Pan African Resources PLC
(Incorporated and registered in England and Wales under the Companies Act 1985 with registered number 3937466 on 25 February 2000)
Share code on AIM: PAF
Share code on JSE: PAN
ISIN: GB0004300496
ADR ticker code: PAFRY
(“Pan African” or the “Company” or the “Group”)
PAN AFRICAN SUCCESSFULLY CONCLUDES MINTAILS’ MOGALE GOLD DEFINITIVE FEASIBILITY STUDY (“DFS”)
Pan African is pleased to announce that the Company has successfully completed a DFS on the Mogale Gold Proprietary Limited (“Mogale Gold”) Tailings Storage Facilities (“TSFs”) that forms part of the Mintails Mining SA (Proprietary) Limited (“Mintails SA”) assets, situated near Krugersdorp to the west of Johannesburg, South Africa (the “Project”). The DFS was prepared by DRA Projects SA (Pty) Ltd (“DRA”), with reliance on specialist input from third parties for Mineral Resource and Mineral Reserve estimation, dump re-mining, tailings pumping and disposal and metallurgical test work. The parties have provided their consent for the release of the information contained in this announcement as far as it pertains to the results of the DFS.
HIGHLIGHTS FROM DFS
Cobus Loots, CEO of Pan African, commented: “Pan African has an excellent track record of successfully commissioning and operating surface tailings retreatment operations, as evidenced by our BTRP, ETRP and Elikhulu operations. As originally anticipated, the Mogale Gold DFS has demonstrated a compelling Project, both operationally and financially. Mintails has the potential to further improve the Group’s overall AISC, while increased annual production will move Pan African further up the ranks of mid-tier gold producers.
Additionally, our re-mining activities will assist with environmental remediation in this area. We look forward to working with all stakeholders to further progress the Project in the months ahead.”
Background to the Project
In November 2020, Pan African announced that the Company had entered into conditional sale of shares agreements to acquire the share capital and associated shareholder loans and other claims of Mogale Gold and Mintails’ SA Soweto Cluster Proprietary Limited (“MSC”) (together the “Mintails Transaction”). Both Mogale Gold and MSC are 100% owned by Mintails SA, which was placed into provisional liquidation during 2018.
The deadline for fulfilment of the conditions to conclude the Mintails Transaction was extended to August 2022 and included the completion of a fatal flaw analysis, prefeasibility study (“PFS”) and DFS. The PFS on the Mogale Gold TSFs was completed during July 2021, followed by the DFS, announced today. Both studies were led by DRA. Further technical work on the MSC TSFs is currently in progress.
Mineral Reserves and Resources
Following the initial due diligence on Mogale Gold, the following work was undertaken to improve the Mineral Resource confidence:
The combined drilling totaled 2,761m resulting in 1,877 samples and 187 control samples; and resulted in the remodeling of all available resources as reported in the Mineral Resource table below:
Indicated and Inferred
TSF |
Tonnage
Mt |
Gold | ||
g/t | kg | oz | ||
Indicated | ||||
Total Indicated | 121.62 | 0.29 | 35,049 | 1,126,855 |
Inferred | ||||
Total Inferred | 4.64 | 0.33 | 1,525 | 49,040 |
The updated three-dimensional Mineral Resource models were subjected to a hydro-mining and load-and-haul mine design and schedule according to engineering parameters as defined in the DFS. The same approach was previously used by Pan African during the design process of the Group’s Elikhulu operation (Elikhulu).
Scheduling of the available resources was built around achieving a throughput rate of 800ktpm, as detailed in the July 2021 PFS, as the optimal processing throughput. The Mineral Resources subjected to the mine design and scheduling was subsequently converted to Probable Mineral Reserves, as depicted in the table below:
Mineral Reserves
Probable Reserves |
Tonnage | Gold | ||
Mt | g/t | kg | oz | |
Total Mineral Reserves | 123.58 | 0.29 | 35,400 | 1,140,180 |
Conceptual MSC resource/reserve and production upside
In the SENS announcement of 6 November 2020, the Company reported that the MSC TSFs comprise nine separate facilities with resources of 119Mt with an in-situ grade of 0.31g/t, containing an estimated gold content of 1.20Moz. Although Pan African currently classifies the MSC Mineral Resources in the Inferred Mineral Resource category until further technical studies and work is completed, a conceptual production schedule for this project was applied, based on available information.
This conceptual production scheduling, entailing the processing of combined TSFs demonstrates a more robust recovered ounce profile and an extended LOM for the project, in excess of 20 years. The conceptual MSC TSF model increased production by an average of 11koz/yr from years 6 to 13 (once the Mogale Gold TSF resources are depleted), giving rise to a production profile of an average 54koz/yr from year 14 to 20.
No Mineral Reserves or financial valuation for the conceptual MSC scheduling can be reported on at this stage and the incremental production from this cluster is included for illustrative purposes only.
Re-mining and processing
The study envisages hydro-mining to be utilised for the larger dumps, using hydraulic guns of similar specification as used at Elikhulu, cutting mine widths of 15m wide and 20m deep. The North Sands and South Sands dumps are conducive to load-and-haul mining, to extract the resources from these dams.
