Sekisovskoye Update
Hambledon Mining PLC
16 May 2007
16 May 2007
HAMBLEDON MINING PLC
More gold, lower construction costs
Update on progress
Hambledon Mining plc ('Hambledon' or the 'Group' or the 'Company'), the
AIM-listed mining and exploration company developing precious metal deposits in
Kazakhstan, is pleased to announce significant progress in both the mining and
construction activities at the Sekisovskoye Gold Project. Refurbishment of the
Ognevka treatment plant for the production of copper/gold/silver concentrate as
well as other valuable by-product concentrates has also commenced.
Highlights
•Mining activities are continuing at Sekisovskoye, with over 1.0 million
cubic metres of material moved since the commissioning of the mining fleet
in June 2006
•Grade control drilling has confirmed the style of mineralisation
predicted by our geological model and shows an increase of 18% in contained
gold in that area. This is consistent with previous results where western
drilling at Sekisovskoye has shown higher contained gold than Soviet
drilling had indicated
•The construction costs are likely to be less than the budget set in June
2006, although time requirements have been extended
•Wholly owned 'TOO Ognevka' has begun refurbishment of the Ognevka
treatment plant and commenced a study into the additional recovery of
feldspar from tailings
Sekisovskoye update
Mining operations have continued with cutback excavations, tailings dam
construction and other support for mill facilities construction activities.
Mining has exceeded targets for all but one month since beginning in June 2006,
with over 1.0 million cubic metres of material moved.
Construction of the mill facilities is ongoing. Although delays have been
experienced from late delivery of our main ball mills and poor performance from
local construction contractors, all major equipment items have now been
installed, are in store or in transit. Our first ball mill has now arrived and
will be installed by the end of May and the second, which has been completed and
is awaiting shipment, is planned to be installed by the end of June. This
delivery schedule is some nine months later than contracted, reflecting the
extraordinary demand for mining equipment which certain suppliers have been
unable to properly schedule or fulfil.
Whilst the standard of work performed by some contractors has been excellent,
the timeliness in some cases has been poor. The principal reason is that only a
limited number of such contractors are authorised to carry out certain types of
work essential to the project, leaving little room for selection or negotiation.
The Company's response has been to take on suitably experienced staff so as to
allow the Company to acquire the necessary licences to do the work itself. To
this end, the Company is now licensed to carry out electrical design and to
construct tailings dams, processing facilities and buildings. All construction
work is now under the direct management of Company staff, with only direct
labour being subcontracted. The result has been an improvement in both the
timeliness and quality of the work and a significant reduction in cost.
Similarly, the Company's mining fleet far outstrips the efficiency available
from local earth-moving contractors. Large sections of the work associated with
site preparation and tailings dam construction have been carried out by the
Company's own fleet, resulting in further significant cost savings which will
impact both the initial construction and the ongoing tailings dam development
costs. Additions to the earth-moving fleet to enable this work to be done have
been authorised and their cost will be recouped within the commissioning period.
The new powerline has been completed and connection to the new supply was made
on 3 May. The main transformer has arrived on-site and will be installed
immediately. The commissioning of the process plant will begin with the crushing
plant later this month and will continue with the remaining sections
progressively through June and July. Regulations in Kazakhstan mean that final
approvals to allow for procurement of certain reagents cannot be applied for
until the completion and inspection of the associated storage and mixing
facilities. No significant delay is expected but it is not possible to predict
the time-line exactly.
Exploration
Open Pit Grade Control Results - Sekisovskoye
Blasting on the 480-490m elevation bench, in the central area of the designed
pit, necessitated the taking of blasthole drilling samples for demarcating the
limits of ore zones, as defined by a 0.5g/t Au cutoff. This ore zone was defined
by 134 blastholes from which 723 one metre length samples were assayed for
contained gold. A 3-D wireframe model representing this ore zone was used to
control the generation of a block model. Gold grades for the model blocks were
estimated, using the blasthole assays, and these blocks were added to the
original grade model, as defined from the exploration diamond drill samples, for
direct comparisons between the two model types. Overall, the blasthole grade
model confirmed the validity of the exploration resource model in this area. The
results were as follows:
Model Au gm/t Tonnage Contained Au oz
Exploration 1.45 12,900 601.4 (18,705gm)
Grade control 1.46 15,074 707.6 (22,008gm)
Percentage increase 0.7% 16.9% 17.7%
Even with the increase in tonnage, partly due to the effects of dilution, the
grade control model is still higher than the original grade model, and the
overall increase in contained metal is 18%, which equates with earlier
statistical analyses that indicated an upgrading of contained gold, from the
former-Soviet drilling results, in the order of +17%. It is predicted that this
trend is likely to continue for the whole of the deposit, especially in areas of
sparse sampling and at depth where the probability of finding additional gold
mineralisation is high.
