Pan African Resources PLC (Incorporated and registered in England and Wales under the Companies Act 1985 with registered number 3937466 on 25 February 2000) Share code on AIM: PAF Share code on JSE: PAN ISIN: GB0004300496 ADR ticker code: PAFRY (“Pan African” or the “Company” or the “Group”)
| Pan African Resources Funding Company Limited Incorporated in the Republic of South Africa with limited liability Registration number: 2012/021237/06 Alpha code: PARI
|
REVISED PRODUCTION GUIDANCE FOR THE YEAR ENDING 30 JUNE 2023, OPERATIONAL UPDATE AND COMMENCEMENT OF MINTAILS PROJECT CONSTRUCTION
Pan African wishes to provide shareholders and noteholders with revised production guidance and an operational update for the financial year ending 30 June 2023 (current financial year). It is also pleased to announce the imminent commencement of the Mintails project’s construction, with site clearance activities having commenced.
Group production guidance
Safety performance
Electricity supply
Barberton Mines
Evander Mines’ underground operations
Mintails project
Financial
Pan African CEO Cobus Loots commented:
“The safety of our people and contractors remains our number one priority and we continue to implement a number of programmes to further improve the safety performance at our operations. We are deeply saddened by the fatal accident that occurred at Evander Mines as a result of a fall of ground incident.
Whilst we are disappointed with the production performance of our underground operations for the current financial year, the turnaround at Barberton Mines is now evident, especially in the past two months, following a longer than anticipated ramp-up after the implementation of continuous operations at Fairview Mine and Sheba Mine and implementation of the contractor mining model at Consort Mine. Barberton Mines’ underground production tonnes have demonstrated a notable increase during the past two months, with further increases expected during the remainder of the current financial year. Implementation of the contractor mining model at Consort Mine is also bearing fruit and the operation is expected to return to profitability in the short term.
Pan African is leading the way in terms of rolling out renewable energy projects and reducing our dependency on Eskom. In the coming years, we believe this strategy will greatly benefit all of our stakeholders.
The development of the 24 Level project at Evander Mines is progressing well, with crews redeployed to the 24 Level area as the 8 Shaft pillar mining nears completion. Improved mining flexibility, together with the other initiatives being implemented to ensure that infrastructure availability is optimised, will ensure sustainable production from this long life underground operation.
Ground clearing at the Mintails project has commenced in anticipation of the senior debt component of the funding package being closed by June 2023. Commissioning of the plant is expected in the fourth quarter of the 2024 calendar year, which will result in a significant increase in the Group’s production profile from the 2025 financial year onwards.
Despite lower than expected production, the Group is positioned to deliver a robust financial performance for the current financial year as a result of the excellent rand gold prices being received and also disciplined operational cost control.
Pan African is committed in its resolve to continued value creation for its stakeholders by positioning the Group as a sustainable, safe, high-margin and long-life gold producer with an attractive pipeline of growth projects. We look forward to presenting our final results in September 2023, which will include further details on our operational and financial performance, as well as information on progress being made with our growth projects.”
Safety
As previously communicated, the Group has implemented initiatives during the second half of the 2023 financial year to further improve its safety performance.
Barberton Mines has seen a progressive improvement in safety performance for both lost-time injury frequency rate (LTIFR) and reportable injury frequency rate (RIFR), compared to the first half of the current financial year.
Despite the regrettable fatal accident, we remain confident that the safety performance at Evander Mines will improve as it continues to implement safety initiatives to reinforce a zero-tolerance approach towards safety incidents. Elikhulu operations have seen a slight regression in safety performance during the current financial year, resulting from two recorded contractor lost-time injuries.
The Group’s forecasted LTIFR and RIFR for the current financial year are expected to improve from the rates reported for the first half of the year.
