Qtr Expl & Dev Jly - Sept 01
BHP Billiton Limited
26 October 2001
BHP Billiton Limited is issuing this announcement to fulfil disclosure
obligations arising from its secondary listing on the London Stock Exchange.
The text of this release is identical to that issued by BHP Billiton Plc
earlier.
Date: 26 October 2001
Number: 25/01
BHP BILLITON QUARTERLY REPORT ON
EXPLORATION AND DEVELOPMENT ACTIVITIES
July 2001 - September 2001
This report covers exploration and development activities for the quarter
ended September 30, 2001. Unless otherwise stated, BHP Billiton's interest in
the projects referred to in this report is 100 per cent.
MINERALS DEVELOPMENT
Aluminium
Mozal 2 Expansion, Mozambique (BHP Billiton 47.11% interest)
Construction work commenced on the 250,000 tonne per annum Mozal 2 aluminium
smelter project in June 2001. At the end of September, piling was 40 per cent
complete and work on the concrete foundations for buildings and equipment has
commenced. Commitments totaling 58 per cent of budget have been made. The
project, estimated cost US$860 million (BHP Billiton share US$405 million), is
within budget and on schedule for initial production towards the end of 2003.
BHP Billiton has a 47.11 per cent share of Mozal and manages the project.
Base Metals
Escondida Phase IV Expansion, Chile (BHP Billiton 57.5% interest) BHP Billiton
and its joint venture partners in the Escondida copper mine in northern Chile
continued development activities for the Escondida Phase IV development
project during the quarter. The Phase IV expansion will increase ore
processing capacity by 85 per cent resulting in an average copper production
of 400,000 tonnes per annum (average total production of 1.2 million tonnes
per year) over the first five years.
The development has an estimated capital cost of US$1,045 million (BHP
Billiton share US$600 million). All major equipment purchases and contracting
activities have been committed. Concrete and structural steel placement in the
concentrator are well advanced and the setting of equipment has commenced in
some areas. Project mechanical completion is on track for September 2002 with
full production expected to be achieved by April 2003.
Tintaya Oxide Project, Peru (BHP Billiton 99.9% interest)
Construction of the Tintaya Oxide project continued during the quarter. The
Oxide project will increase Tintaya production by 38 per cent with a cathode
capacity of 34,000 tonnes per annum. The development has an estimated capital
cost of US$138 million. Bulk earthworks and concrete works are 95 per cent
complete. Mechanical and structural installation works are well advanced, and
piping and electrical installation have also recently started. The project is
currently on schedule and on budget (US$138 million). First cathode production
is expected in early 2002 with full production to be achieved by mid 2002.
Carbon Steel Materials
Blackwater Integration Project, Queensland (BHP Billiton 50% interest) The
project involves the creation of a single mining entity combining the South
Blackwater open cut operations with the Blackwater mine to produce an
estimated 13.5 million tonnes of coking and thermal coal a year. BHP
Billiton's equity in the project changed on 28 June 2001 as a result of the
formation of the BHP Billiton Mitsubishi Alliance (BMA).
On 25 September 2001, the mines became a single entity on an industrial and
operational basis. Commissioning is progressing well on the pre-strip fleet of
300-tonne dump trucks - a key project required to meet sales targets. These
trucks have been commissioned some 17 weeks from date of order. A dragline has
also been relocated on schedule as a complete unit some 35kms from the South
Blackwater lease. A significant number of contracts have been let for the
construction of the new industrial area at the mine site and work is
progressing. The mining operation is on target to meet the project goal of
13.5 million tonnes of saleable coal. Total project capital remains on target
of US$64 million (BHP Billiton share US$32 million).
Escondida Phase IV Expansion, Chile (BHP Billiton 57.5% interest) BHP Billiton
and its joint venture partners in the Escondida copper mine in northern Chile
continued development activities for the Escondida Phase IV development
project during the quarter. The Phase IV expansion will increase ore
processing capacity by 85 per cent resulting in an average copper production
of 400,000 tonnes per annum (average total production of 1.2 million tonnes
per year) over the first five years.
The development has an estimated capital cost of US$1,045 million (BHP
Billiton share US$600 million). All major equipment purchases and contracting
activities have been committed. Concrete and structural steel placement in the
concentrator are well advanced and the setting of equipment has commenced in
some areas. Project mechanical completion is on track for September 2002 with
full production expected to be achieved by April 2003.
Tintaya Oxide Project, Peru (BHP Billiton 99.9% interest)
Construction of the Tintaya Oxide project continued during the quarter. The
Oxide project will increase Tintaya production by 38 per cent with a cathode
capacity of 34,000 tonnes per annum. The development has an estimated capital
cost of US$138 million. Bulk earthworks and concrete works are 95 per cent
complete. Mechanical and structural installation works are well advanced, and
piping and electrical installation have also recently started. The project is
currently on schedule and on budget (US$138 million). First cathode production
is expected in early 2002 with full production to be achieved by mid 2002.
