Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR"). With the publication of this announcement, this information is now considered to be in the public domain.
11 October 2018
InfraStrata plc
("InfraStrata" or the "Company")
Islandmagee Gas Storage Project Update - Major FEED Milestone Completed
InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to provide an update on FEED ("Front End Engineering Design") progress for its Islandmagee gas storage project (the "Project"), having now achieved nearly 70% of the pre-established milestones (11/16).
FEED commenced in May 2018 and is scheduled to be delivered in accordance with the EU Grant provisions. The reports required by the EU are anticipated to be submitted within Q4 2018. FEED remains on budget with no significant issues being uncovered. Milestone 11 has now been completed, following excellent endeavours by our FEED contractors Costain and DEEP. to achieve this ahead of schedule.
Current Milestone Progress
Milestone |
End of Month |
Description |
|
Status |
1 |
April |
Contract Award Costain |
InfraStrata |
√ - Completed |
2 |
May |
Contract Award DEEP |
InfraStrata |
√ - Completed |
3 |
May |
Appointment of Subsurface Expert |
InfraStrata |
√ - Completed |
4 |
May |
Issue FEED schedule, project and quality plans |
Costain |
√ - Completed |
5 |
May |
Current Design Agreed |
Costain |
√ - Completed |
6 |
June |
Current Design Agreed |
DEEP KBB |
√ - Completed |
7 |
June |
Appoint Owners Engineer |
InfraStrata |
√ - Completed |
8 |
July |
Issue Process Flow Diagrams |
Costain |
√ - Completed |
9 |
August |
Gas & Leaching layout review |
Costain |
√ - Completed |
10 |
August |
All Process & Instrumentation Diagrams |
Costain |
√ - Completed |
11 |
Oct. |
Engineering Design Complete |
Costain |
√ - Completed |
12 |
Oct. |
All Investigation work on samples complete |
DEEP KBB |
|
13 |
Oct. |
Cavern Design & Rock Mechanics Complete |
DEEP KBB |
|
14 |
Nov. |
Surface FEED Deliverables & Estimates |
Costain |
|
15 |
Nov. |
Subsurface FEED Deliverables & Estimates |
DEEP KBB |
|
16 |
Dec. |
Submit Reports To EU |
InfraStrata |
|
The engineering design that has been completed is intended to position InfraStrata's proposed Islandmagee facility as a globally competitive and technologically advanced, fast-cycle, pioneering gas storage facility. Costain, DEEP, Atkins and WSP have all worked together seamlessly to ensure the best possible outcome for InfraStrata.
The Expression of Interest ("EOI") period has now ended and its many responses are currently being evaluated prior to a bid pack being issued to the selected EPC (engineering, procurement, and construction) contractors in December of this year. Work continues at pace to examine ways for potential enabling works to be undertaken between FEED completion and final investment decision ("FID").
Advanced discussions continue between InfraStrata and potential project equity providers and offtake partners.
John Wood, Chief Executive Officer commented "Completion of the Project's Engineering Design is a major fundamental milestone for InfraStrata. We still have some milestones left to complete prior to completing FEED, however, with the information we have to date we do not foresee any issues and expect to complete FEED on time and on budget."
For further information, please contact:
InfraStrata plc John Wood, Chief Executive
|
c/o Yellow Jersey +44 (0)20 3735 8825 |
Allenby Capital Limited (AIM Nominated Adviser & Joint Broker) Jeremy Porter / Alex Brearley / Liz Kirchner
|
+44 (0)20 3328 5656 |
SI Capital Limited (Joint Broker) Nick Emerson
|
+44 (0) 20 3871 4038 |
Yellow Jersey Tim Thomson |
+44 (0)20 3735 8825 |
-ENDS-
Notes to editors:
InfraStrata is an independent gas storage company focused on the UK and Ireland. Further information is available on the Company's website: www.infrastrata.co.uk.
Background on the Islandmagee Storage Project
The Islandmagee gas storage project is a proposed salt cavern gas storage facility located on Islandmagee in County Antrim, Northern Ireland. The Board of InfraStrata believes that the proposed 500 million cubic metres Natural Gas Cavern Storage facility will provide over 25% of the UK's Natural Gas Storage once constructed, and will be situated adjacent to the Scotland Northern Ireland (gas) Pipeline (SNIP) and the Moyle 500 Megawatt Electricity Interconnector. Work commenced in 2007 with the acquisition of 3D seismic data to image the Permian salt in the Larne Lough area. During 2012, planning permission was granted for the project and a gas storage licence was issued by the Utility Regulator. In 2015 a well was drilled to core the salt and confirm the technical feasibility of the project, supported in part by the European Commission. The Front End Engineering and Design (FEED) element of the Project is scheduled for completion by the end of 2018. To date approximately £11.5m has been invested in the project.
Further information is available on the company's website: www.infrastrata.co.uk
The Front End Engineering & Design (FEED) and Insitu Downhole Testing programme for the Islandmagee gas storage project is co-financed by the European Union's Connecting Europe Facility.