Results of Pre-Feasibility Study
Chaarat Gold Holdings Limited
("Chaarat" or "the Company")
RESULTS OF PRE-FEASIBILITY STUDY
Road Town, Tortola, British Virgin Islands (30 June 2011)
Chaarat Gold Holdings Limited (AIM - CGH), the AIM quoted exploration and
development company with assets in the Kyrgyz Republic, is pleased to announce
the results of an encouraging Pre-Feasibility Study ("PFS") for the explored
section of its 100% owned Chaarat gold Project (the "Project") located in
Western Kyrgyzstan.
HIGHLIGHTS
* Mine life estimated on current resources of 13 years
* Mine has the potential to produce in excess of 200,000 ounces per annum in
full production
* Cash operating cost estimated at $501*/ounce
* all figures in United States dollars, unless otherwise noted
Dekel Golan, CEO of Chaarat, commented: "The prefeasibility study is a
substantial milestone in the long process of unlocking the value of the Chaarat
deposit, and demonstrates the robustness of the project and points the way to
its development. Furthermore the Company remains enthusiastic that these
positive results can be significantly improved with more work which can increase
the resource and reserve base and reduce costs.
"The Company is currently in the process of building an early stage production
unit for the Tulkubash project with the objective of eliminating a lot of the
uncertainty related to the infrastructure status of the project and easing
concerns related to the perception of doing business in the Kyrgyz Republic.
 The Company is comfortable that the fundraising completed earlier this year
will be sufficient to build the Tulkubash project and that additional equity
finance will not be required for this phase."
Further information about the Company:
Chaarat Gold Holdings Limited          +44 (0) 20 7499 2612
c/o Central Asia Services Limited
Dekel Golan - CEOÂ Â dekel@chaarat.com
Linda Naylor - Finance Director  linda.naylor@chaarat.com
Westhouse Securities Limited            +44 (0) 20 7601 6100
Tim Feather tim.feather@westhousesecurities.com
Richard Baty                             richard.baty@westhousesecurities.com
Bankside Consultants +44 (0) 20 7367 8888
Simon Rothschild simon.rothschild@bankside.com
PRE-FEASIBILITY STUDY
The prefeasibility study was compiled by SNC-Lavalin South Africa (Pty) Ltd in
conjunction with Chaarat employees in the Kyrgyz Republic and in the UK.
The operation described in the PFS is based initially on open pit followed by
underground mining, milling of the ore and its preparation for gold leaching by
pressure oxidation technology. The gold will be leached via a Carbon-in-Leach
("CIL") extraction circuit. Â The mine will operate at an average production rate
of 1.718 Mt of ore per annum after a commissioning period of six months. Â Over
the 13 years life of mine production will average about 202,000 ounces of gold
annually at a cash operating cost estimated at $501/ounce.
The financial analysis has been based on a gold price of $1,250/ounce which
reflects a lower price than current market value. Â No allowance has been made
for inflation or escalation. Â The discount rate used was 8%.
OPERATING HIGHLIGHTS OF THE PROJECT
Project Performance[1]
+-----------------------------------------+-----------+
| Production Data | Â |
+-----------------------------------------+-----------+
| Life of Mine | 13 years |
+-----------------------------------------+-----------+
| Annual plant throughput | 1.78Mt |
+-----------------------------------------+-----------+
| Metallurgical recovery Au | 92% |
+-----------------------------------------+-----------+
| Average annual gold production | 202,000oz |
| Â | |
+-----------------------------------------+-----------+
| Total gold produced | 2.48Moz |
+-----------------------------------------+-----------+
| Operating Costs/ Tonne Ore | Â |
| Â | |
+-----------------------------------------+-----------+
| Mining | $41.17/t |
+-----------------------------------------+-----------+
| Processing | $16.13/t |
+-----------------------------------------+-----------+
| Tailings treatment | $0.90/t |
+-----------------------------------------+-----------+
| G&A | $1.50/t |
+-----------------------------------------+-----------+
| Total Operating Cost/Tonne Ore | $59.70/t |
+-----------------------------------------+-----------+
| Cash Operating Costs/Ounce Ore | $527/oz |
+-----------------------------------------+-----------+
| Silver credit not included in cash cost | $26/oz |
+-----------------------------------------+-----------+
| Â | Â |
+-----------------------------------------+-----------+
| Capital Cost | Â |
+-----------------------------------------+-----------+
| Initial investment capital | $473.7M |
+-----------------------------------------+-----------+
| Â | Â |
+-----------------------------------------+-----------+
| Â | Â |
+-----------------------------------------+-----------+
| Economics @ $1,250/oz Au After Tax | Â |
+-----------------------------------------+-----------+
| Net Present Value After Tax @ 0% | Â $980M |
+-----------------------------------------+-----------+
| Net Present Value After Tax @ 8% | Â $354M |
+-----------------------------------------+-----------+
| Internal Rate of Return After Tax | 18.0% |
+-----------------------------------------+-----------+
| Pay back | 4 years |
+-----------------------------------------+-----------+
1. For the purpose of this study and in light of the spatial distribution of
different types of resource, a certain proportion of inferred resource was
included in the economic calculation but was not included in the reserve
calculation.
