Esquel Gold Project

Brancote Holdings PLC 6 November 2001 Date: 6th November 2001 Contacts: Richard Prickett, Chairman Bill Humphries, Managing Director Brancote Holdings PLC 020 7493 1002 David Bick Holborn Public Relations 020 7929 5599 david.bick@holbornpr.co.uk BRANCOTE HOLDINGS PLC Esquel Gold Project (74%) Pre- Feasibility Study In May 2001 Pincock Allen & Holt (PAH), Engineering Consultants from Denver Colorado, were engaged by Brancote to prepare a Pre-feasibility study for the Esquel Gold Project. The completed study includes the construction of facilities, mining by open pit methods and processing of precious metal ores at the nominal rate of 1.8 million tonnes per year, beginning in the year 2004. Highlights from the study are: * A mine plan with a processing facility capable of producing 500,000 ounces of gold per annum has been adopted with a 10 years mine life, including 5/6 years of mineable reserves and 4/5 years of resource. * High proportion (88%) of the measured and indicated resource converted into mineable reserves of 10.4 million tonnes containing 2,818,000 ounces of gold at a grade of 8.5 gpt. * Good metallurgical recoveries of 89.5 percent for gold using standard whole ore Carbon in Leach (CIL) recovery methods. * Cash cost averages US$102 per ounce of gold plus US$9 per ounce for royalty and refining charges. The average cash cost per ounce of gold is US$81 for the first two full years of production. * Estimated capital costs of up to US$131.5 million for the plant and infrastructure including indirect charges and contingencies of US$41 million. Based on the information developed during the Pre-feasibility Study, PAH is of the opinion that this is a positive project with the likelihood of increasing resources and improving operating costs. Mine Plan In considering the parameters for the design of the mine and the processing facilities, Brancote opted for a 10 year production/mine life with 5/6 years of mineable reserves and 4/5 years of defined resource as the minimum criteria. At commencement of pre-feasibility, the defined resource already stood at 4.1 million ounces, including 3.3 million ounces of measured and indicated that had a high probability of conversion into mineable reserves. In addition, the high rate of discovery (70 ounces of gold per metre drilling) together with the prospectivity of the central zone containing numerous un-drilled but highly anomalous vein systems, led Brancote to believe that a resource of +5 million ounces of gold was likely to be achieved in the early years of mining. Accordingly, a mine plan and processing facility capable of producing circa 500,000 ounces of gold per annum was adopted. Mine Design and Resource Estimate The Esquel Gold Project is an open-pit gold mining project that will utilise excavators and trucks as the primary mining equipment. Production is scheduled for 1.8 million tonnes of ore and an average 19.3 million tonnes of waste per year over the 6.5 years of life of the project. These reserves will come from three pits, which will encompass all of the Galadriel, Galadriel Sur, Julia and Elena Norte systems. At the end of the phase IV drilling programme in May 2001 the total resource defined at the Esquel Project, at a cut-off grade of 1gpt, was: Resource Resource Contained Contained Category Tonnes Gold Ounces Silver Ounces Measured 7,756,000 1,910,500 3,303,200 Indicated 7,010,600 1,420,200 2,644,000 Inferred 4,695,700 492,700 1,036,800 Total 19,462,300 3,823,400 6,984,000 The Base Case for the Pre-feasibility Study was based on proven and probable reserves derived from the measured and indicated resources only. Neither the inferred resources have been included in the Mineable reserve, nor have the resources from the satellite areas Elena Sur and Antonia, both requiring additional drilling for better definition. A 'Floating cone' analysis was used to design the ultimate pit as well as to examine the project's sensitivity to gold price. At a gold price of $270 per ounce and cut-off of 1.44 gpt, the resulting floating cone contained 10.8 million tonnes at a gold grade of 8.5 gpt and a silver grade of 14.5 gpt with 126.8 million tonnes of waste. Reserves for the ultimate pit design are summarised in table 1-4 Table 1-4 Minera El Desquite Esquel Gold Project Reserve Estimate - Undiluted & Diluted at 11.5% & Zero Grade Category Ore Gold Contained Silver Contained Tonnes Grade Au oz Grade Ag oz g/t G/t Proven 6,009,000 8.91 1,721,000 15.23 2,942,000 Probable 4,348,000 7.85 1,097,000 13.65 1,908,000 Total 10,357,000 8.46 2,818,000 14.57 4,850,000 Undiluted Proven 6,700,000 7.99 1,721,000 13.66 2,492,000 Probable 4,848,000 7.04 1,097,000 12.24 1,908,000 Total Diluted 11,458,000 7.59 2,818,999 13.06 4,850,000 Category Gold Silver Waste Strip Ratio Recovery Recovery Tonnes Waste/ore % % Proven 89,67 73.00 Probable 89.53 73.00 Total Undiluted 89.62 73.00 115,953,000 11.2 Proven 89.67 73.00 Probable 89.53 73.00 Total Diluted 89.62 73.00 114,762,000 9.9 Metallurgy PAH reviewed metallurgical test-work performed during the past 2 years on samples from the Galadriel, Galadriel Sur, Julia, Antonia, Elena Norte and Elena Sur deposits. Testing was performed by Hazen Research Inc. of Golden, Colorado on samples taken from drill holes within the boundaries of the planned pits and representative of ore types planned for mining. The testing has investigated gravity concentration, whole ore cyanide leaching, whole ore carbon in leach, flotation of concentrates followed by CIL leaching to recover gold from the concentrates and flotation tailings, whole ore