Geological exploration - Tserkovka
Results of a 5,000m exploration drilling programme, to determine the magnitude
and continuity of gold mineralisation, as indicated from favourable historical
sampling, indicated that contained gold in exploitable commercial quantities was
not apparent. This exploration activity was centred along strike at Tserkovka,
situated 5km NW from the Sekisovskoye open pit operations. The exploration
drilling also included two small target areas, situated NW at 6km and 2km.
A total of 45 diamond drillholes and 4 minor surface trenches contained an
average of 102m linear metres ranging from 24m to 323m. Gold grades from the
4,347 core and trench samples showed a range in values from 0.0g/t to 46.8g/t
and silver values ranging from 0g/t to 903.6g/t. A number of drillhole
intersections contained favourably mineralised breccias and dykes, similar to
the geology at the Sekisovskoye deposit. However, these zones at Tserkovka are
relatively narrow and continuity along strike and downdip appears to be limited.
The best continuity was found at profile 26 where an interpreted 1.2m wide zone
contained 1.0g/t gold and traced for about 90m along dip.
Although the results are disappointing, it is possible these relatively minor
gold intersections represent an upper expression of a large auriferous breccia
pipe at depth, where the physico-chemical conditions are more appropriate for
gold mineralisation. Therefore, as a second phase to the exploration drilling at
Tserkovka, further strategic drillholes will be drilled to intersect known
favourable breccia zones at depth.
Exploration at Sekisovskoye deposit
Current exploration drilling is centred within the western margins of the open
pit where extensions of orebody 11 are being defined for both open pit and
future underground exploitation. Analytical results have not been received yet,
but mineralised intersections have been observed. Known gold mineralisation,
immediately along strike to the Sekisovskoye deposit, will also be target
drilled to help better define the extent of gold resources in these areas. Next
year, underground drilling will be focused on upgrading the resources and
reserves for underground extraction.
Ognevka processing facility
Registration of the acquisition of TOO Ognevka has been completed and the court
has approved the rehabilitation plan. Renovation of the clinker treatment
facility has commenced.
The first stage of renovation focuses only on those parts of the plant that will
be used for the treatment of zinc smelter residues, 150,000 tonnes of which are
already on site. However, the plant was originally built to treat the output
from an associated mine (to which the Company does not currently have the mining
rights) which contains substantial resources of feldspar, with potential
by-products including tantalum, lithium, niobium, tin and mica. Production
facilities to treat these ores are also in place and can potentially be brought
back into use. Whilst the possibility of acquiring the mining rights is a medium
term objective, a study is being carried out on the more immediate opportunity
to recover substantial quantities of tailings which can be retreated to recover
the feldspar and other by-products which were not previously extracted.
The processing facility is configured to treat up to 350,000 tonnes per year of
zinc smelter residues, but the first stages of a significant expansion of the
facility have already been completed by the previous owners. This includes an
extension of the mill building, and construction of the ore handling system and
mill-feed storage bins. As soon as production from the existing capacity has
been successfully restarted, a study into the completion of the expansion will
be carried out.
Enquiries
Hambledon Mining plc
Nicholas Bridgen, Chief Executive Telephone: +7 701 733 8915
Seymour Pierce
Nicola Marrin Telephone: +44 207 107 8018
Bankside Consultants
Michael Padley / Daniela Hale Telephone: +44 207 367 8888
Qualified Person
The drilling results in this announcement have been reviewed by Roger Rhodes
BSc, MSc, MIMMM, independent geological consultant with Computer Resource
Services. He has over 35 years of relevant experience and is a qualified person
for the purposesof the JORC Code and the AIM Rules.
Note to editors
Hambledon Mining plc is an AIM-listed gold mining and exploration company which
is developing the Sekisovskoye gold deposit and owns the Ognevka processing
plant, both of which are close to Ust Kamenogorsk in East Kazakhstan.
At Sekisovskoye, the company is mining from an open pit and constructing an
850,000 tonnes per year treatment plant. Production from the open pit will
average over 40,000 ounces per annum. After the start of open pit processing,
the Company plans to develop the much larger underground resource which is
expected to lead to a combined production rate of around 100,000 ounces per
year.
The Ognevka processing plant is being refurbished and will produce concentrates
containing gold, silver, copper, iron and coke from the retreatment of zinc
smelter residues.
Ends
This information is provided by RNS
The company news service from the London Stock Exchange