CAPITAL COSTS
Capital costs for the mine infrastructure, on-site process plant, mining
operations development and other related items have been estimated using
construction data from recently completed projects in the region and are based
on quotes from reliable suppliers. Â Mining costs include pre-stripping of the
open pit in preparation for production. Â Underground costs include portal and
access development. Â Quotations for infrastructure facilities, such as power and
the access road, were received from competent suppliers familiar with working in
the region. Â Equipment costs have mostly been based on budgetary quotations
received with an appropriate indexation of piping, electricity and metal-works
elements.
Investment Capital Cost Estimate
The investment capital cost below includes mine infrastructure during the first
year of operation. The initial capital requirement is reduced due to the
availability of operational income.
+-----------------------+------------------------+
| Category | Prefeasibility Results |
+-----------------------+------------------------+
| Â | Â Â Â Â Â Â Â Â Â Â Â Â Â |
+-----------------------+------------------------+
| Mining pre production | Â Â Â Â $51,336,000 |
+-----------------------+------------------------+
| Site Development | Â Â Â Â Â $48,000,000 |
+-----------------------+------------------------+
| Process Plant | Â Â Â $309,595,000 |
+-----------------------+------------------------+
| Infrastructure | Â Â Â Â Â $60,008,000 |
+-----------------------+------------------------+
| Tailings Disposal | Â Â Â Â Â $2,325,000 |
+-----------------------+------------------------+
| Owner's Costs | Â Â Â Â Â $21,047,000 |
+-----------------------+------------------------+
| Contingency | Â Â Â Â Â $42,094,000 |
+-----------------------+------------------------+
| Total | Â Â Â $534,405,000 |
+-----------------------+------------------------+
FINANCIAL ANALYSIS
The financial analysis of the Project uses a discounted cashflow model
incorporating the mine production schedule, estimated capital and operating
costs and local tax and royalty as are currently applied in the Kyrgyz Republic.
 The financial analysis has been based on a gold price of $1,250/oz which
reflects a lower price than current market value. Â No allowance has been made
for inflation or escalation.
Chaarat Gold Project Financial Analysis Summary
+-----------------------------------+-----------------+
| Project Data | Estimated Value |
+-----------------------------------+-----------------+
| Â | Â |
+-----------------------------------+-----------------+
| Life of Mine | 13 years |
+-----------------------------------+-----------------+
| Total gold produced | 2.48Moz |
+-----------------------------------+-----------------+
| Total ore mined | 21.9Mt |
+-----------------------------------+-----------------+
| Initial project capital cost | $473.7M |
+-----------------------------------+-----------------+
| Cash Operating Cost (years 2-11) | $501/oz |
+-----------------------------------+-----------------+
| Base Case Gold Price | $1,250/oz |
+-----------------------------------+-----------------+
| After Tax Net Present Value @ 8% | $354M |
+-----------------------------------+-----------------+
| After Tax Internal rate of Return | 18.0% |
+-----------------------------------+-----------------+
Gold Price Sensitivity Analysis
+---------------+--------+--------+---------+
| Gold Price/oz | $1,000 | $1,250 | $1,500 |
+---------------+--------+--------+---------+
| NPV @ 0% | $481 M | $980M | $1,495M |
+---------------+--------+--------+---------+
| NPV @ 8% | $60M | $354M | $660M |
+---------------+--------+--------+---------+
| IRR | 9.8% | 18% | 25.5% |
+---------------+--------+--------+---------+
PROJECT OVERVIEW
Deposit
The Chaarat deposit (the "Deposit") is a sediment-hosted, intrusion-related,
structurally controlled deposit, located in the Tien Shan belt of Kyrgyzstan.