roasting followed by CIL leaching and heap leaching of low grade wall rock materials. PAH evaluated the test-work and then compared the metal recoveries, operating costs and capital costs of several viable industrial process alternatives. The Metal recoveries from the test work of the various ore types/deposits and the metal recoveries that were applied to the mine model are presented in table 1-8 (Appendix 1). PAH determined that the process that combines gravity concentration with whole ore CIL leaching is currently the most desirable for this project. This process yields high gold recoveries at lower capital and operating costs. The average gold recovery over the life of the project is estimated to be 89.5% and silver recovery is estimated at 73%. Ore Processing The ore processing facility is designed to treat 1.83 million tonnes per year of ore and will include equipment to perform coarse-crushing, SAG and ball-mill grinding, gravity concentration, CIL leaching, carbon adsorption, carbon stripping, electro-winning and smelting. The crusher will be located near the open-pit mine. Ore will be crushed at a rate of about 5,000 tonnes per day and conveyed to a large stockpile. Crushed ore from the stockpile will be conveyed to the grinding circuit, which consists of a SAG mill, one ball mill, hydro-cyclones and a pebble crusher. The ore is ground to less than 80 percent passing 74 microns in the grinding circuit to liberate the gold and silver from the waste material. Gravity concentrates are collected from a slurry stream taken from the grinding circuit utilising centrifugal and table concentrators. Finely ground ore is leached with cyanide in a series of seven large mix tanks to recover the gold and silver that was not collected in the gravity circuit. The dissolved gold and silver is recovered from the leach solutions using activated carbon (CIL process). The carbon absorbs the precious metals out of the leach solutions. The carbon is then collected from the mix tanks, screened and washed. The precious metals are then stripped from the carbon using hot cyanide/ caustic solution under pressure in a strip vessel. The strip solution containing the precious metals is then passed through electro-winning cells. The metals are collected in the cells of stainless steel cathodes. The precious metal sludge collecting on the cathodes is periodically washed from the cathodes, filtered, dried and then smelted to produce dore, which is shipped off-site to a refinery. Tailings produced from ore processing will be detoxified using the INCO/SO2 air process, thickened to a paste consistency and mixed with cement prior to disposal into a Tailings facility. This will result in a material with significantly more beneficial properties than the slurried tailings typically produced in similar operations. Grinding and cyanide leaching, followed by carbon recovery is one of the most common gold recovery circuits in the world. Sustainable Development The MED project would balance economic, environmental, social and community issues through environmental sound design and construction methods, avoiding waste and being sensitive to present and future community needs. The duration of the base case project is a minimum of 10.5 years from start of construction to closure. The needs of the present generation would be met by this project through the creation of employment and the production of gold. During the construction, production and closure phases of the project, there would be environmental impacts. The Environmental Impact Study (EIS) report conclusions are that, after the application of proposed mitigations, the project: * Would not exceed the established regulatory limits; * Would be compatible with the environment in that the environment would quickly recover from the forecasted impacts once the activity has ceased; * Would provide socio-economic benefits to the community. The project would employ approximately 340 people. Furthermore, there would be additional indirect employment generated by goods and services required by the project as well as support services for the workers and their families. During production the Esquel Gold Project will produce about 30% of the gold produced in Argentina. Environment and Environmental Planning The project will be developed under both Federal and Provincial regulatory requirements of Argentina. Principal regulatory requirements are included in the following: * Mining Code of Argentina as amended by Decree 456/97, which governs the rights, obligations and procedures for the purchase and operation of mines. Title 13, section 2 of the Mining Code addresses Environmental Protection of Mining Activities. * Law 24,585 'Supplemental Title of The Mining Code', which addresses environmental protection requirements for mining activities, including providing the scope and approach for the Environmental Impact Study that is required for permitting mining exploitation. This law provides certain responsibilities to the Province for the implementation of the Law. * Provincial Decree 4032, 'Environmental Impact Evaluation', which addresses the Chubut Province requirements for completion of environmental impact analysis for mining projects. Central to these regulations will be the requirement to prepare a comprehensive Environmental Impact Study (EIS) for the project. Requirements for the study are presented in Exhibit 3 of Law 24,585-Supplemental Title of the Mining Code. An Environmental Management System will be developed for the project, following the guiding principles of internationally recognised industrial groups