3rd Quarter Results
SouthernEra Releases Third Quarter Results
Shares Issued and Outstanding: 51,828,400
TSX: SUF
AIM: SRE
TORONTO, Nov. 29 /CNW/ - SouthernEra Resources Limited is pleased to
announce the following highlights from the third quarter of 2002:
- SouthernEra Joint Venture awarded new platinum properties in South
Africa: 7.8 million ounces of PGMs added to Resource Base
- Trading in the Company's common shares commences on London Stock
Exchange's AIM
- Drill program defines 1.44 million ounce mineral resource at Millennium
Platinum
- Camafuca diamond operating joint venture agreement signed
- Yamba Lake diamond project yields encouraging diamond results
- SouthernEra underwrites Messina Limited Rights Offer
- Messina Phase 2 Feasibility Study completed by SRK, upgrading mineral
resource to 6.3 million ounces
- SouthernEra added to S&P/TSX Composite Index
- Messina Platinum commissions Phase 1 (Voorspoed) Main Shaft and
Concentrator Plant
Subsequent to September 30, 2002:
- Additional drilling at Yamba Lake completed
- Shaft Deepening Capital Costs reduced by 50% following optimization
study at Messina Phase 1 Mine
- Messina Rights Offer concluded
- Company reports progress at Millennium Platinum second phase drilling
program
Operations Update
The Company's 70.91 percent subsidiary (70.42 percent at September 30,
2002) Messina Limited and its wholly owned subsidiary Messina Platinum Mines
Limited, continued to make good progress in developing the Phase 1 Mine.
Equipping of the main shaft to 430 metres was concluded, while development and
production at the 150 and 200 metre levels continued through the secondary
shaft.
Following the recently announced optimization study, the conventional
shaft sinking will conclude at the end of November. Development of a decline
ramp system below the 350 metre operating level has commenced following
completion mid-year of the design for the implementation of the mechanized
long hole stoping method at the Phase 1 Mine. By leading with the ramp
development to 730 metres, it is possible to raise-bore and slipe the Phase 1
shaft system.
As planned, the Phase 1 Main Shaft was commissioned on August 19 and the
construction of the main 90,000 tonnes per month concentrator plant was
commissioned on September 12.
The focus of activity has now shifted to development on the 275, 350 and
400 metre levels to support the build-up of production to 80,000 tonnes per
month during the third quarter of 2003 and 120,000 tonnes per month during the
second quarter of 2004.
At the Company's 50 percent-owned Klipspringer Diamond Mine, sinking of
the decline was completed during the quarter. Fissure development and mining
is now the focus of activity. In the current quarter, tonnage throughput was
61,900 tonnes. Average grade in the quarter was 40 carats per hundred tonnes,
yielding 24,900 carats.
The Company incurred a net loss for the three months to September 30 of
$0.7 million (1 cent per share) on revenue of $0.9 million, compared to a loss
of $0.8 million (2 cents per share) on revenue of $0.7 million in the third
quarter of 2001. Cash flow used in operations for the quarter was $3.0 million
(6 cents per share), compared to a source of $1.6 million (2 cents per share)
in the third quarter of 2001.
For the nine months ended September 30, the net loss was $4.3 million
(9 cents per share) versus $3.8 million (12 cents per share) for the
comparable period in 2001. Cash used in operations totaled $4.1 million
(8 cents per share) compared to $0.8 million (3 cents per share) for the nine
months in 2001.
SouthernEra Joint Venture awarded new platinum properties in South
Africa: 7.8 million ounces of PGMs added to resource base
The award of three new platinum properties (the Dwaalkop Properties) to
SouthernEra and its 50 percent joint venture partner, Mvelaphanda Resources,
increased the PGM resource base at the Greater Messina to approximately 25
million ounces. The newly acquired properties contain both the UG2 and
Merensky Reefs and are located between Phase 1 (Voorspoed) and Phase 2
(Doornvlei) Projects currently being developed by Messina Limited,
SouthernEra's 70.42 percent subsidiary (following the conclusion of the
Messina rights issue, see news release dated November 11, 2002, this interest
increased to 70.91%).
