Kenmare Resources PLC
25 July 2005
Kenmare Resources plc ('Kenmare' or 'the Company')
Good Progress on Kenmare's Moma Titanium Mineral Sands Project
Construction Ahead of Schedule
The board of Kenmare is pleased to announce that, as of the end of June,
construction of the Moma Titanium Mineral Sands Project was 28% completed and
ahead of schedule. Completion is currently anticipated in late September 2006,
some six weeks earlier than the contractual programme.
Satisfactory progress is being made across all areas of the project and the
majority of 'big-ticket' items have already been ordered. The 1600m long
airstrip has been completed and is already in use transporting staff between
Moma and Johannesburg. Bulk earthworks are nearly complete and civil works are
progressing well.
The first concrete pour took place in June as foundations were prepared for the
arrival of the ex-Beenup plant from Western Australia. This dismantled plant
departed Bunbury Port in Australia on board two 100m long ocean-going barges,
both of which have already arrived at Moma. The offloading of one barge is 50%
complete and the second barge is waiting off-shore.
Construction of infrastructure, such as the mine village and 170 kms of overhead
power line, is well advanced, and an order will be placed this month with a
shipyard for the construction of the 75m long product transportation barge,
whose design has been recently completed.
The board remains confident that further good progress will be made in the
coming months, both in terms of construction and of the marketing of Moma's
output.
The board of Kenmare is also pleased to announce the signing of another 5 year
marketing contract with a major consumer for anticipated production from its
Moma Project in Mozambique. While full details of this latest contract cannot be
disclosed, the pricing structure is comfortably above levels anticipated in
Kenmare's financing plan.
A full update of progress on the Moma Project will be given at the Company
Annual General Meeting today.
For further information, please contact:
For more information:
Kenmare Resources plc
Michael Carvill, Managing Director
Tel: + 353 1 671 0411
Mob: + 353 87 674 0110
Conduit PR Ltd
Leesa Peters/Pam Spooner
Tel: + 44 (0) 207 618 8708
Mob: + 44 (0) 781 215 9885
Murray Consultants Ltd
Elizabeth Headon
Tel: + 353 1 498 0300
Mob: + 353 87 989 7234
www.kenmareresources.com
25th July 2005
This information is provided by RNS
The company news service from the London Stock Exchange
*A Private Investor is a recipient of the information who meets all of the conditions set out below, the recipient:
Obtains access to the information in a personal capacity;
Is not required to be regulated or supervised by a body concerned with the regulation or supervision of investment or financial services;
Is not currently registered or qualified as a professional securities trader or investment adviser with any national or state exchange, regulatory authority, professional association or recognised professional body;
Does not currently act in any capacity as an investment adviser, whether or not they have at some time been qualified to do so;
Uses the information solely in relation to the management of their personal funds and not as a trader to the public or for the investment of corporate funds;
Does not distribute, republish or otherwise provide any information or derived works to any third party in any manner or use or process information or derived works for any commercial purposes.
Please note, this site uses cookies. Some of the cookies are essential for parts of the site to operate and have already been set. You may delete and block all cookies from this site, but if you do, parts of the site may not work. To find out more about the cookies used on Investegate and how you can manage them, see our Privacy and Cookie Policy
To continue using Investegate, please confirm that you are a private investor as well as agreeing to our Privacy and Cookie Policy & Terms.