Adriatic Metals PLC
('Adriatic Metals' or the 'Company')
ENVIRONMENTAL & SOCIAL IMPACT ASSESSMENT
RELEASED FOR PUBLIC REVIEW
HIGHLIGHTS
• Adriatic has undertaken an Environmental & Social Impact Assessment ("ESIA") in line with best international practice.
• Baseline studies started in Q1 2020, following a screening and scoping study that commenced in Q4 2019.
• The Company appointed Wardell Armstrong International to develop the ESIA, in order to conform with the Performance Requirements set out in the European Bank for Reconstruction and Development's 2019 Environmental and Social Policy.
• The ESIA has now been released for a 60-day public review and disclosure period.
• The data from the baseline studies, and predictive modelling of the project components and activities, has informed a comprehensive suite of Environmental and Social Management Plans. These will guide the Company's activities throughout the development, exploitation, and ultimate decommissioning of the Vares Silver Project to avoid, minimise and manage impacts.
• The ESIA can be downloaded from the Company's website https://www.adriaticmetals.com/sustainability/esia/
Paul Cronin, Adriatic's Managing Director and CEO commented:
"The completion of the first natural resources ESIA in Bosnia & Herzegovina is a significant step forward for the Adriatic Metals' team, and reinforces our commitment to both best international practice, as well as to the communities and environment that host our operation. As we end nearly two years of studies, our passionate and committed staff can start the development of the Vares Silver Project, secure in the knowledge that they understand the requirements of the community and have the tools available to minimise, and where required, mitigate the impacts of our operation."
Eric Rasmussen, EBRD's Director of Natural Resources commented:
"The EBRD has published the Vares Silver Project ESIA for public consultation. The ESIA has been developed by Adriatic Metals following over nearly two years of studies to meet EBRD's Performance Requirements under its 2019 Environmental and Social Policy. The Performance Requirements set out good international practice for the management of environmental and social impacts and risks and aligns with Adriatic Metal's commitment to environmental and social stewardship and its support of communities near to the mine. EBRD has supported Adriatic Metals in the development of this ESIA which sets a high standard for the Vares Silver Project and future projects."
Adriatic Metals PLC (ASX:ADT, LSE:ADT1, OTCQX:ADMLF) ("Adriatic" or the "Company") is pleased to announce the release of its Environmental & Social Impact Assessment ("ESIA") for its Vares Project ("Vares Silver Project" or "Project") in Bosnia & Herzegovina.
Background
The Company took the decision in 2019 to conduct an ESIA in compliance with the highest recognised international industry standards. The Company appointed Wardell Armstrong International ("WAI") to produce the ESIA to conform with the Performance Requirements ("PR") set out in the European Bank for Reconstruction and Development's ("EBRD") 2019 Environmental and Social Policy, as well as taking into consideration, amongst others, the World Bank's International Finance Corporation ("IFC") Performance Standards and the recently published findings of the Global Tailings Review.
ESIA Review Period
The ESIA has now been released for a 60-day public review and disclosure period as per EBRD's PRs. The ESIA can be downloaded from the Company's website https://www.adriaticmetals.com/sustainability/esia/ and will be made readily available to all stakeholders. A comprehensive dissemination and disclosure plan, including "open-house" meetings with both near-mine communities and federal stakeholders has been produced, Chapter 8 of the ESIA sets this out in detail.
Scope of Assessment
The ESIA was undertaken to assess and present the risks and impacts of the Vares Silver Project along with mitigation measures and environmental and social management plans, in accordance with international best practices and standards. Specifically, the ESIA conforms to the requirements of EBRD's 2019 Environmental and Social Policy. The Company also completed a separate local permitting process to ensure the Project conforms with the legislative requirements of Bosnia & Herzegovina, a part of which also includes environmental impact assessments for different project components.
The ESIA process commenced with a screening and scoping study, completed by WAI in Q1 2020. This study allowed for the design and implementation of a baseline collection programme. Impact assessment and mitigation design, together with social, environmental and health management plans, are based on these baseline conditions and take account of the releases and effects associated with the Vares Silver Project.
A critical component of the impact assessment process is the consultation with all the various stakeholders affected by the Project to ensure that the ESIA considers, as a priority, any issues identified. These stakeholders are principally those within the local communities, as well as government institutions and non-governmental organisations. An ESIA consultation process was initiated with local communities in November 2019 and has continued throughout the ESIA period. Feedback from these consultations has helped refine the baseline data collection and inform the application of the mitigation hierarchy and management planning detailed in the ESIA.
