Final Results - Rio Zim Ltd

Rio Tinto PLC 20 February 2004 Rio Tinto Zimbabwe (Rio Tinto 56 per cent interest) issued the following statement in Harare. Rio Tinto Zimbabwe Limited - Statement to shareholders The Group's audited results for the year ended 31 December 2003 were as follows: Profit and loss statement Historical $ millions Dec Dec 2003 2002 Group turnover 32,942 4,936 Cost of sales (24,471) (4,159) Operating profit before depreciation 8,471 777 Depreciation (134) (77) Net monetary (loss) gain Profit before interest 8,337 700 Net interest receivable 9 41 Profit before taxation 8,346 741 Taxation (2,472) (159) Profit after taxation 5,874 582 Dividends payable (proposed) 0 0 Earning per share (dollars) 262 3 Dividends per share (dollars) 3 0 Interim (dollars) 3 Final (dollars) 0 0 Number of shares in issue (millions) 22 22 Abridged balance sheet Shareholder's funds 7,204 1,794 Deferred tax 1,301 212 Employee welfare provision 624 106 Mine closure provision 980 178 Medium and long term debt 6 948 Total funds employed 10,115 3,238 Represented by: Fixed assets 1,367 3,410 Investments 515 84 Current assets 21,603 1,922 Current liabilities 13,370 2,178 Net current assets 8,233 (256) Total net assets employed 10,115 3,238 IAS 29 accounts are in the process of preparation. The directors have approved the issue of the historical accounts to maintain the normal timing of the provision of information to shareholders. Results Gold production for the year was 814 kg compared to 1,182 kg in the same period last year. The sale of Patchway Mine in August has a negative impact on the comparison. The other production related factor was the lower available grade at Renco Mine. The refinery operated with a steady matte supply in the second half and 3,639 tonnes of nickel were produced bringing production for the year to 6,198 tonnes (2002, 6,412 tonnes). Whilst a satisfactory production level was attained intermittent power supply problems affected efficiencies. On 26 December 2003 the refinery was hit by a localized windstorm. This caused structural damage and felled power lines in the area. The plant was off line for 2 days although the impact on operations extended for a longer period. The vagaries of the foreign exchange regime increasingly placed Renco in a distressed situation during the year as it failed to generate sufficient Zimbabwe dollars to cover its local commitments. In December the mine applied for and was granted permission to be paid at the $60,000 per gram price paid to smaller producers. This significantly improved the situation. Following BCL's force majeure in the first half of the year, the refinery entered into an agreement with its bankers to utilize a short-term credit facility. This allowed maximization of the operation's earnings and assisted through a period of low revenue. The company recorded a historical profit after tax of $5,874 million compared with $582 million in 2002. Exploration The exploration joint venture had been largely wound up by year end with only final tidying up in progress. RioZim's expenditure for the year amounted to $331 million. Murowa Work at the resettlement site effectively concluded in December with the handover of the agreed communal infrastructure including a primary school and clinic to the Masvingo Rural District Council. The project team moved on to planning and preparatory work for the Accelerated Production Project and by year end work had commenced on a weir on the Runde River and fencing of the mine site. Outlook The short term outlook for the company is not good as the continued use of an exchange rate of 824 for part of its earnings, has left the company short of Zimbabwe dollars to meet local and some foreign commitments. In addition the enforced payment to ZESA of foreign currency for electricity supplies has created a shortage of US dollars available to meet the company's commitments from its 50 per cent retention. Despite some positive changes to the national economic situation, these two items remain as constraints which are felt by all exporters and must be addressed by the authorities before the country's foreign currency earnings are severely reduced. In more reasonable economic circumstances with current commodity prices the company should be in a strong situation. The formalization of the shareholders agreement in respect of Murowa Diamonds (Private) Limited and the approval of a loan package from Rio Tinto plc amounting to US$13.5 million (which is still subject to Reserve Bank approval) allowed the Board to finally approve the development of the Accelerated Murowa Production Project. Production is expected to commence in the third quarter. Dividend Despite the reasonable outturn for 2003 the Board deferred a decision on any final dividend payment until the current fiscal issues impinging on the company are resolved. For further information, please contact: LONDON AUSTRALIA Media Relations Media Relations Lisa Cullimore Ian Head Office: +44 (0) 20 7753 2305 Office: +61 (0) 3 9283 3620 Mobile: +44 (0) 7730 418 385 Mobile: +61 (0) 408 360 101 Investor Relations Investor Relations Peter Cunningham Dave Skinner Office: +44 (0) 20 7753 2401 Office: +61 (0) 3 9283 3628 Mobile: +44 (0) 7711 596 570 Mobile: +61 (0) 408 335 309 Richard Brimelow Susie Creswell Office: +44 (0) 20 7753 2326 Office: +61 (0) 3 9283 3639 Mobile: +44 (0) 7753 783 825 Mobile: +61 (0) 408 360 764 Website: www.riotinto.com This information is provided by RNS The company news service from the London Stock Exchange

Companies

Rio Tinto (RIO)
UK 100

Latest directors dealings