Operational update
Chaarat Gold Holdings Limited
("Chaarat" or the "Company")
Operational update
Road Town, Tortola, British Virgin Islands (2 November 2010)
Chaarat (AIM: CGH) is pleased to provide an update on its operations at its
principal project in Kyrgyzstan.
HIGHLIGHTS
* Chaarat's principal asset (the "Chaarat Project"), a 4Moz gold project, now
separated into two distinct projects; the Tulkubash project and the Main
project
* The Tulkubash project to be accelerated with the potential for mining to
commence in Q4 2011
* SNC Lavalin appointed to conduct a Definitive Feasibility Study on the
Tulkubash project the conclusions of which are expected in mid-2011
* Pre-feasibility Study on the Main project expected in Q1 2011
Background to the Chaarat Project and the Tulkubash and Main projects
During the course of the last few months, work has been focused on advancing the
Pre-Feasibility Study (PFS) on the Company's principal asset, the Chaarat
Project.
The PFS is aimed towards identifying and quantifying the best way of bringing
the Chaarat Project into production and has involved large batteries of
metallurgical tests which have been conducted on different parts of the deposit.
 The metallurgical testing has highlighted the fact that the Tulkubash zone has
a different mineralogy from the rest of the Chaarat Project, located in the
Contact and Main zones (now collectively referred to as the "Main project"). As
a consequence the Tulkubash deposit can be processed using a different and less
capital intensive process which presents an advantageous development route for
this part of the deposit.
The mineralisation in the Tulkubash formation is cleaner (having significantly
lower levels of sulphur, arsenic, antimony and silver) and more importantly, it
is mostly free milling and thereby much more amenable to direct cyanidation
without oxidation which is a relatively less capital and power intensive
process.
This is an important and welcome development as it will enable the Company to
reach production earlier than previously anticipated. Â In addition, bringing the
Tulkubash deposit into production earlier, will greatly simplify the process of
developing the larger Main project.
The two projects are located approximately 2 km apart and will share many
aspects such as access to the property, tailings dams and technical roads. Â The
fact that the two projects are separate means that the operations can be managed
and developed independently and, importantly, production from the Tulkubash
project will not be interrupted when the larger Main project is developed.
Preliminary testwork indicates a large proportion of the resource in the
Tulkubash project can also be mined by open pit methods. The Company is now
investigating the possibility of developing a first stage production unit
capable of mining and processing 700-1,000 tonnes of ore per day. Â The principal
characteristics of the two projects are summarised in the table below:
Characteristics of the two projects (company estimates)
 Tulkubash project Main project
Expected Mining rate (tpd) ~700-1000 ~4000-5000
Gold production rate (ozs p/a) ~40,000 ~140,000-180,000
Estimated investment (US$million) 70 300 (additional)
Estimated cash cost per ounce Not yet available Not yet available
Power source Generators(1) Power line
Mining method Mostly open pit Mostly underground
(1)Generators will be required until the power line is established for the Main
project.
The Tulkubash project
The Tulkubash quartzite formation extends along the Chaarat Project. Â Whilst the
Company had conducted geological works in this formation, it was not considered
a priority. Â Following some promising results, a sample of which are set out in
the table below, a rigorous soil sampling programme along the crest lines of the
Tulkubash area was carried out.
Sample of already announced drill results from the Tulkubash project
Drive/drill hole Intersection True width Depth Gold grade
(metres) (metres) (Au g/t)
DH-62/b 28.50 23.56 155 5.21
DH-93/b 30.00 12.79 35 4.42
DH-61 15.60 14.69 73 4.85
Adit#2 28.00 18.00 65 4.60
Including 9.00 5.78 Â 9.09
T0796 31.50 24.60 38 4.88
The results showed a large area of 4.80 km of strike showing good potential to
be included in the Tulkubash project. Â The Company undertook a significant
structural geology exercise in order to decipher the geological controls of the
mineralisation.
In addition to the drilling and soil sampling programme, important structural
information was obtained from an existing Soviet adit, which was cleared and
sampled last year. Â A sample of the findings is included in the table above.
 Initially the Tulkubash zone was intended to be included in the larger project
and as such the work on the PFS included a general outline of an open pit for
the Tulkubash area. The Company has decided to focus its exploration work on
delineating additional mineralisation which is likely to be mineable by open pit
methods. Â The 2010 exploration season is now close to completion and the Company
expects that, based on work done during the season, sufficient data will allow
the calculation of a maiden resource early in Q1 2011 and that most of it can be
mined by an open pit operation. Â The Company is confident that the Tulkubash
project incorporates a significant free milling resource and once a maiden
resource has been delineated, Chaarat will be in a position to commence
development.
In addition to the shallow drilling and trenching, some deeper holes were
drilled to follow the mineralisation down dip and establish whether underground
mining is feasible.
In order to enable "fast-tracking" of the Tulkubash project, whilst optimising
the usage of funds and development activities, the essential elements of the
Tulkubash project; mill, tailings dam, workers' camp, roads and associated
infrastructure were included as part of the PFS in the design of the Main
project. Â The geotechnical work required for detailed engineering of the
Tulkubash project has already been undertaken. Â This work will enable the
Company and its consultants to complete the design work during the winter.
Work on a Definitive Feasibility Study (DFS) for the Tulkubash project has been
commissioned. Chaarat has engaged a world class team for the DFS which will be
led by Canadian group SNC-Lavalin (SNC). SNC is an international leader in
consulting, design, engineering and construction of processing and
infrastructure facilities for the mining industry and it has been engaged to
manage and coordinate the work of a number of consultants, each providing
specific expertise. The metallurgy is being developed by another global leader,
SGS Lakefield. The process plant design will be undertaken by South African
consultants, Consulmet, in conjunction with SNC, and the costing and economic
analysis will also be prepared by SNC. Infrastructure planning and mining will
be carried out by local companies to ensure that operations comply with the
local regulatory framework with supervision and support provided by SNC. It is
anticipated that the DFS will be completed during the first half of 2011.
