Projects Status Update

RNS Number : 5732Q
Jubilee Metals Group PLC
07 June 2018
 

Jubilee Metals Group PLC

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

("Jubilee" or "the Company")

 

Projects Status Update

 

Projects Highlights

 

·    Hernic project achieves record  production of 2 101 PGM* ounces for the month of May with Q2 2018 already touching 4 000 PGM ounces in the first two months 

·    First PGM material from PlatCro targeted for delivery to Northam in June 2018

·    Construction of Kabwe project underway with initial focus on the zinc leach circuit

·    Implementation of the fine chrome recovery circuit at DCM underway

* 6 Element Platinum Group Metals

 

Leon Coetzer, Chief Executive Officer, says: "

 

I am particularly pleased with the performance of our Hernic operation.  The Hernic operation continues to set new benchmarks quarter on quarter with May setting a new record high delivering an impressive 2101 PGM ounces.  At the current production rates we are expecting to increase the production of PGM ounces by more than 20% during Q2 2018 compared with Q1 2018.

 

We have awarded the transport contract to commence with the delivery of ourPlatCro PGM material  to Northam Platinum for the recovery of the PGM's.. 

The construction of our Kabwe project is underway following the reinstatement of the mining licence by the Zambian authorities. Our initial focus is on the implementation of the zinc recovery circuit. I will provide further details and clarity on the project following my presentation to the Zambian Mining Department later this month.   

 

At DCM we have commenced with the implementation of the hydro-mining circuit to replace the mechanical reclamation of the tailings material. This switch-over forms part of the installation of the integrated fine chrome recovery circuit which is the pre-cursor to the platinum recovery circuit at DCM."

 

 

 

 

Hernic Platinum and Chrome Operation (South Africa)

 

The production rate during the first two months of Q2 2018 continues to show a significant increase in PGM ounces compared with the previous quarter.  Production during May 2018 has set a new record high for the operation of 2 101 ounces, an increase of 12% on the previous reported high.  The ounces produced to date for Q2 2018 equals 3 972 with a target being set of 6 000 ounces for the full quarter (equates to a targeted growth of 22.5% quarter-on-quarter). The corresponding financial numbers for the quarter-to-date is yet to be finalised.

 

Production performance of the Hernic project for Q1 2018 and Q2 2018 month-to-date as follows:

 

 

Tailings processed Tonnes

PGM Ounces delivered*

 

 

 

Jan-18

        26 073

            1284

Feb-18

        38 052

            1755

Mar-18

        46 284

            1858

Q1 2018

      110 409

            4897

Apr-18

        39 458

            1871

May-18

        39 734

            2101

Jun-18

-

-

 Q2 2018**

        79 192

3 972

 

 

 

Project to date

      497 745

          16305

*Ounces calculated based on assays received to date and subject to final metal accounting.

**Quarter 2 2018 numbers include only the months of April and May 2018.

 

PlatCro Platinum Project (South Africa)

 

Jubilee executed a processing agreement with Northam Platinum's Eland Platinum operation to process the PlatCro PGM material as announced in April 2018.  The project targets the processing of 60 000 tonnes of PGM material per month equating to the production of approximately 2 800 PGM ounces per month.  Jubilee has awarded the transport contract for the delivery of the PGM material and the first delivery to Northam is expected to commence during June 2018.

 

Kabwe Zinc, Lead and Vanadium Project (Zambia)

 

Our Jubilee and BMR teams are hard at work with the construction of the Kabwe project in Zambia.  The initial construction focus is on the zinc primary leach recovery circuit.

 

The lead and vanadium project schedule will be concluded following completion of the circuit optimisation work currently undertaken by Jubilee. The circuit optimisation test work by Jubilee's research and development team includes work to evaluate the optimal product purity specifications. Further detail relating to the project's implementation schedule and design specifications will be provided following the presentation to the Zambian Mining Authorities during June 2018.

 

Clarification note on settlement of historical creditors by BMR Group PLC ("BMR")

 

Jubilee wishes to clarify the conditions under which Jubilee has agreed to allow BMR to allocate a portion of its existing holding of Jubilee shares to settle certain approved BMR creditors.

 

Under the agreement reached with BMR, such number of Jubilee shares as required to settle the approved creditors will be placed into a Jubilee nominated broker account ("transferred shares").  The transferred shares will be now be under Jubilee's control for onward placing to ensure orderly market conditions.

 

 

United Kingdom

7 June 2018

 Contacts

Jubilee Metals Group PLC

Colin Bird/Leon Coetzer
Tel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913
Andrew Sarosi
Tel +44 (0) 1752 221937

Nominated Adviser

SPARK Advisory Partners Limited
Mark Brady/Andrew Emmott
Tel: +44 (0) 203 368 3555

Broker

Shard Capital Partners LLP
Damon Heath/Erik Woolgar
Tel +44 (0) 20 7 186 9900

JSE Sponsor

Sasfin Capital (a member of the Sasfin group)

Sharon Owens
Tel +27 (0) 11 809 7500

 

    


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLFKADKCBKDAAK
UK 100

Latest directors dealings