Balasausqandiq Feasibility Study Update

RNS Number : 2337K
Ferro-Alloy Resources Limited
20 December 2022
 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 which is part of       UK law by virtue of the European Union (Withdrawal) Act 2018.

 

 

20 December 2022

Ferro-Alloy Resources Limited

("Ferro-Alloy" or "the Company")

 

Balasausqandiq Feasibility Study Update

 

Ferro-Alloy Resources Limited (LSE:FAR), the vanadium producer and developer of the large Balasausqandiq vanadium deposit in Southern Kazakhstan , is pleased to announce an update on the ongoing feasibility study ("Feasibility Study") into the large Balasausqandiq vanadium project.

 

Drilling

As previously announced, the drilling programme for Phase 1 of the Feasibility Study has been completed and an updated resource estimate for Phase 1 will be announced during Q1 2023. Similarly, the drilling programme for Phase 2 of the Feasibility Study has been completed as far as possible and the Company is assessing drilling options for a residual area of difficult topography.  

 

Metallurgy

Metallurgical test-work continues to advance at SGS Lakefield under the supervision of TetraTech.

Extraction of vanadium during acid leaching continues to be above expectations with 94-97% vanadium extraction into solution.  The test-work programme will also complete subsequent phases of vanadium, uranium, molybdenum and potassium alum extraction stages, and solid liquid separation tests.  

 

Carbon

Additional technical studies are advancing to understand and validate the potential use of the carbon-rich tailings for the production of a carbon black substitute for the making of rubber and as a feed for the production of ferro silicon.

 

Feasibility Study Engineering

The open pit geotechnical drilling has commenced and will continue into 2023.  The results of the drilling and subsequent mechanical testing programme will be used to confirm the open pit slope design.  In addition, a geophysical survey of the water supply bore field area is underway.  The results of the survey will be used to define the fieldwork programme required to define the water extraction bore field required to support the projects water needs. 

The open pit hydrogeology drilling is currently being contracted per the scope defined by SRK Consulting (Kazakhstan) Limited.  The drilling is expected to commence in early 2023.

 

Publication Timetable

As previously announced, the Company's Feasibility Study for Phase 1 of the project (processing 1 million tonnes of ore per year) was expected to be published during the middle of 2023.

Following unscheduled delays during the course of 2022, in the main as a result of capacity issues within the mineral analysis industry, the Company now expects the Feasibility Study for Phase 1 of the project to be published during Q4 of 2023 as opposed to the middle of 2023 as previously reported.  

 

ENDS

 

For further information,   visit   www.ferro-alloy.com   or   contact:

 

Ferro-Alloy Resources Limited

Nick Bridgen (CEO) / William Callewaert (CFO)

 

info@ferro-alloy.com

 

Shore Capital

(Joint Corporate Broker)

Liberum Capital Limited

(Joint Corporate Broker)

Toby Gibbs/John More

 

Scott Mathieson/William King

 

+44 207 408 4090

 

+44 20 3100 2000

 

St Brides Partners Limited

(Financial PR & IR Adviser)

Catherine Leftley/Ana Ribeiro

+44 207 236 1177

 



 

About Ferro-Alloy Resources Limited:

The Company's operations are all located at the Balasausqandiq deposit in the Kyzylordinskaya Oblast in the South of Kazakhstan. Currently the Company has two main business activities:

a) the high grade Balasausqandiq vanadium project (the "Project"); and

b) an existing vanadium concentrate processing operation (the "Existing Operation").    

Balasausqandiq is a very large deposit, with vanadium as the principal product together with several by-products. Owing to the nature of the ore, the capital and operating costs of development are very much lower than for other vanadium projects.    

A reserve on the JORC 2012 basis has been estimated only for the first ore-body (of five) which amounts to 23 million tonnes, not including the small amounts of near-surface oxidised material which is in the Inferred resource category. In the system of reserve estimation used in Kazakhstan the reserves are estimated to be over 70m tonnes in ore-bodies 1 to 5 but this does not include the full depth of ore-bodies 2 to 5.    

There is an existing concentrate processing operation at the site of the Balasausqandiq deposit. The production facilities were originally created from a 15,000 tonnes per year pilot plant which was then adapted to treat concentrates and expanded. Further expansion is being undertaken which is expected to result in annualised production capacity of around 1,500 tonnes of contained vanadium pentoxide plus significant by-product molybdenum.    

The strategy of the Company is to develop both the Project and the Existing Operation in parallel. Although they are located on the same site and use some of the same infrastructure, they are separate operations.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDBIBDDLGBDGDC
UK 100

Latest directors dealings