National Grid responds to Ofgem on RIIO-2 and HSB

RNS Number : 1231W
National Grid PLC
30 July 2018
 

                                                                                                                                                     

 

 

 

 

30 July 2018  

National Grid plc

 

Ofgem's RIIO-2 Framework decision and decision on Hinkley

 

 

Ofgem today published its RIIO-2 Framework Decision. We are pleased that the decision provides further clarity on the length of the price control from April 2021 and continues to put consumers and other stakeholders in a central role in the process. We look forward to continuing to work constructively with Ofgem and other stakeholders over the coming months to achieve the best possible outcome for all stakeholders.

 

Separately, Ofgem has also published its final decision on the delivery model for the Hinkley-Seabank project (HSB) today, in which it chose the Competition Proxy model.

 

Ofgem's decision does not affect our commitment to delivering HSB to time and to quality as per our licence obligations.

 

We will now review the detailed decision by Ofgem and consider all of our options prior to Ofgem formally implementing the proposals into our licence later in the year or early 2019.

 

The HSB project is expected to have a total cost of around £650m, with the majority of forecast spend by National Grid Electricity Transmission plc in the RIIO-T2 price control period from April 2021 onwards.

 

 

 

Investors and Analysts

 

Aarti Singhal

+44 (0)20 7004 3170

+44 (0)7989 492447 (m)

Will Jackson

+44 (0)20 7004 3166

+44 (0)7584 206578 (m)

 

Media

 

Charles Armistead

(Teneo Blue Rubicon)

+44 (0)20 7420 3199


 

 

 

 

CAUTIONARY STATEMENT

This announcement contains certain statements that are neither reported financial results nor other historical information. These statements are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. These statements include information with respect to National Grid's financial condition, its results of operations and businesses, strategy, plans and objectives. Words such as 'aims', 'anticipates', 'expects', 'should', 'intends', 'plans', 'believes', 'outlook', 'seeks', 'estimates', 'targets', 'may', 'will', 'continue', 'project' and similar expressions, as well as statements in the future tense, identify forward-looking statements. These forward-looking statements are not guarantees of National Grid's future performance and are subject to assumptions, risks and uncertainties that could cause actual future results to differ materially from those expressed in or implied by such forward-looking statements. Many of these assumptions, risks and uncertainties relate to factors that are beyond National Grid's ability to control or estimate precisely, such as changes in laws or regulations, including any arising as a result of the United Kingdom's exit from the European Union; announcements from and decisions by governmental bodies or regulators, including those relating to the role of the UK electricity system operator as well as increased political and economic uncertainty; the timing of construction and delivery by third parties of new generation projects requiring connection; breaches of, or changes in, environmental, climate change and health and safety laws or regulations, including breaches or other incidents arising from the potentially harmful nature of its activities; network failure or interruption, the inability to carry out critical non network operations and damage to infrastructure, due to adverse weather conditions including the impact of major storms as well as the results of climate change, due to counterparties being unable to deliver physical commodities, or due to the failure of or unauthorised access to or deliberate breaches of National Grid's IT systems and supporting technology; failure to adequately forecast and respond to disruptions in energy supply; performance against regulatory targets and standards and against National Grid's peers with the aim of delivering stakeholder expectations regarding costs and efficiency savings, including those related to investment programmes and remediation plans; and customers and counterparties (including financial institutions) failing to perform their obligations to the Company. Other factors that could cause actual results to differ materially from those described in this announcement include fluctuations in exchange rates, interest rates and commodity price indices; restrictions and conditions (including filing requirements) in National Grid's borrowing and debt arrangements, funding costs and access to financing; regulatory requirements for the Company to maintain financial resources in certain parts of its business and restrictions on some subsidiaries' transactions such as paying dividends, lending or levying charges; inflation or deflation; the delayed timing of recoveries and payments in National Grid's regulated businesses and whether aspects of its activities are contestable; the funding requirements and performance of National Grid's pension schemes and other post-retirement benefit schemes; the failure to attract, train or retain employees with the necessary competencies, including leadership skills, and any significant disputes arising with the National Grid's employees or the breach of laws or regulations by its employees; and the failure to respond to market developments, including competition for onshore transmission, the threats and opportunities presented by emerging technology, development activities relating to changes in the energy mix and the integration of distributed energy resources, and the need to grow the Company's business to deliver its strategy, as well as incorrect or unforeseen assumptions or conclusions (including unanticipated costs and liabilities) relating to business development activity (including acquisitions and disposals) and joint ventures. For further details regarding these and other assumptions, risks and uncertainties that may impact National Grid, please read the Strategic Report section and the 'Risk factors' on pages 193 to 196 of National Grid's most recent Annual Report and Accounts, as published on 4 June 2018. In addition, new factors emerge from time to time and National Grid cannot assess the potential impact of any such factor on its activities or the extent to which any factor, or combination of factors, may cause actual future results to differ materially from those contained in any forward-looking statement. Except as may be required by law or regulation, the Company undertakes no obligation to update any of its forward-looking statements, which speak only as of the date of this announcement.


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCGLGDRSGXBGIG
UK 100