20 December 2017
DRAX GROUP PLC
(Symbol: DRX)
Biomass Outage at Drax Power Station
Following an unplanned outage on the rail unloading facilities at Drax Power Station, biomass deliveries are currently restricted and, in order to optimise available supplies, generation on the two ROC(1) units has been reduced. These two units will then be taken offline for a short period. The CfD(2) unit and coal operations remain unaffected.
The outage on the rail unloading facilities is currently expected to be completed during January 2018, at which point the ROC(1) units should return to service.
Reflecting the outage and reduced generation on the ROC(1) units, Drax currently expects a reduction in EBITDA(3) of £10 million in 2017.
Enquiries:
Investor Relations:
Mark Strafford
+44 (0) 1757 612 491
Media:
Ali Lewis
+44 (0) 1757 612 165
Website: www.drax.com
END
Notes
1) Renewable Obligation Certificate.
2) Contract for Difference.