The Main project
Work has continued on the Main project PFS, which is being compiled by the South
African arm of the SRK Consulting Group. Â With the Tulkubash project having been
established as a separate development from the Main project, the Tulkubash ore
has been excluded from the assumed production schedule in the PFS. The process
package has been developed, the plant design completed and all the aspects of
the operation identified, designed to the required level and costed. On the
mining side, further design work is being undertaken that will incorporate
drilling data from the 2010 exploration season. The PFS is scheduled to be
finalised in Q1 2011.
The metallurgical work has been completed with the conclusion that at least 88
per cent. of contained gold will be recovered. Â The process plant has been
designed and the Company is pleased to report that, although significant changes
of operational strategy have been introduced since the scoping study, the
anticipated capital costs seem to be marginally lower than those costs outlined
in the scoping study. Â The reduction in projected capital costs is significant
as this also includes further processing equipment to enable Chaarat to produce
a higher margin metal doré as its finished product rather than concentrate.
As previously announced the selected operational strategy will be whole ore
pressure oxidation (WOPOX) followed by the CIL (Carbon in Leach) method of gold
extraction. Â Numerous tests on different ore samples support the suitability of
this technology to handle the somewhat variable mineralogy.
The WOPOX method, in addition to being economically superior, in Chaarat's case,
to any other method is an environmentally sound technology ensuring that no
hazardous contaminants are left untreated.
The Company has identified a suitable location for the process plant and
tailings dam not far from the site. Â Following significant geotechnical,
hydrological and other environmental investigations, the site was found to be
suitable and the tailings dam has been designed according to local and
international standards.
During the winter season, the Company plans a significant underground drilling
programme which, if successful, should enable us to proceed towards a full DFS
for the Main project.
 Subscription by China Nonferrous Metals International Mining Co Ltd ("CNMIM")
In connection with the placing announced on 1 July 2010, CNMIM had the option,
within 15 days, to subscribe for such number of shares at the placing price so
as to maintain its pre-placing percentage shareholding in the Company. A notice
was given to CNMIM as required under the subscription agreement.
CNMIM confirmed to the Company that it would subscribe for such number of shares
to maintain its holding, but that the necessary regulatory approvals from the
Chinese government would require more than the permitted 15 days and were likely
to be received by 31 October 2010. Chaarat has now been informed by CNMIM that
there will be an additional delay in receipt of these approvals. The
complicated and lengthy process by which a Chinese state owned enterprise is
permitted to invest in non-Chinese companies has led both companies to decide to
abandon the current anticipated investment. Instead they will seek together to
find a more efficient solution to enable CNMIM to participate on a timely basis
in future fund raisings.
Further information about the Company:
Chaarat Gold Holdings Ltd +44 (0) 20 7499 2612
c/o Central Asia Services Ltd dekel@chaarat.com
linda.naylor@chaarat.com
Westhouse Securities Limited +44 (0) 20 7601 6100
Tim Feather  tim.feather@westhousesecurities.com
Richard Baty  richard.baty@westhousesecurities.com
Smith's Corporate Advisory +44 (0) 20 7321 2508
Dominic Palmer-Tomkinson tomkinson@smiths-ca.com
Conduit PR +44 (0) 20 7429 6603
Jos Simson jos@conduitpr.com
Emily Fenton emily@conduitpr.com
Note to Editors:
About Chaarat Gold
Chaarat Gold is an exploration and development company operating in the Kyrgyz
Republic. The Company's main activity is the development of the Chaarat Main and
Tulkubash projects situated within the Middle Tien Shan Mountains of Kyrgyzstan
which form part of the Tien Shan gold belt. The Company has thus far delineated
a JORC compliant mineral resource of 4.009 Moz at a grade of 4.14 g/t gold
across both deposits. Â The Company is currently in the process of compiling a
Pre-Feasibility study on the Main Project and a Definitive Feasibility Study on
the Tulkubash project. Â Chaarat's objective is to become a low cost gold
producer targeting production of over 200,000 ounces per annum by early 2013
from the Chaarat Main project with first production from the smaller Tulkubash
project in Q4 2011
Competent Person
The Competent Person with overall responsibility for this press release, and who
has reviewed the information contained herein, is Sunit Patel M.Sc (Geology),
FGS, GSSA, who is an employee of Chaarat Gold. Mr. Patel is an exploration
geologist with 22 years of experience in the resource industry who has
sufficient experience relevant to the style of mineralisation and type of
deposit under consideration and was supervisor to the work subject of this
release.
Disclaimer
This press release includes forward-looking statements. Such forward-looking
statements involve known and unknown risks, uncertainties and other important
factors beyond Chaarat's control that would cause the actual results,
performance or achievements of Chaarat to be materially different from future
results, performance or achievements expressed or implied by such forward-
looking statements. Such forward-looking statements are based on numerous
assumptions regarding Chaarat's present and future business strategies and the
environment in which Chaarat will operate in the future. Any forward-looking
statements speak only as at the date of this document. Chaarat expressly
disclaims any obligation or undertaking to disseminate any updates or revisions
to any forward-looking statements contained in this document to reflect any
change in Chaarat's expectations with regard to these or any change in events,
conditions or circumstances on which any such statements are based. As a result
of these factors, the events described in the forward-looking statements in this
press release may not occur either partially or at all.
[HUG#1457805]
This announcement is distributed by Thomson Reuters on behalf of
Thomson Reuters clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.
Source: Chaarat Gold Holdings Ltd via Thomson Reuters ONE