Group production
Group production for the current financial year is expected to be approximately 175,000oz, split per operation as follows:
Operation | Year ended 30 June 2021 | Year ended 30 June 2022 | Guidance for current financial year | Guidance for 2024 financial year |
Barberton Mines – Underground total | 84,826 | 75,738 | 64,000 | 71,000 - 74,000 |
BTRP | 18,239 | 19,560 | 19,000 | 17,000 - 20,000 |
Elikhulu | 51,459 | 52,220 | 50,000 | 49,000 - 51,000 |
Evander Mines – Underground and surface sources | 47,253 | 58,170 | 42,000* | 41,000 - 45,000* |
| 201,777 | 205,688 |
| 178,000 - 190,000 |
* Includes gold equivalent PGM ounces produced by Evander Gold Mines’ Osmiridium circuit
Royal Sheba Project
Mine layout optimisation and scheduling was finalised and requests for quotations were issued for the initial development and production activities. Preliminary optimisation work for the life-of-mine (LOM) planning has been completed at a cut-off grade of 1.7g/t, which translates into an average mining grade of approximately 3.0g/t and circa 235,000oz of gold recovered over the life of the project, with the orebody open at depth.
DRA Global has finalised the feasibility study for placing a crushing and milling circuit at the Royal Sheba Mine site, together with the design to enable slurry pumping from the milling plant at Royal Sheba to the BTRP. The processing plant’s feasibility study and the project’s financial model is being updated and reviewed. A phased approach to capital spending, based on the availability of material to feed the BTRP plant, is also being considered. This will entail the phased development of the decline, production levels, as well as the ventilation infrastructure required for initial stoping operations.
First stoped ore is planned in 2025 at 5,000t per month, ramping up to 10,000t, 30,000t and 45,000t per month, every twelve months thereafter in line with a set lateral and vertical development schedule. A trucking cost trade-off analysis indicates that the onsite crushing and milling circuit and pipeline will only be required to be completed once production rates reach 45,000t per month. The internal feasibility study for the complete project is expected to be completed in the next months.
Evander Mines’ 8 Shaft pillar and 24, 25 and 26 Level and Egoli projects
The opening up of mining areas on 24 Level continues, which will enable the phased transfer of crews from the pillar area as mining of the pillar resource is completed. Two crews are currently mining the 24 Level F-line, with an additional two crews mining the 24 Level D-line. Construction of phase 2 of the refrigeration plant for cooling 24 Level is ongoing. The development of the 24_N1B drive towards 25 Level progressed slower than expected due to challenging ground conditions. As ground conditions progressively improved, development rates have now increased and multi-blasting is being considered to further accelerate development.
The equipping of the ventilation shaft to enable hoisting of waste and ore produced on 24 Level will reduce reliance on the ageing conveyor belt system and simplify the ore handling process. Installation of pipes for equipping the ventilation shaft at 17 Level has commenced, with the development of the winder chamber and shaft station ongoing. Completion of the ventilation shaft’s equipping is expected by the end of the first quarter of the 2024 calendar year and will provide a hoisting capacity of up to 40,000t per month. Additional crews have been deployed to the conveyor belts in order to improve maintenance and breakdown reaction times, which is expected to increase conveyor belt availability until such time that ore hoisting will commence through the ventilation shaft.
Construction of an additional grout plant (for pseudo-pack support) is expected to be completed in June 2023. This plant will supply 24 Level and future mining on 25 and 26 Levels with the required output for mining support. The use of pseudo-packs in the 8 Shaft pillar area has proven to be effective in controlling mining subsidence and enabling clean mining practices, and these benefits will also be replicated through the utilisation of pseudo-packs as mining support on the 24, 25 and 26 Level projects.
Dewatering of the 3 Decline infrastructure to 19 Level at the 7 Shaft Egoli project is progressing well. The completion of the dewatering is projected to take place in the next months, which will enable a more accurate assessment of potential mining of remnant areas within the Egoli complex.
Mintails project progress and funding
Progress on the Mintails project and expected milestones include:
A derivative funding structure was implemented during March 2023, to complete the funding package for the Mintails project. The structure provided a US$22.6 million (ZAR400 million) upfront premium which, together with the proceeds of US$47.3 million from the sustainability bond raised during December 2022 and the debt funding package of US$73.4 million in the form of a credit approved term loan facility underwritten by FirstRand Bank Limited, acting through its Rand Merchant Bank division, ensure that the project is fully funded at commencement of construction. Independent technical reviews of the project together with legal drafting are currently underway in anticipation of the debt funding package being closed by June 2023.