The purpose of the ESIA now disclosed is to document the existing environmental and social conditions, describe the proposed operation, identify its impacts, develop implementation measures to avoid, reduce or minimise the impact of the operation and the actions needed to ensure their performance. This includes the planned activities of construction, operations and decommissioning on the following four main components of the Vares Silver Project:
- the Rupice underground mine and associated surface infrastructure ("Rupice");
- the Vares Processing Plant ("VPP");
- the VPP dry stack tailings storage facility ("TSF"); and
- the 24.5km haul route connecting VPP to Rupice.
The impact assessment subject areas are interlinked. The ESIA has been developed alongside and based upon the Vares Project Definitive Feasibility Study, as announced on 19 August 2021, in close collaboration with its authors. The environmental, social and health aspects of these areas have been integrated into the overall Vares Silver Project design, avoiding any significant adverse impacts.
The final stage of the ESIA process is to consider and take into account any comments received during the disclosure period and the meetings that will be held to share the results with local communities, nearby municipalities, and national stakeholders, as well as other interest groups. The Final ESIA will incorporate these comments as appropriate and the documents will thereafter be available, in English and Bosnian, on our websites.
Summary
The publication of the ESIA represents a further landmark in the development of the Vares Silver Project. The resulting environmental, social and health mitigation measures, encapsulated in comprehensive management plans, enable the Company to commence development secure in the knowledge that is proceeding in accordance with best international practise and is aligned with the aspirations and requirements of its key stakeholders; the communities and environment in which it operates.
** ENDS **
MARKET ABUSE REGULATION DISCLOSURE
The information contained within this announcement is deemed by the Company (LEI: 549300OHAH2GL1DP0L61) to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. The person responsible for arranging and authorising the release of this announcement on behalf of the Company is Paul Cronin, Managing Director and CEO.
For further information please visit www.adriaticmetals.com or @adriaticmetals visit on Twitter; or contact:
Adriatic Metals PLC |
|
Paul Cronin / Thomas Horton |
Tel: +44 (0) 7866 913207 |
|
|
Canaccord Genuity Limited (Joint Corporate Broker) |
|
Jeremy Dunlop (Australia) |
Tel: +61 2 9263 2700 |
James Asensio (UK) |
Tel: +44 (0) 207 523 8000 |
|
|
RBC Capital Markets (Joint Corporate Broker) |
|
Marcus Jackson / Jamil Miah |
Tel: +44 (0) 20 7653 4000 |
|
|
Stifel Nicolaus Europe Limited (Joint Corporate Broker) |
|
Ashton Clanfield / Callum Stewart |
Tel: +44 (0) 20 7710 7600 |
|
|
Buchanan |
|
Bobby Morse / Ariadna Peretz |
Tel: +44 (0) 207 466 5151 |
|
|
The Capital Network |
|
Julia Maguire / Lelde Smits |
Tel: +61 2 8999 3699 |
|
|
ABOUT ADRIATIC METALS
Adriatic Metals PLC (ASX:ADT, LSE:ADT1, OTCQX:ADMLF) is a precious and base metals developer that is advancing the world-class Vares Silver Project in Bosnia & Herzegovina, as well as the Raska Zinc-Silver Project in Serbia.
The 2021 Vares Silver Project Definitive Feasibility Study boasts robust economics of US$1,062 million post-tax NPV8, 134% IRR and a capex of US$168 million. The Company is well-funded and concurrent with the advancing of the Vares Silver Project into construction, it continues to explore across its highly prospective 41km2 concession package.
Adriatic Metals completed the acquisition of TSX-listed explorer Tethyan Resource Corp. in Q4 2020, which contained the Raska Zinc-Silver Project in southern Serbia. The Company is exploring across its 99km2 highly prospective concession area, which includes around the formerly operating Kizevak and Sastavci polymetallic mines.
There have been no material changes to the assumptions underpinning the forecast financial information derived from the production target in the 19 August 2021 DFS announcement and these assumptions continue to apply and have not materially changed. Adriatic Metals is not aware of any new information or data that materially affects the information included in the announcement of the updated Mineral Resource Estimate announced on 1 September 2020 and all material assumptions and technical parameters underpinning the Mineral Resource Estimate
ABOUT WARDELL ARMSTRONG INTERNATIONAL
Wardell Armstrong are a multidisciplinary Environmental, Engineering, and Mining consultancy working in the Infrastructure & Utilities, Property & Development, and Mining & Minerals Sectors. Its history dates back over 180 years and has a reputation for high quality service, both in the UK and internationally.