The re-mined tailings will be processed in a CIL plant of similar design to the Elikhulu operation, with the addition of a water treatment section to limit corrosion and potentially improve recoveries. The DFS process plant is designed for an average throughput of 800ktpm, with up to 900ktpm achievable without negatively affecting performance.
All of the borehole samples were utilised to refine and test the expected gold recoveries from the processed material, under the direct supervision and management of Pan African. The modelled recoveries are presented in the table below:
Resource material TSF | % Recovery modelled |
1L23-25 | 54.70% |
1L13-15 | 48.90% |
1L28 | 34.40% |
1L8 | 53.56% |
1L10 | 50.85% |
North Sand Dump | 71.00% |
South Sand Dump | 75.71% |
Key financial assumptions and outputs (as per DFS)
Description | |
Net Present Value (9.4) | R1,006 million (US$64,9 million) |
Real Ungeared Internal Rate of Return | 20.1% |
Total construction capex requirement | R2,460 million (US$158,7 million) |
Forecast payback period (post commissioning) | 38 months |
Average AISC | ~US$ 914/oz |
LOM operating cost | ~ZAR 78/t (~US$5/t) |
Average annual gold production | ~50koz |
LOM | 13 years |
Envisaged project financing
The Group has received a number of offers from financing institutions and third party financiers for the Project funding and expects to finalise the funding package later this year, if the Company was to proceed to project execution.
Way forward and possible project execution timeline
Following in-principle approval by Pan African’s board to further progress the Project, the Company will commence with the environmental authorisation process and stakeholder engagements.
Activity Estimated date
Completion and finalisation of DFS Completed
Engineering optimisation activities June – August 2022
Detailed engineering study September 2022 – March 2023
Likely project commencement date September 2022
Funding package finalised October/November 2022
Environmental approvals March 2023
Construction commences April 2023
Commissioning July 2024 – December 2024
ESG/Social Impact
As part of the DFS, the Company has already conducted extensive engagements with community representatives and other interested and affected organisations based in the area, including regulatory authorities. This information and the EMPR is being utilised to compile an action plan to remediate past environmental damage and restore the surface for productive land use, while at the same time investigating impactful socio-economic development projects intended to stimulate the local economy.
The Company will also conduct feasibility studies into the merits of renewable energy for the new tailings retreatment plant’s energy requirements.
Competent Person
The competent person for Pan African Resources, Hendrik Pretorius, the manager for Group mineral resource management, signs off the Mineral Resources and Mineral Reserves for the Group. He is a member of the South African Council for Natural Scientific Professions (SACNASP 400051/11 – Management Enterprise Building, Mark Shuttleworth Street, Innovation Hub, Pretoria, Gauteng Province, South Africa), as well as a member in good standing of the Geological Society of South Africa (GSSA – CSIR Mining Precinct, Corner Rustenburg and Carlow Roads, Melville, Gauteng Province, South Africa). Hendrik has 18 years' experience in economic geology and mineral resource management (MRM). He is based at The Firs Office Building, 2nd Floor, Office 204, Corner Cradock and Biermann Avenues, Rosebank, Johannesburg, South Africa. He holds a BSc (Hons) degree in Geology from the University of Johannesburg as well as a Graduate Diploma in Mining Engineering from the University of the Witwatersrand. Hendrik has reviewed, and approved, in writing the information contained in this document as it pertains to Mineral Resources and Mineral Reserves.
The information contained in this announcement is the responsibility of the Company’s board of directors and has not been reviewed or reported on by the Group’s external auditors.
Rosebank
30 June 2022
Certain information communicated in this announcement was, prior to its publication, inside information for the purposes of Article 7 of Regulation 596/2014.
For further information on Pan African, please visit the Company's website at
Corporate information | |
Corporate Office
The Firs Office Building 2nd Floor, Office 204 Cnr. Cradock and Biermann Avenues Rosebank, Johannesburg South Africa Office: + 27 (0)11 243 2900 info@paf.co.za |
Registered Office
Suite 31 Second Floor 107 Cheapside London EC2V 6DN United Kingdom Office: + 44 (0)20 7796 8644 |
Chief Executive Officer
Cobus Loots Office: + 27 (0)11 243 2900 |
Financial Director
Deon Louw Office: + 27 (0)11 243 2900 |
Head: Investor Relations
Hethen Hira Tel: + 27 (0)11 243 2900 E-mail: hhira@paf.co.za |
Website: www.panafricanresources.com |
Company Secretary
Phil Dexter/Jane Kirton St James's Corporate Services Limited Office: + 44 (0)20 7796 8644 |
Nominated Adviser and Joint Broker
Ross Allister/Alexander Allen Peel Hunt LLP Office: +44 (0)20 7418 8900 |
JSE Sponsor
Ciska Kloppers Questco Corporate Advisory Proprietary Limited Office: + 27 (0)11 011 9200 |
Joint Broker
Thomas Rider/Nick Macann BMO Capital Markets Limited Office: +44 (0)20 7236 1010 |
Joint Broker
Matthew Armitt/Jennifer Lee Joh. Berenberg, Gossler & Co KG (Berenberg) Office: +44 (0)20 3207 7800 |