Third Quarter FY2015 Trading Update

RNS Number : 1593G
OPG Power Ventures plc
27 February 2015
 



27th February 2015

 

 

OPG Power Ventures plc

("OPG", the "Group" or the "Company")

 

Trading update for the three months ended 31st December 2014

 

OPG (AIM: OPG), the developer and operator of group captive power generation plants, announces the following trading update for the three months ended 31st December 2014 ("Q3 FY15").

 

Highlights

·   Average Plant Load Factor (PLF) of 94% and average tariff of Rs 5.71 in Q3 FY15;   

·   300 MW Gujarat : 150 MW unit I synchronised, plant expected to commence operations in early March;

·   180 MW Chennai IV expected to commence operations by April 2015

·   Over 10% increase in tariff on 55 MW Group Captive sales in Tamil Nadu

 

Operations Summary

 

Parameter

Quarter ended

 

Nine Months ended

 

Year ended


31 Dec 14

30 Sep 14

31 Dec 13

31 Dec 14

31 Dec 13

31 Mar 14

Generation (million units)







Chennai I

167

115

161

429

493

646

Chennai II

173

158

178

500

512

668

Chennai III

145

152

178

457

355

527

Total (million units)

484

425

518

1387

1360

1,841








PLF (%)







Chennai I

98

67

95

84

97

96

Chennai II

102

93

105

98

101

99

Chennai III

82

86

101

87

88

92

Average (%)

94

82

100

90

96

96








Tariff (Rs/kWh)

5.71 

5.58

5.54

5.61

5.55

5.55

 

Power generation in Q3 FY15 was 14% higher than the immediately preceding quarter and 7% lower than in the previous year following the effect of planned shutdowns.  For the same reason, average PLF across the three operating units for the nine months to December 2014 was 90%.  Average tariffs have remained constant.  

 

Average load factors for the three units in January 2015 were above 90% and overall, we expect an average PLF of approx. 90% for FY15 at the Chennai plant as a whole.

 

Projects

 

300 MW Gujarat - expected to commence operations in early March 2015

With the plant now synchronised with the grid, the plant is expected to commence operations early in March 2015, selling power under the Group Captive model to industrial customers using an interim transmission line whilst the second 150 MW unit is expected to be synchronised during the next quarter.  Ramp up of the plant is now expected by Q2 FY16.

 

180 MW Chennai IV - expected to commence operations in March 2015

This unit is in the final phase of commissioning and the Company expects to start operations by April 2015.  Sales are to be to TANGEDCO until September 2015.

 

Domestic coal supply unaffected by ongoing coal block reallocation

Following the de-allocation of coal blocks under a Supreme Court order last year, the Government of India has established a process for re-allocating blocks or mines through a series of bidding processes.  We were not affected by the de-allocation as our domestic coal, which has in the past made up between a third and half of our coal supply at prevailing market price, is provided to us under a linkage arrangement from mines operated by Coal India Limited.  Those linkages remain in place and all of the domestic coal we anticipated during the quarter was received by us.  We continue to maintain our current track record of no generation outages on account of fuel shortage. 

 

Interest Rate reduction by Reserve Bank of India ("RBI")

The RBI announced a 25 basis points cut in benchmark interest rates in January 2015. We expect a corresponding rate cut to be effected across our plants in the next quarter.

 

Outlook

Trading for the current year continues to be good and the Board remains confident about the outlook for the year. With commissioning activities across our projects now more or less complete, we expect our gross installed capacity to ramp up to 750 MW during FY16. 

 

For further information, please visit www.opgpower.com or contact:

 

OPG Power Ventures PLC

+91 (0) 44 429 11 211

Arvind Gupta / V Narayan Swami / Ajay Paliwal

 

 

 

Cenkos Securities (Nominated Adviser & Broker)

 

Stephen Keys / Mark Connelly / Callum Davidson

+44 (0) 20 7397 8900

 

 

Tavistock Communications

 

Simon Hudson / James Collins

+44 (0) 20 7920 3150

 

About OPG

OPG is operating and developing power plants in India under the group captive model with 270 MW in operation and a further 480 MW under development.  In the half year ended 30 September 2014, OPG generated revenues of £46.5 million, EBITDA of £16.6 million and earnings per share of 2.24   pence.

 

-ends-


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTSEFFWWFISEEE
UK 100

Latest directors dealings