Caledonia Mining Corporation: January 2011 Shar...
FOR: CALEDONIA MINING CORPORATION
TSX SYMBOL: CAL
OTC Bulletin Board SYMBOL: CALVF
AIM SYMBOL: CMCL
January 24, 2011
Caledonia Mining Corporation: January 2011 Shareholder Update
TORONTO, ONTARIO--(Marketwire - Jan. 24, 2011) - Caledonia Mining Corporation ("Caledonia")
(TSX:CAL)(OTCBB:CALVF)(AIM:CMCL) is pleased to provide the following update on the gold production increase and
the installation of standby generators at the Blanket Mine in Zimbabwe.
Following the successful commissioning of the No. 4 Shaft Expansion Project at the end of September 2010,
Blanket Mine commenced the production ramp-up to the targeted annualized rate of 40,000 ounces of gold by the
end of 2010. During the final 2 weeks of December, 2010, production reached an annualized rate of 39,670
ounces, determined after taking into consideration a Public Holiday on Christmas Day and downtime due to power
interruptions during this period.
Monthly gold production from September 2010 to December 2010 was as follows:
/T/
----------------------------------------------------------------------------
Month September October November December
----------------------------------------------------------------------------
Gold Production (ounces) 1,740 1,841 1,521 2,865(i)
----------------------------------------------------------------------------
(i) Includes Work in Progress
/T/
The production rate achieved by the end of 2010 is over 99 per cent of the target of 40,000 ounces per year and
represents a very substantial increase in Blanket's production capacity. More importantly the level of
production achieved at the end of December 2010 conclusively proved that key aspects of the No. 4 Shaft
Expansion Project, namely the underground crushing station, the automated skip loading system and the increased
milling capacity all operate well within their design capacity.
Blanket is now in a position to address the historic under-investment in mine development, equipment and
machinery. Underground development work has commenced in order to ensure that production levels in years to
come can be maintained, as well as providing platforms for underground exploration with a view to potentially
increasing production above the currently planned rate of 40,000 ounces per annum. This development work, in
conjunction with re-investment in equipment and machinery, is expected to have a temporary effect on production
in Quarter 1 of 2011, but it is still anticipated that Blanket will produce 40,000 ounces in 2011.
Blanket has experienced considerable unexpected delays with the delivery of the 33kV electrical switchgear
which is required for the installation and commissioning of the four generating sets. It is anticipated that
the entire 10 Megawatt generating system will be operational by the end of March 2011 at which point Blanket
will be able to maintain all mining, hauling and milling operations during interruptions to the electricity
supply. Subsequent to Blanket entering into a new supply agreement with the Zimbabwe Electricity Supply
Authority, electricity supply has been more stable. Whilst Caledonia welcomes the improvement in electricity
supply it still believes it is prudent to proceed with its plans to equip Blanket with full standby generating
capacity to safeguard production against any future power interruptions.
Further information regarding Caledonia's exploration activities and operations along with its latest
financials may be found at www.caledoniamining.com.
-30-
FOR FURTHER INFORMATION PLEASE CONTACT:
Caledonia Mining
Mark Learmonth
+27 11 447 2499
marklearmonth@caledoniamining.com
www.caledoniamining.com
OR
BuckBias
Alex Buck
+44 7932 740 452
OR
RBC Capital Markets
Martin Eales
+44 20 7029 7881
-0-
Caledonia Mining Corp
*A Private Investor is a recipient of the information who meets all of the conditions set out below, the recipient:
Obtains access to the information in a personal capacity;
Is not required to be regulated or supervised by a body concerned with the regulation or supervision of investment or financial services;
Is not currently registered or qualified as a professional securities trader or investment adviser with any national or state exchange, regulatory authority, professional association or recognised professional body;
Does not currently act in any capacity as an investment adviser, whether or not they have at some time been qualified to do so;
Uses the information solely in relation to the management of their personal funds and not as a trader to the public or for the investment of corporate funds;
Does not distribute, republish or otherwise provide any information or derived works to any third party in any manner or use or process information or derived works for any commercial purposes.
Please note, this site uses cookies. Some of the cookies are essential for parts of the site to operate and have already been set. You may delete and block all cookies from this site, but if you do, parts of the site may not work. To find out more about the cookies used on Investegate and how you can manage them, see our Privacy and Cookie Policy
To continue using Investegate, please confirm that you are a private investor as well as agreeing to our Privacy and Cookie Policy & Terms.