Gravelotte Emerald Mine Update

URA Holdings PLC
28 June 2023
 

NOT FOR RELEASE, PUBLICATION OR DISTRIBUTION, IN WHOLE OR IN PART, DIRECTLY OR INDIRECTLY, IN OR INTO OR FROM THE UNITED STATES, AUSTRALIA, CANADA, JAPAN, THE REPUBLIC OF SOUTH AFRICA OR ANY OTHER JURISDICTION WHERE IT IS UNLAWFUL TO DISTRIBUTE THIS ANNOUNCEMENT.

 

2014/596/EU (WHICH FORMS PART OF DOMESTIC UK LAW PURSUANT TO THE EUROPEAN UNION (WITHDRAWAL) ACT 2018) ("UK MAR"). UPON THE PUBLICATION OF THIS ANNOUNCEMENT, THIS INSIDE INFORMATION (AS DEFINED IN UK MAR) IS NOW CONSIDERED TO BE IN THE PUBLIC DOMAIN.

 

 

URA Holdings plc

("URA" or the "Company")

 

Gravelotte Emerald Mine Update

URA Holdings plc, the Main Market listed exploration company with assets in both the Republic of South Africa and Zambia, is pleased to announce an operational update for its 74% owned Gravelotte Emerald Mine ("GEM" or Gravelotte").

Highlights

·    Significant on site work completed as part of preparing for the restart of mining operations at the Gravelotte Emerald Mine.

·    The following items have now been completed:

Upgrade of water supply and water storage capacity available for processing operations

Completion of site security upgrades and electrical fencing

Establishing, rehabilitating and upgrading of the main haulage roads between the open pits and processing plant

Rehabilitating and upgrading of the main electrical infrastructure

Approximately 1.5ha of historic gold slimes and tailings have been rehabilitated

Management accommodation has been refurbished

Upgrading of the dewatering and screening circuit#

Engineering drawings completed to upgrade the existing processing plant and include an additional crushing and milling circuit as well as a vibrator to increase throughput.

 

Edward Nealon, Chairman of URA commented:

"Following the establishment of the first ever JORC resource for the historic Gravelotte Emerald mine we are now focussing our activities on preparing for the recommencement of mining and processing operations. Although we are fortunate to already have significant historic mine infrastructure in place the infrastructure still needs to be repaired and upgraded as part of the restarting of mining and processing operations. I would like to thank our team on the ground in South Africa for all their hard work and dedication to get us ever closer to restarting mining operations on a very tight budget."

 

Enquiries:

 

URA Holdings plc

Chief Executive Officer

Bernard Olivier

 

Chief Operating Officer
Jeremy Sturgess-Smith

 

+44 (0)746 368 6497

 

 

 

 

info@uraholdingsplc.co.uk

 

 

Peterhouse Capital Limited

Corporate Broker

Lucy Williams

Duncan Vasey

+44 (0)20 7469 0930

 

Site Improvements

During the year to date the Company has made significant progress with upgrading the critical infrastructure at the Gravelotte Emerald mine in preparation for the restart of mining and processing activities.

 

Water storage and availability

The current levels of available water for processing activities have increased to approximately 14million litres. The total water storage capacity on site has been upgraded to approximately 20 million litres. Water reclamation infrastructure continues to be further upgraded in order to ensure maximum recovery once operations commence.

 

Security Upgrades

On-site security has now been upgraded with over 10km of electric fencing around the site perimeter and high risk areas. Additional fire breaks have also been created and existing fire breaks have been cleared in preparation for the winter fire season.

 

Haulage roads

Approximately 7km of main haulage roads on site as well as the access road to the part of the open pit where mining is scheduled to recommence has been rehabilitated, upgraded or established (See Figure 1) 

 

Rehabilitation of historic disturbance

Approximately 1.5ha of historic gold slimes and tailings have been rehabilitated. This represents over 50% of the total rehabilitation requirement.

 

Electrical infrastructure

Over 80 High voltage electrical poles have either been replaced or re-treated. An additional  11KV 380V transfer has been installed and electrical conductors and switch gear has been replaced and updated (see Figure 2)

 

Accommodation

Upgrades to accommodation continues and all current staff and management are now accommodated on site

 

 

 

Processing Plant Upgrades

Upgrades to the dewatering and screening circuit has been completed (see Figure 3 and 4). Engineering drawings have been completed to upgrade the existing processing plant and include vibrating screens as well as an additional crushing and milling circuit. This will create additional surge and throughput capacity. The local procurement of suitable high-quality second-hand equipment and components has commenced.

 

For the purposes of UK MAR, the person responsible for arranging the release of this announcement on behalf of URA is Jeremy Sturgess-Smith, Chief Operating Officer of URA Holdings Plc.

 

 

 

Figure 1. On site road construction in progress

Figure 2. Upgrades to the electrical circuits at the processing plant.

Figure 3. Installation of the dewatering screen.

Figure 4. View of the completed screening and dewatering circuit of the processing plant.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
Investor Meets Company
UK 100