reducing the time for ore body access development.
Phase-1 mining will extend Evander’ 8 shaft production profile, post cessation of the 8 Shaft pillar mining, for an additional two and a half years and maintain annual production of approximately 34,000oz per year. The 24 Level project will result in a five-year life for the Evander 8 Shaft complex.
An integral component of the Phase-1 study was the identification of risk mitigating measures to address the major challenges previously encountered during the mining of the Kinross orebody and ensure economical extraction.
The principal challenges identified and the planned mitigation measures are outlined below:
Factors | Prior to 2018 curtailment of operations | Current Study mitigation measures |
Low efficiencies | High temperatures due to inadequate refrigeration capacity | Installation of a new refrigeration plant at a capital investment of approximately ZAR170 million. |
Ore and waste separation | Waste was previously hoisted to surface | Underground waste handling and storage facilities are to be installed at a capital investment of approximately ZAR60 million |
Face time | Limited face time due to excessive underground travelling distances | Installation of a man carriage on 24 level |
Labour intensive ore handling infrastructure | Production requirements entailed three shifts to operate on a continuous basis | Reduced tonnage profile requires only one shift to be manned to meet planned production targets |
Key inputs used in the internal technical and financial assessment include:
*Real after-tax internal rate of return
Egoli Project (Egoli)
Following the reprioritisation of the Group’s capital expenditure programmes, a more phased approach for the development of the Egoli Project will be followed, concurrent with the 8 Shaft Phase-1 and possible Phase-2 developments at 24, 25 and 26 level, as described above.
Egoli’s first phase development will entail the dewatering of the number 3 decline infrastructure to 19 level, where a drilling platform will be established to enable infill drilling, in order to finalise short-term mine planning.
The Egoli project’s phased development approach and production profile will coincide with the depletion of the 24 Level mineral resources.
EVANDER MINES’ SOLAR PHOTOVOLTAIC PLANT
During the first calendar quarter of 2021, the Group contracted with juwi Renewable Energies Proprietary Limited, to construct a 9,975MW solar photovoltaic plant at Evander Mines. Civil works and the procurement of major components have commenced and commissioning is anticipated in the third calendar quarter of 2021.
The solar photovoltaic plant will provide an estimated 30% of Elikhulu’s power requirements, resulting in a reduction of fossil fuel-generated power and an expected annual CO2 saving of more than 26,000t in the first full year of operation. A feasibility study for a similar solar photovoltaic plant at Barberton Mines is currently being undertaken as well as expanding the Evander plant currently being constructed to meet the Evander underground power requirements and to reduce the escalating cost of electricity.
COMPETENT PERSON
The competent person for Pan African Resources, Hendrik Pretorius, the manager for group mineral resource management, signs off the Mineral Resources and Mineral Reserves for the Group. He is a member of the South African Council for Natural Scientific Professions (SACNASP 400051/11 – Management Enterprise Building, Mark Shuttleworth Street, Innovation Hub, Pretoria, Gauteng Province, South Africa), as well as a member in good standing of the Geological Society of South Africa (GSSA – CSIR Mining Precinct, Corner Rustenburg and Carlow Roads, Melville, Gauteng Province, South Africa). Hendrik has 17 years' experience in economic geology and mineral resource management (MRM). He is based at The Firs Office Building, 2nd Floor, Office 204, Corner Cradock and Biermann Avenues, Rosebank, Johannesburg, South Africa. He holds a BSc (Hons) degree in Geology from the University of Johannesburg as well as a Graduate Diploma in Mining Engineering from the University of the Witwatersrand. Hendrik has reviewed, and approved, in writing the information contained in this document as it pertains to Mineral Resources and Mineral Reserves.
For more detail on the reported Mineral Resources and Mineral Reserves, the FY2020 annual Mineral Resource and Mineral Reserve Report is published on our website www.panafricanresources.com
The information contained in this update is the responsibility of the Pan African board of directors and has not been reviewed or reported on by the Group’s external auditors.
Rosebank
21 May 2021
This announcement contains inside information.
For further information on Pan African and its ESG initiatives, please visit the Company's website at www.panafricanresources.com
Contact information | |
Corporate Office The Firs Office Building 2nd Floor, Office 204 Cnr. Cradock and Biermann Avenues Rosebank, Johannesburg South Africa Office: + 27 (0)11 243 2900 info@paf.co.za |
Registered Office Suite 31 Second Floor 107 Cheapside London EC2V 6DN United Kingdom Office: + 44 (0)20 7796 8644 |
Cobus Loots Pan African Resources PLC Chief Executive Officer Office: + 27 (0)11 243 2900 |
Deon Louw Pan African Resources PLC Financial Director Office: + 27 (0)11 243 2900 |
Phil Dexter/Jane Kirton St James's Corporate Services Limited Company Secretary Office: + 44 (0)20 7796 8644 |
Ross Allister/David McKeown Peel Hunt LLP Nominated Adviser and Joint Broker Office: +44 (0)20 7418 8900 |
Ciska Kloppers Questco Corporate Advisory Proprietary Limited JSE Sponsor Office: + 27 (0)11 011 9200 |
Thomas Rider/ Nick Macann BMO Capital Markets Limited Joint Broker Office: +44 (0)20 7236 1010 |
Hethen Hira Pan African Resources PLC Head: Investor Relations Tel: + 27 (0)11 243 2900 E-mail: hhira@paf.co.za |
Website: www.panafricanresources.com |