 The Chaarat Project is located in a mountainous area along the Sandalash River
valley, on the western border of Kyrgyzstan. Â The valley marks the north-
easterly trending hinge zone of an anticline, the north-western limb of which
consists of a sequence of Upper Proterozoic and Cambrian-Ordovician
siliciclastic rocks - the Chaarat formation, which dips at around 50(0)
northwest hosts the Chaarat mineralisation. Â The formation comprises greywacke,
sandstone with siltstone, shale, rhythmically bedded siltstone and black shale
with limestone lenses and an upper tillite.
The gold mineralisation in Chaarat is defined as "deep epithermal" due to the
"epithermal" element suite - Au, Ag, Sb and As, typical of those found in
similar deposits within the Tien Shan belt. Mineralisation is associated with a
series of sericiticaly altered sulphide rich lodes, within a quartzitic and
shale rich meta-sedimentary succession. Â The lodes occur in three mineralised
structures; the Main Zone, the Contact Zone and the Tulkubash Zone. Â The
mineralised zones are generally developed sub-parallel to the strike and dip at
between 45 and 90 degrees. Â The gold mineralisation is associated with Ag and As
mineralisation.
RESOURCE ESTIMATION
The resource estimate announced on 7 February 2011 was compiled from all core
drill holes completed on 10 sub-project areas at Chaarat to date. Â The 282 holes
(totalling 57,677 m) included in the resource estimate were drilled on the three
sub-parallel zones of mineralisation at Chaarat, the Main, the Contact and the
Tulkubash Zones, which are characterised by mineralisation up to 37 metres wide
and dipping at 45 to 90 degrees to the northwest. Â In all project areas the
mineralisation remains open down dip, and on the majority, also along strike.
 The bulk of mineralisation has been delineated in three clusters; the Contact
project cluster 2,093,000oz the Main Zone cluster (projects M2400, M3000, M3400
and M3900 totalling 1,734,000oz) and the Tulkubash zone (321,000oz).
The resource database contains 56,458 gold assay records from surface, adit and
drill-core samples. Â In addition, Wardell Armstrong International ("WAI") has
reviewed 4,027 umpire assays, 1,328 results of reference materials and 2,450
blanks sent to three laboratories and concluded that the quality and quantity of
data are sufficient to support the Mineral Resource estimates reported.
Samples were prepared and assayed at the Stewart Group laboratories in Bishkek.
 Analysis for gold was done on sawn half core samples using fire assay methods.
 Standard reference materials, blank and field duplicate samples were inserted
prior to shipment from site to monitor the quality control of the assay data.
 The resource estimate was made from a 3D block model utilising commercial mine
planning software. Â Mineralised shells were generated using a cut off gold grade
of 2 g/t. Â The grade interpolation estimated values for gold using ordinary
kriging.
Mineral Resources
+----------------+-------------+--------------+-------------+
| Classification | Tonnes '000 | Grade g/t Au | Ounces '000 |
+----------------+-------------+--------------+-------------+
| Indicated | 13,238 | 4.30 | 1,841 |
+----------------+-------------+--------------+-------------+
| Inferred | 19,190 | 4.20 | 2,565 |
+----------------+-------------+--------------+-------------+
| Total | 32,428 | 4.20 | 4,406 |
+----------------+-------------+--------------+-------------+
1. Mineral resources at the Chaarat Project are reported at 2 g/t Au cut-off
grade.
2. The contained gold represents estimated contained metal in the ground and has
not been adjusted for the metallurgical recoveries of gold.
3. Sunit Patel, M.Sc. (Geology), FGS, GSSA, who is an employee of Chaarat is the
qualified person responsible for the Chaarat mineral resource estimate.
Reserve and Resource Estimation
A&B Global Mining, a South African firm specialising in mine design and reserve
evaluation, were retained to prepare the reserve estimation for the project. Â In
certain areas of the mineralised body the Indicated and Inferred resources were
spatially organised in such a way that the mine design had to include some of
the 60% of the inferred resource as mineable material. Â No inferred resource was
included in the Probable reserve, but the mineable portion of the inferred
resource was included in the economic analysis of the Project.