Carbon Steel Materials
Blackwater Integration Project, Queensland (BHP Billiton 50% interest) The
project involves the creation of a single mining entity combining the South
Blackwater open cut operations with the Blackwater mine to produce an
estimated 13.5 million tonnes of coking and thermal coal a year. BHP
Billiton's equity in the project changed on 28 June 2001 as a result of the
formation of the BHP Billiton Mitsubishi Alliance (BMA).
On 25 September 2001, the mines became a single entity on an industrial and
operational basis. Commissioning is progressing well on the pre-strip fleet of
300-tonne dump trucks - a key project required to meet sales targets. These
trucks have been commissioned some 17 weeks from date of order. A dragline has
also been relocated on schedule as a complete unit some 35kms from the South
Blackwater lease. A significant number of contracts have been let for the
construction of the new industrial area at the mine site and work is
progressing. The mining operation is on target to meet the project goal of
13.5 million tonnes of saleable coal. Total project capital remains on target
of US$64 million (BHP Billiton share US$32 million).
Energy Coal
San Juan Underground, New Mexico, USA (BHP Billiton 100% interest) The project
involves the development of an underground longwall mine at the San Juan
thermal coal operations in New Mexico, USA. The mine will replace production
from two of BHP Billiton's three existing surface mines. The project reached
60 per cent completion during the quarter. Three of the four portal entries
were completed, the surface conveyor system erection was 80 per cent completed
and the ventilation shaft was excavated to 270 feet (54 per cent complete).
Underground mine development reached 47,000 feet (31 per cent complete).
Approval of the prototype mining shields was achieved during September.
Project capital spending is on budget at US$146 million. The completion of
surface facilities is on schedule for March 2002. At present, underground
development mining is approximately six weeks behind schedule.
Mount Arthur North, New South Wales (BHP Billiton 100% interest) The Mount
Arthur North mine will be capable of producing up to 15 million tonnes of raw
thermal coal per annum when full production is achieved in 2006. The Project
is on schedule. Commitments for the quarter ended September 2001 total US$99
million. Capital expenditure for the quarter was US$7 million. The project has
completed its third month of an anticipated 32-month construction period.
Forecast costs to completion remain unchanged at US$411 million.
During September the design has been frozen on the Coal Handling Plant.
Engineering activities continue to focus on evaluating tenders for long
lead-time items, earthworks and concrete designs, HV power reticulation and
documentation for upcoming tender packages.
The Project Consent Agreement was signed on 5 September 2001 and is now
registered with the New South Wales Industrial Relations Commission.
PETROLEUM DEVELOPMENT
Echo Yodel, Australia (BHP Billiton 16.7%, non operated)
The Echo Yodel subsea tie-back project to the Goodwyn Alpha Platform remains
on track with production expected to commence in early 2002. Yodel 4, the
second and final well, was completed in September and hookup to the pipeline
is planned for the end of the year. The production licence has been granted.
Laminaria Phase 2 development, Australia (BHP Billiton 32.6%, non operated)
The project, entailing two new infill subsea wells tied-back to the Northern
Endeavour, is progressing as per schedule with the drill rig contract awarded
in September. The spudding of the first well is planned for January 2002.
Liverpool Bay - Hamilton East Field, UK (BHP Billiton 46.1%, operated)
The Hamilton East single subsea gas well has been successfully drilled, tested
and tied-back to the Hamilton North platform with first gas produced on 17
September 2001.
North West Shelf expansion, Australia (BHP Billiton 16.67%, non operated)
The construction of the fourth liquefaction processing train has commenced and
work on the foundations began in September. Construction of the workforce
accommodation village in Karratha has begun, with the first stage due to be
finished and occupied before the end of 2001. All long lead items have been
committed with further contracts for mechanical erection on-plot and heavy
lift cranage works to be awarded soon. Front end engineering design is
continuing for the 42-inch second trunkline with major tenders for linepipe
and pipelay contracts currently under review.
Ohanet Development, Algeria (BHP Billiton 45%, joint operating organisation
comprising SONATRACH/BHP Billiton)
The Ohanet development consists of the development of four gas/condensate
reservoirs in the Illizi Basin in southern Algeria under a Risk Service
Contract with SONATRACH. Three dimensional seismic data acquisition across all
reservoirs was completed in June 2001 and the data is currently being
processed and utilised in reservoir engineering for the development. The
development drilling program has commenced and facilities engineering is
approaching 80 per cent completion. Most major construction sub-contracts have
been award. First production is scheduled for third quarter of 2003.
ROD Integrated Development, Algeria (BHP Billiton 35.1%, joint operating
entity comprising SONATRACH/BHP Billiton)
The ROD Integrated Development involves the development of six satellite oil
fields in the Berkine Basin in eastern Algeria under a Production Sharing
Contract with SONATRACH. The formal gazettal of the Exploitation Licences for
the first five fields was received in July 2001. In addition, the RAR
discovery was declared commercial in September 2001 and an application for an
Exploitation Licence has been made. All drilling contracts have been awarded
and civil engineering for the drilling campaign is well underway. The first
contract for the long lead engineering items has been awarded and the other is
imminent. It is anticipated that the Engineer-Procure-Construct (EPC) contract
for the production facilities will be awarded in the fourth quarter 2001.