such as the International Council on Metals and the Environment (ICME). The Management plan will address all aspects of environmental monitoring, hazardous material handling, mine waste management, site health and safety, spill prevention and response, dust control, surface water and erosion control and project reclamation and closure. Environmental staffing will consist of a senior level Environmental, Health and Safety Manager reporting to the General Manager, three environmental co-ordinators who are to be responsible for day to day direction of the environmental issues, and eight environmental technicians. Reclamations and closure planning for the operation will be focused on returning the site to a forested and grazing land-use, similar to the existing site conditions. Capital Cost Estimate PAH have provided a capital cost estimate for the process plant and ancillary facilities. The average accuracy of the capital estimate is +/- 25percent. Plant and Infrastructure US$131,577,680 The estimate covers the total costs of the construction and installation of the plant and infrastructure, including indirect charges and contingencies of US$41,182,474. The plant and infrastructure design allows for an enclosed conveyor from the primary crusher to the plant, a distance of 2.5 Km and drop in elevation of 450 metres. An alternative would be to haul the ore by trucks with possible savings of US$+10 million. However the conveyor will ultimately provide substantial savings in mine costs and will be environmentally friendly Mining Equipment. PAH has also budgeted US$24,588,000 for an owner operated mining fleet instead of contract mining, which will provide substantial savings in operating costs over the life of the mine as well as provide greater employment opportunities for the local community. Funds have been allocated for training of operators. Operations Costs The Base Case operations costs for the mine, process plant and ancillary facilities, as well as general and administrative are shown in table 1-14. The accuracy of the operating estimate is +/- 25percent. Table 1-14 Minera El Desquite Esquel Gold Project Base Case Operating Cost Summary Area* 2004** 2005 2006 2007 2008 2009 2010 Total Mining 14.69 13.57 11.49 12.37 9.58 8.39 4.32 10.70 Process 10.69 11.13 11.13 10.30 10.30 10.30 10.22 10.57 Reclamation 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 G&A 3.51 2.57 2.44 2.31 2.31 2.31 2.31 2.44 Total US$ per tonne 28.94 27.32 25.11 25.02 22.23 21.05 16.90 23.75 Total US$ per ounce 170.00 83.00 79.00 113.00 113.00 137.00 90.00 102.00 Total US$ per ounce with Royalty & 179.00 92.00 88.00 122.00 121.00 144.00 96.00 111.00 Refining *All values per ore tonne ** Includes pre-production and Q 3 through Q4 These costs are well within the cost limits of other operations of similar grades and stripping ratios internationally. PAH Qualifications The information requested by PAH and supplied by MED conforms to the level of detail and stage of information PAH normally requires for a Pre-feasibility Study. The information includes a general engineering basis of the study, recognised standards for the resource estimate, test and check values for the drill hole assays, some preliminary geotechnical and metallurgical test-work, budget quotes on major equipment and factors for construction, overheads, freight and contingencies. The majority of the information required was provided by MED or developed by PAH. PAH Observations and Recommendations. During the course of the study, PAH has recognised several areas that will enhance the project economics if proven by drilling, actual practice or further testwork. These items include: * Exploration drilling should be continued in order to move the inferred resource into the measured and indicated categories. * Undertake additional laboratory studies to increase recoveries from the vein and wall-rock materials. * Additional studies need to be undertaken to optimise pit slopes in the mining plan if possible. Managing Director Bill Humphries commenting on the study said: 'The results of the Pre-feasibility Study are very encouraging ensuring that the Esquel Project will be advanced through full feasibility, project financing, construction and then production. It also confirms the Esquel Gold Project as one of the most viable up and coming gold projects in the world today'. Table 1-8 Minera El Desquite Esquel Gold Project Metallurgical Test Results - Recoveries by Deposit APPENDIX 'A' Deposit Hazen Program Number Test Ore Type Representing As % of Of Tests Or Deposit Deposit Name Total Name Ore Tonnes Phase I - Year 9 Type A & B Galadriel & 38 2000 Veins Galadriel Sur (North area of Mine) Phase II - Year 32 Galadriel Sur Julia (North) 40 2001 & (Middle Area of Football Mine) Field Phase II - Year 1 Julia Julia (South) 19 2001 (South Area of Mine) Phase II - Year 1 Elena Norte Elena Norte 3 2001 (South Area of Mine) Totals/weighted 43 All All Deposit 100 Averages Ores/Veins Area Test Test Applied Applied Au Ag Au Ag Hazen Deposit Metallurgical Recovery Recovery Recovery Recovery Program As % Test By By By By of Procedure Leaching Leaching Leaching Leaching Total Oz of Gold % % % % Phase I - 51 Whole-ore 92.7 72.7 92 73 Year 2000 CIL Phase II - 29 Whole-ore 86.4 76.9 86 73 Year 2001 CIL Phase II - 17 Whole-ore 89.8 71.4 90 73 Year 2001 CIL Phase II - 3 Whole-ore 79.6 55.0 80 73 Year 2001 CIL Totals/weighted 100 Whole-ore 90.0 73.2 89.5 73.0 ed Averages CIL Note: Silver recoveries were applied to the mine model and project cash flow at a constant 73 percent
UK 100

Latest directors dealings