The mine design, reserve estimate, mining costs and mining fleet requirements
for the project were prepared by A&B Global Mining.
Reserve Statement of the Chaarat project
+---------------------------------------------+------+------+----+------+------+
|Classification |Tonnes| Grade| Au| Grade|Ag Moz|
| | '000|g/t Au| Moz|g/t Ag| |
+---------------------------------------------+------+------+----+------+------+
|Probable Reserve |12,555| 4.02|1.62| 12.66| 5.11|
+---------------------------------------------+------+------+----+------+------+
|Mineable Inferred Resource |11,658| 3.54|1.33| 10.01| 3.75|
+---------------------------------------------+------+------+----+------+------+
|Material considered mineable (Probable |24,213| 3.78|2.95| 11.38| 8.86|
|reserve and inferred resource) | | | | | |
+---------------------------------------------+------+------+----+------+------+
1. The open pit cutoff grade to economic limits has been calculated dynamically
by the open pit optimisation software (Datamine NPVS) and for underground 2.41
g/t for cut and fill and 2.29 g/t for sub level open stoping (SLOS) mining
method is used. Â The gold price is assumed to be $1,200/ounce.
2. The reserves evaluation for the open pit and the underground project is
scheduled with all resources, and the reserve statement and reserve evaluation
was undertaken in accordance with NI43-101 guidelines.
MINING
The mine would be operated as both open pit and underground mining operations to
achieve the designed rate of 4,000-5,000 tonnes per day.
Open pit
The open pit mine is designed for conventional multiple open pit operations
using 40t dump trucks with 90/35t class excavators for a five year Life of Mine
(LOM) to produce at a peak mining rate of 48Mt of material and 1.69Mt of ore per
year with production starting from year one. Â Waste rock will be hauled to a
dedicated waste dump adjacent to the open pit. Â Ore will be transported to the
plant through aerial ropeway and trucks on an ongoing basis.
Underground
The deeper extension of the ore bodies at Kiziltash below the economic pit
limits would be mined by underground mining operations to produce approximately
17Mt of 15 year LOM. Â This will involve approximately 120,000 metres of waste
development and 12,000 metres of ore development. Â The total waste handling
would be just over 9Mt.
Drilling will be done with fully mechanised twin and single boom jumbo drill
rigs. Â Loading and hauling will be done by LHD loading (3t/5t) and dump truck
hauling (20t).
Mining rate and grade
The mine design was generated in order to maximise the minable material. It has
been recognised however, by SNC Lavalin as well as the Company, that it would be
beneficial to change the ROM grade at the expense of LOM. A&B Global estimate
that the re-design of the mine will reduce the LOM (based on known resource)
from 16 to 13 years, but that the resulting grade will be 3.85g/t as against
3.51g/t in the maximised version. The lower LOM with higher grade scenario was
used by the Company in the financial models.
Metallurgy
Extensive metallurgical testwork has defined that the most effective gold
recovery process for Chaarat is whole ore pressure oxidation followed by
cyanidation to produce gold and silver doré.  Overall gold recovery using this
process has been estimated at 92%. Â Based on these design criteria a
conventional crushing, screening and grinding circuit has been designed using
three stages of crushing followed by a ball mill. Â The milled material after
treatment for pH adjustment and pre heating is fed into an autoclave where it is
heated under pressure in the presence of oxygen to oxidise the sulphidic
minerals. Â The oxidised material is fed into a CIL battery of tanks where it is
stripped of gold. Tailings from the CIL circuit will be detoxified prior to
disposal in a conventional tailings dam.
The plant will be operated continuously with a planned throughput of 1,850,000t
per year. Â Annual gold production will average approximately 202,000oz with a
total of 2.48Moz of gold to be recovered over the life of the mine.  Doré
produced on site will be sold for further refining.
In order to reduce the technological risk, initially or in general, it is
possible to add a flotation circuit and process the flotation concentrate by the
same POX method. Â The gold recovery from the concentrate will improve to 95% but
as the gold collection to the concentrate will only be 86%-90%, the overall gold
recovery was conservatively estimated to be 82% for this scenario. Â This
alternative was not evaluated at the same level of detail as the whole ore
treatment.