Trading in the Company's Common Shares Commences on the London Stock
Exchange's AIM
Trading in the Company's common shares on the London Stock Exchange's AIM
commenced on August 13, 2002. In support of its application to AIM the Company
published an AIM admission document pursuant to the AIM rules of the London
Stock Exchange. The document includes an independent competent person's
report.
1.44 million ounce mineral resource at Millennium Platinum
The initial drilling program at the Company's Millennium Project in
Mpumalanga Province, South Africa successfully intersected the UG2 Reef and
defined an inferred resource of 10.03 million tonnes, grading 4.46 grams per
tonne (5PGE + Au), containing 1.44 million ounces of precious metals. The
mineral resource defined is restricted to portions 10 and 11 of the farm
Blaauwbank 168 JS only, less than 20 percent of the prospected area to be
drilled.
Camafuca Operating Joint Venture Approved
The Council of Ministers of Angola approved the operating agreement for
Project Camafuca and authorized the formation of the operating company,
Sociedade Mineira do Camafuca, Lda (SMC). Following the incorporation of the
operating company and the issuance of the necessary mining licenses, it is
anticipated that production at Camafuca could commence during 2003.
Yamba Lake Diamond Project Results
SouthernEra's first drill hole into the Sue kimberlite pipe on the
Company's 60% controlled Yamba Lake project in the Northwest Territories of
Canada intersected 172 metres of kimberlite yielding a sample of 226.7
kilograms. The sample returned 77 microdiamonds (using a 0.106 millimetre mesh
bottom screen) plus 18 macrodiamonds having one dimension greater than or
equal to 0.50 millimetres. Subsequent to the quarter a further three holes
tested the Sue kimberlite pipe. The three additional drill holes; Y02-09,
Y02-10 and Y02-11 yielded sample sizes of 190.95, 147.9 and 151.33 kilograms
and returned 5, 4 and 6 macrodiamonds respectively, having one dimension
greater than or equal to 0.50 millimetres (see news release dated October 29,
2002).
SouthernEra underwrites Messina Limited Rights Offer
The Messina Limited rights offering consisted of 20 rights for every 100
shares currently in issue. Each right enabled the purchase of one common share
of Messina Limited at a price of South African Rand (R) R60. A total of
2,592,979 rights were issued to the shareholders of record of the 12,964,895
Messina Limited shares issued and outstanding for total proceeds of R155.6
million. The rights offer was concluded subsequent to the quarter and the
Company's ownership in Messina Limited increased to 70.91 percent.
Messina Phase 2 Feasibility Study completed by SRK
The Company announced the completion of the Bankable Feasibility Study
for its Messina Phase 2 Project on the Doornvlei Property by SRK Consulting.
The Property is 100 percent owned by Messina Limited, which in turn is
70.91 percent owned by SouthernEra Resources Limited (70.42 percent at
September 30, 2002). An indicated mineral resource of 6.3 million ounces,
grading 5.08 grams per tonne (5PGE + Au) has been defined at Doornvlei. The
expected operating mine life is 23 years with full production of 120,000
tonnes per month with an annual average production rate of approximately
173,000 ounces of 5PGE + Au.
SouthernEra added to S&P/TSX Composite Index
SouthernEra's admission followed the quarterly S&P/TSX Composite Index
Review and the subsequent announcement on September 17 by Standard and Poor's.
The index changes outlined in the announcement occurred after the close of
trading on the Toronto Stock Exchange on September 20, 2002.
Messina Platinum Commissions Phase 1 (Voorspoed) Main Shaft and
90,000tpm Concentrator Plant
Following cold commissioning, the 90,000 tonnes per month main
concentrator plant was handed over for hot commissioning on September 12, nine
days ahead of schedule and approximately 12 percent under budget. Final
commissioning occurred on September 19, 2002.
SouthernEra Resources Limited is an independent producer of platinum
group metals and diamonds. The Company also has an extensive PGM and diamond
exploration program. The common shares of SouthernEra are traded on the
Toronto Stock Exchange (SUF) and the London Stock Exchange's AIM (SRE).
For further information: PLEASE CONTACT: SouthernEra Resources Limited,
Patrick C. Evans, President and CEO; or Dr. Sally Eyre, Vice President
Corporate Affairs, Telephone: (416) 359-9282, Fax: (416) 359-9141, e-mail:
inbox(at)southernera.com
SUF. SRE