First production is scheduled for 2003.
Typhoon, Gulf of Mexico, USA (BHP Billiton 50%, non operated)
The Typhoon oilfield started production on 31 July. Production from Typhoon is
reported in the BHP Billiton Production report.
MINERALS EXPLORATION
The Exploration Group of BHP Billiton Minerals continued to carry out global
grass-roots exploration for key commodities of interest to the company.
The Junior Alliance Program (third party alliances and joint ventures) has
been greatly enhanced following the merger of BHP and Billiton. This program
emphasises the use of distinctive capabilities and innovative commercial
investments to gain the widest possible exposure to the results of third
party-funded exploration.
The two FALCON(TM) systems are continuing to fly extensive campaigns in Africa
and the Americas.
PETROLEUM EXPLORATION
Exploration and appraisal wells drilled during the quarter or in the process
of drilling as at 30 September 2001.
WELL LOCATION BHP Billiton STATUS
EQUITY
Atlantis-3 Green Canyon 44%, Operator Encountered hydrocarbon bearing
Block 743, Gulf - BP reservoirs. For more information see
of Mexico News Release of 11 October.
Atlantis-3 Green Canyon 44%, Operator For information see News Release of
ST Block 743, Gulf - BP 11 October.
of Mexico
Boris-1 Green Canyon 50% BHP Well reached total depth and was
Block 282, Gulf Billiton sidetracked updip.
of Mexico operator
East VIC/L9, Bass 50%, Cased and Suspended.
Pilchard-1 Strait,
Australia Operator -
Esso Australia
Resources
Frampton-1 Green Canyon 44% BHP Plugged & Abandoned.
872, Gulf of Billiton
Mexico Operator For more information see News
Release of 11 October.
Gnome-1 Atwater Valley 50% BHP Drilling ahead.
Block 18, Gulf Billiton
of Mexico Operator
Ika Marin-1 Tolo Block, 40.12% BHP Drilling ahead.
Gabon Billiton
Operator
Kairi-1 Trinidad Block 45% BHP Plugged & Abandoned. For more
2(c) Billiton information see News Release of 20
Operator August.
Mad-Dog-4 Green Canyon 23.9%, Plugged back and Sidetracked. For
Block 782, Gulf Operator - BP more information see News Release of
of Mexico 11 October.
Mad-Dog-4ST Green Canyon 23.9%, See News Release of 11 October.
Block 782, Gulf Operator - BP
of Mexico
Expenditure
Information related to exploration expenditure will be included in the first
quarter BHP Billiton profit report, to be released on 7 November 2001.
MINERALS COMPETENCE AND RESPONSIBILITY
The following statements apply in respect of the information in this report
that relates to any stated Mineral Resources or Ore Reserves.
* The information is based on and accurately reflects information compiled
by the person named under each relevant section of the report
* Each named person is either a Corporate Member or Fellow of The
Australasian Institute of Mining and Metallurgy or the Australian
Institute of Geoscientists, or a Recognized Mining Professional under the
ASX listing rules, and is a full-time employee of a member company of the
BHP Billiton Group;
Each named person has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and to the activity
which he or she is undertaking to qualify as a Competent Person as defined in
the 1999 Edition of the 'Australasian Code for Reporting of Mineral Resources
and Ore Reserves'. Each named person consents to the inclusion in the report
of the matters based on their information in the form and context in which it
appears.
***
Further news and information can be found on our Internet site:
www.bhpbilliton.com
Australia
Dr Robert Porter, Investor Relations
Tel:+61 3 9609 3540
Mobile: +61 419 587 456
Email: Robert.Porter@bhpbilliton.com
Mandy Frostick, Media Relations
Tel:+61 3 9609 4157
Mobile: +61 419 546 245
Email: Mandy.J.Frostick@bhpbilliton.com
United States
Francis McAllister, Investor Relations
Tel: +1 713 961 8625
Mobile: +1 713 480 3699
Email: Francis.R.McAllister@bhpbilliton.com
United Kingdom
Marc Gonsalves, Investor Relations & Communications
Tel:+44 20 7747 3956
Mobile: +44 7768 264 950
Email: Marc.Gonsalves@bhpbilliton.com
Ariane Gentil, Manager Communications
Tel:+44 20 7747 3977
Mobile: +44 7881 518 715
Email: Ariane.Gentil@bhpbilliton.com
South Africa
Michael Campbell, Investor & Media Relations
Tel:+27 11 376 3360
Mobile: +27 82 458 2587
Email: Michael.J.Campbell@bhpbilliton.com
BHP Billiton Limited ABN 49 004 028 077 BHP Billiton Plc Registration number
Registered in Australia 3196209
Registered Office: 600 Bourke Street Registered in England and Wales
Melbourne Victoria 3000 Registered Office: 1-3 Strand London
Telephone +61 3 9609 3333 WC2N 5HA United Kingdom
Facsimile +61 3 9609 3015 Telephone +44 20 7747 3800
Facsimile +44 20 7747 3900
The BHP Billiton Group is headquartered in Australia