Infrastructure
Access Road
The Chaarat deposit licence area is situated in the Sandalash River valley in
the north west of Kyrgyzstan. Â The only existing road access was constructed by
Soviet Geological Survey teams in the early 1970's. This access road starts in
the Chatkal Valley some 23km north of the village Kanysh-Kiya and routes over
the Kumbel Pass at 3,250 metres to the Sandalash Valley, a road distance of
approximately 30km.
A review of the upgrade of the access road, carried out by local company ECO-
Service, has indicated that this original route can be followed and developed
with expansion of the hairpin radii and adjustment to the incline angles in
several areas. Â The cost of upgrading the road has been included in the capital
cost of the project.
Power Supply
Two main options exist for supplying the required estimate of 25MW external
power supply to the Project. Â Both involve the construction of a 110kV power
line. Â One option is to construct a power line from the Kristal substation
through the Chatkal Ridge, a distance of some 160km. Â The other option is to
connect to the northern part of the Kyrgyz Republic grid near the town of
Kirovka. Â The Company has already been granted a power quota from the Kristal
location, but as a result of changes in the organisation of the national grid
organisation, the northern line towards Kirovka is a cheaper and better option.
Both options require the construction of a 20 km 110KVA power line from the
Chatkal valley road to the deposit as well as a distribution network (for mine,
plant, camps, etc.) as well as backup generating system. Â The contract for this
line, which is the main construction challenge, as well as the backup generating
unit and internal distribution is currently being negotiated and their
construction will commence immediately on signing of the contract.
It should be noted that the option of a power line from Kirovka was not included
in the PFS work.
Operating Costs
Life of mine operating cost is estimated to be $59.70 per tonne of ore mined,
excluding production royalties. Â This cost leads to a cash cost of production of
$501 per oz of gold produced (assuming $26 credit from silver production) for
the whole ore processing solution. The numbers include mining, processing,
tailings treatment and general and administrative costs.
Risk Analysis
Risk management on all projects and studies is a critical aspect of project
management. SNC-Lavalin recognises the significance of analysing risks and
opportunities and providing mitigation strategies on an ongoing basis,
particularly the risks associated with operating technically advanced circuits
in remote locations.
In light of this, SNC-Lavalin provided strong input into the process flowsheet
development. The design of the plant was carefully considered to minimise any
unnecessary risks. In light of this, the flowsheet is considered to be
commercially proven technology. All the primary process units are considered to
be low risk.
Next steps
In early 2011 the Company raised a total of $80 million (net) which will enable
it to commence the construction of certain elements of the infrastructure and a
small capacity mine to treat the free milling segment of the ore. Â The Company
is actively pursuing the strategy of construction of the smaller Tulkubash
Project. Â At the same time significant exploration effort, as well as
engineering work, is focused on finding ways to improve the NPV and IRR of the
project as a whole.
NOTES
This report combines the input from different sources. Â The aspects related to
the processing plant capital and operating costs have been estimated by SNC-
Lavalin South Africa (Pty) Ltd office.
The aspects related to reserve calculation and the associated capital and
operating costs have been estimated by A&B Global Mining.
The resource estimate on which the work was based is the resource estimation
prepared by Wardell Armstrong International which was announced on 7 February
2011.
The financial analysis to generate net present value, internal rate of return
and tax calculations was carried out by the Company.
SNC-Lavalin South Africa (Pty) Ltd, incorporated the infrastructure design,
capital and operating costs into the PFS. The resource calculation was done by
Wardell Armstrong International.
About Chaarat Gold
 Chaarat Gold is an exploration and development company operating in the Kyrgyz
Republic. The Company's main activity is the development of the Kiziltash and
Tulkubash projects situated within the Middle Tien Shan Mountains of Kyrgyzstan,
which form part of the Tien Shan gold belt. The Company has delineated a JORC
compliant mineral resource of 4.406Moz at a grade of 4.20g/t gold across both
projects. Chaarat's key objective is to become a low cost gold producer; with
initial production from the Tulkubash project, targeting annual production of
over 200,000 ounces per annum as the Kiziltash project comes on stream.
www.chaarat.com
Disclaimer
This press release includes forward-looking statements. Such forward-looking
statements involve known and unknown risks, uncertainties and other important
factors beyond Chaarat's control that would cause the actual results,
performance or achievements of Chaarat to be materially different from future
results, performance or achievements expressed or implied by such forward-
looking statements. Such forward-looking statements are based on numerous
assumptions regarding Chaarat's present and future business strategies and the
environment in which Chaarat will operate in the future. Any forward-looking
statements speak only as at the date of this document. Chaarat expressly
disclaims any obligation or undertaking to disseminate any updates or revisions
to any forward-looking statements contained in this document to reflect any
change in Chaarat's expectations with regard to these or any change in events,
conditions or circumstances on which any such statements are based. As a result
of these factors, the events described in the forward-looking statements in this
press release may not occur either partially or at all.