Blyvoor conditional acquisition - update
The due diligence and fulfilment of other conditions precedent for the acquisition of the Blyvoor Gold Operations Proprietary Limited historical TSFs was not completed within the required timeframe, and this transaction has therefore lapsed. Although the Group is currently focused on the construction of the Mintails Project, it continues to engage with the current owners of Blyvoor Gold Operations to evaluate options to further develop this project.
Sudan exploration project
Following the outbreak of violence in the Republic of Sudan, all expatriate employees working on the exploration project were safely repatriated. All of the Group’s assets situated in the Republic of Sudan, including the fire assay multi-element analytical laboratory, are currently guarded and have been placed under care and maintenance until such time as the situation stabilises and the Group can resume its exploration programme. The carrying value of the Group’s investment in the Sudan exploration project to date, including the acquisition of the exploration concessions and other assets, amounts to approximately US$5.0 million. Limited expenditure is currently being incurred on securing the Group’s assets and their care and maintenance, until such time as exploration activities can recommence.
The Group successfully commissioned the first commercial fire assay multi-element analytical laboratory within the Republic of Sudan during 2022. This laboratory is used to analyse all exploration samples extracted from the Block 12 exploration concessions granted to Pan African by the Sudan Ministry of Mines and any regional exploration work by other explorers.
Prior to the conflict, the exploration team active within Block 12A South and Block 12A North conducted soil geochemistry and hard rock chip sampling programmes to further define the identified exploration anomalies. Initial assaying received from the exploration targets identified in the south-eastern corner of Block 12A South averaged 1.7g/t from 12 samples taken from quartz veins, rock debris and soil. However, some of the structures sampled indicated significantly higher gold mineralisation, with values ranging from 2.9g/t up to 9.4g/t. These structures will be further defined as part of a confirmatory sampling programme. No Mineral Resources or Mineral Reserves are currently reported for any of the targets.
Remote sensing imagery in Block 12A North detected a notable additional NE-SW anomaly approximately 11km long. Initial field investigations identified a siliceous unit hosting significant iron oxide alteration, with reported grades of 7.3, 0.19, and 0.58 g/t. Further sampling along the strike and down-dip of the unit, as well as subsequent mapping, revealed a potential extension of several kilometres towards the southwest.
Pan African remains positive that the in-country situation will stabilise to the extent that it can resume exploration activities in the near future.
Final results for the twelve months ended 30 June 2023
Pan African anticipates announcing its final results for the current financial year on or about 13 September 2023.
The information contained in this update is the responsibility of the Pan African board of directors and has not been reviewed or reported on by the Group’s external auditors.
Certain information communicated in this announcement was, prior to its publication, inside information for the purposes of Article 7 of Regulation 596/2014.
Rosebank
26 May 2023
For further information on Pan African, please visit the Company's website at
Corporate information | |
Corporate office The Firs Office Building 2nd Floor, Office 204 Cnr. Cradock and Biermann Avenues Rosebank, Johannesburg South Africa Office: + 27 (0)11 243 2900 | Registered office 2nd Floor 107 Cheapside London EC2V 6DN United Kingdom Office: + 44 (0)20 7796 8644 |
Chief executive officer Cobus Loots Office: + 27 (0)11 243 2900 | Financial director Deon Louw Office: + 27 (0)11 243 2900 |
Head: Investor relations Hethen Hira | Website: www.panafricanresources.com |
Company secretary Jane Kirton St James's Corporate Services Limited Office: + 44 (0)20 7796 8644 | Nominated adviser and joint broker Ross Allister/David McKeown Peel Hunt LLP Office: +44 (0)20 7418 8900 |
JSE Sponsor and JSE debt sponsor Ciska Kloppers Questco Corporate Advisory Proprietary Limited Office: + 27 (0)11 011 9200 | Joint broker Thomas Rider/Nick Macann BMO Capital Markets Limited Office: +44 (0)20 7236 1010 |
| Joint broker Matthew Armitt/Jennifer Lee Joh. Berenberg, Gossler & Co KG Office: +44 (0)20 3207 7800 |