Kenmare Resources PLC
25 October 2006
Kenmare Resources plc ('Kenmare' or 'the Company')
Kenmare announces short delay in completion of Mineral Separation Plant at the
Moma Project and early implementation of capacity expansion.
Kenmare has today received notification from the contractor constructing the
Moma Titanium Minerals Project of a six week delay to the completion of the
Minerals Separation Plant (MSP). Kenmare also announce that it intends to
execute an expansion of the capacity of its Moma Titanium Minerals Project in
the second half of 2007.
The capacity expansion, which is now in detailed design, will bring the output
of ilmenite, a titanium mineral and Moma's main product, from a steady state
production level of 700,000 tonnes per year to 800,000 tonnes per year. Hence
expected production in 2008 will be 800,000 tonnes of ilmenite, 56,000 tonnes of
zircon and 21,000 tonnes of rutile. The capital involved in this expansion is
estimated to be US$6.5 million, which is available from Kenmare's internal
resources.
In addition, Kenmare also announced that it has today received notification from
the contractor constructing the Moma Titanium Minerals Project of a six week
delay to the completion of the MSP. The MSP, which was due to be completed in
early January 2007, will now be complete around mid February. This delay has
been caused by the late delivery of materials to the project site. The Moma
Project is now 94.5% complete. Construction began in August 2004 with a
contract period running until the 5th of January 2007. It has been running
ahead of schedule until now.
Kenmare's Chairman Charles Carvill said; 'We have been signalling for some time
that we intend to expand production at Moma from initial levels. It is very
pleasing to see that engineering design has verified our view that this can be
done in an extremely cost effective manner and that we can move forward so
rapidly. Also, while it is disappointing to hear news of this short delay in
delivery of the MSP, its significance is small seen in context of the overall
project implementation which has gone extremely well.
For more information:
Kenmare Resources plc
Michael Carvill, Managing Director
Tel: + 353 1 671 0411
Mob: + 353 87 674 0110
Conduit PR Ltd
Leesa Peters
Tel: +44 (0) 207 429 6600
Mob: + 44 (0) 781 215 9885
Murray Consultants Ltd
Elizabeth Headon
Tel: + 353 1 498 0300
Mob: +353 87 989 7234
www.kenmareresources.com
25 October 2006
This information is provided by RNS
The company news service from the London Stock Exchange
*A Private Investor is a recipient of the information who meets all of the conditions set out below, the recipient:
Obtains access to the information in a personal capacity;
Is not required to be regulated or supervised by a body concerned with the regulation or supervision of investment or financial services;
Is not currently registered or qualified as a professional securities trader or investment adviser with any national or state exchange, regulatory authority, professional association or recognised professional body;
Does not currently act in any capacity as an investment adviser, whether or not they have at some time been qualified to do so;
Uses the information solely in relation to the management of their personal funds and not as a trader to the public or for the investment of corporate funds;
Does not distribute, republish or otherwise provide any information or derived works to any third party in any manner or use or process information or derived works for any commercial purposes.
Please note, this site uses cookies. Some of the cookies are essential for parts of the site to operate and have already been set. You may delete and block all cookies from this site, but if you do, parts of the site may not work. To find out more about the cookies used on Investegate and how you can manage them, see our Privacy and Cookie Policy
To continue using Investegate, please confirm that you are a private investor as well as agreeing to our Privacy and Cookie Policy & Terms.