Glossary of Technical Terms
"assay" qualitative or quantitative analysis of a metal or ore to
determine its components
"Ag" chemical symbol for silver
"As" chemical symbol for arsenic
"Au" chemical symbol for gold
"CIL" Carbon-in-Leach
"cut-off grade" the lowest grade value that is included in a resource
statement. It must comply with JORC requirement 19:
"reasonable prospects for eventual economic extraction" the
lowest grade, or quality, of mineralised material that
qualifies as economically mineable and available in a given
deposit. It may be defined on the basis of economic
evaluation, or on physical or chemical attributes that
define an acceptable product specification
"Inferred Resource" that part of a Mineral Resource for which tonnage, grade
and mineral content can be estimated with a low level of
confidence. It is inferred from geological evidence and
assumed but not verified geological and/or grade
continuity. It is based on information gathered through
appropriate techniques from locations such as outcrops,
trenches, pits, workings and drill holes which may be
limited or of uncertain quality and reliability
"Indicated Resource" that part of a Mineral Resource for which tonnage,
 densities, shape, physical characteristics, grade and
mineral content can be estimated with a reasonable level of
confidence. It is based on exploration, sampling and
testing information gathered through appropriate techniques
from locations such as outcrops, trenches, pits, workings
and drill holes. The locations are too widely or
inappropriately spaced to confirm geological and/or grade
continuity but are spaced closely enough for continuity to
be assumed
"JORC" The Australasian Joint Ore Reserves Committee Code for
Reporting of Exploration Results, Mineral Resources and Ore
Reserves, 2004 (the "JORC Code" or "the Code"). The Code
sets out minimum standards, recommendations and guidelines
for Public Reporting in Australasia of Exploration Results,
Mineral Resources and Ore Reserves
"kriging" an inverse distance weighting technique where weights are
 selected via the variogram according to the samples'
distance and direction from the point of estimation. The
weights are not only derived from the distance between
samples and the block to be estimated, but also the
distance between the samples themselves. The kriging
estimates are controlled by the variogram parameters which
are interpreted from the data
"Measured Resource" that part of a Mineral Resource for which tonnage,
densities, shape, physical characteristics, grade and
mineral content can be estimated with a high level of
confidence. It is based on detailed and reliable
exploration, sampling and testing information gathered
through appropriate techniques from locations such as
outcrops, trenches, pits, workings and drill holes. The
locations are spaced closely enough to confirm geological
and grade continuity
"Mineral Resource" a concentration or occurrence of material of intrinsic
economic interest in or on the Earth's crust in such form,
quality and quantity that there are reasonable prospects
for eventual economic extraction. The location, quantity,
grade, geological characteristics and continuity of a
Mineral Resource are known, estimated or interpreted from
specific geological evidence and knowledge. Mineral
Resources are sub-divided, in order of increasing
geological confidence, into Inferred, Indicated and
Measured categories when reporting under JORC
"Moz" million troy ounces
"Mt" million tonnes
"ordinary kriging" commonly used type of kriging which assumes a constant but
 unknown grade
"oz" troy ounce (= 31.103477 grammes)
"Sb" the chemical symbol for antimony
"swath analysis" used to validate a block estimate by comparing a selected
block with a composite of the data in that block
"t" tonne (= 1 million grammes)
"variogram" a method of displaying and modelling the difference in
grade between two samples separated by a distance "h",
called the "lag" distance. It provides the mathematical
model of variability with distance and is used during
kriging
"wireframe" this is created by using triangulation to produce an
isometric projection of, for example, a rock type,
mineralisation envelope or an underground stope. Volumes
can be determined directly of each solid
This announcement is distributed by Thomson Reuters on behalf of
Thomson Reuters clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.
Source: Chaarat Gold Holdings Ltd via Thomson Reuters ONE
[HUG#1527086]