Interim Results

RNS Number : 3682H
Shanta Gold Limited
17 August 2016
 

 

17 August 2016

 

Shanta Gold Limited

("Shanta Gold" or the "Company")

 

Interim results for the six months ended 30 June 2016

 

Shanta Gold (AIM: SHG), the East Africa-focused gold producer, developer and explorer, announces its unaudited results for the six months ended 30 June 2016 (the "Period").

 

Highlights

 

 

Operational

·     H1 gold production of 48,237 ounces ("oz") (H1 2015: 28,180 oz);

·     H1 gold sales of 47,621 oz at an average price of US$1,193 per oz ("/oz"), compared to average spot price of US$1,222 /oz (H1 2015: 25,142 oz at an average price of US$1,238 /oz);

·     Cash costs for H1 of US$437 /oz (H1 2015: US$993 /oz) and AISC of US$632 /oz (H1 2015: US$1,310 /oz);

·     Annual production guidance maintained for 2016 of 82,000 - 87,000 oz and expected to be towards the upper end of guidance;

·     AISC guidance lowered to US$730 - 780 /oz, from US$750 - 800 /oz; and

·     No lost time injuries for the period.

 

 

Financial

·     H1 revenue of US$55.7 million (H1 2015: US$31.9 million);

·     H1 EBITDA of US$33.3 million compared to full year 2015 EBITDA of US$31.3 million (H1 2015: US$1.0 million negative EBITDA);

·     Loss after taxation for the Period of US$4.7 million, as a result of non-cash charges relating to the amortisation of waste mining associated with the open pits and future development expenditure amortisation together totalling US$21.1 million (H1 2015: loss after taxation of US$8.3 million);

·     Net cash flow from operating activities for the Period was US$17.2 million (H1 2015: US$4.4 million);

·     Cash balance of US$30.5 million (FY 2015: US$19.6 million);

·     Net debt of US$39.5 million (31 December 2015: US$41.5 million); and,

·     ROM inventory of 190,000 tonnes representing an inventory value of US$18.1 million.

 

 

 

Corporate

·     Convertible Loan Note restructuring with US$10 million repaid and an extension of the maturity date of the remaining US$15 million to April 2019;

·     Well-supported equity placement with US$10.75 million raised; and

·     US$5.25 million silver stream entered for seven years (minimum) and 10 years (maximum) mine life at current mill capacity. Closure of the deal is expected by the end of Q3 2016.

 

 

Development and Exploration

·     Underground project commenced decline development in June 2016 and remains on track and within budget to produce first production of underground ore in Q2 2017;

·     The Luika River dam now completed and the dam is full ensuring low cost water security;

·     Works have begun on the second Tailings Storage Facility ("TSF2");

·     Exploration drilling in a two phase program delivered excellent intersections at the Ilunga prospect at depth and along strike; and

·     Development plans for Singida underway with pilot plant production targeted for Q1 2017.

 

 

Toby Bradbury, Chief Executive Officer, commented:

 

"This has been an excellent half year for Shanta, with a robust financial performance across the board.  As we transition into the underground resource, we retain our expectation of meeting the upper levels of our 2016 production guidance of 82-87,000 oz, which will be an annual record for the New Luika Gold Mine. All-in sustaining costs are expected to remain highly competitive at a reduced US$730-780 /oz, enabling the Company to generate significant cash flows to meet our capital programs and debt obligations.

Net debt is back below US$40 million, even before taking account of the US$5.25 million silver stream proceeds that are expected to be received shortly. Shanta is well funded to deliver on its plans and with an improved gold price environment; we can look forward to further cash generation in the second half of the year."

Presentation and webcast

The Interim results presentation has been placed on the Company's website and a webcast of that presentation is also available at www.shantagold.com.

This announcement is inside information for the purposes of Article 7 of Regulation 596/2014.

 

Enquiries:

 

Shanta Gold Limited
 
Toby Bradbury (CEO)
Mark Rosslee (CFO)
+255 (0)22 2601 829
 
 
Nominated Adviser and Broker
 
Peel Hunt LLP
 
Matthew Armitt / Ross Allister / Chris Burrows
+44 (0)20 7418 8900
 
 
Financial Public Relations
 
Tavistock
 
Jos Simson / Barney Hayward
+44 (0)20 7920 3150
 

 

 

About Shanta Gold

Shanta is an East Africa-focused gold producer, developer and explorer. It currently has defined ore resources on the New Luika and Singida projects in Tanzania and holds exploration licences over a number of additional properties in the country. Shanta's flagship New Luika Gold Mine commenced production in 2012 and produced 81,873 ounces in 2015. For further information please visit: www.shantagold.com.

 

Income Statement

 

Revenue for the Period of US$55.7 million was generated from the sales of 47,621 oz of gold at an average price of US$ 1,193 /oz. Revenue for H1 2016  was 74% higher than for H1 2015 reflecting higher gold production and improved efficiencies within the operations. The higher sales volumes were directly as a result of the higher gold production levels due to improved ore access post the optimisation of both Bauhinia Creek and Luika Pits in the first half of 2015. Sales volumes and average gold price for H1 2015 were 25,142 oz and US$1,238/oz respectively.

 

Cost of sales for the Period amounted to US$50.0 million, up 53% from H1 2015 which includes an amortisation charge for the period of US$21.1 million, a non-cash charge, relating to the amortisation of waste mining (US$11.2 million) and future development expenditure (FDE) amortisation (US$9.9 million) relating to the capital expenditure programme. 

 

EBITDA for H1 2016 is US$33.3 million, a significant improvement from a negative of US$1.0 million in H1 2015 and a very pleasing result for the six months. The US$33.3 million for H1 2016 compares very favourably against the full year for 2015 of US$31.3 million.

 

In 2015 some of the reserves at both the Luika and Bauhinia Creek open pits were reallocated to underground mining, resulting in the need to accelerate amortisation of the costs of overburden waste (including the Bauhinia Creek cut back) over the reduced open pit reserves and shortened life of the two open pits. This adjustment was retrospective to the start of mining in each pit (2013/14) and this was carried in the 2015 year end accounts (US$11.4 million). This also meant that for the remaining life of each pit (1 January 2016 to the end of the pit life), the proportionate amount of amortisation would be higher than had been the case previously. In the case of the Luika Pit, surface mining completed in June 2016 and hence is fully amortised within the Period under review (US$2.1 million). Bauhinia Creek Pit will complete in Q3 2016 and will be fully amortised at that point (US$9.1 million to June 2016 with remaining balance of US$2.4 million). These significant non-cash costs will cease from that point and total costs will reduce accordingly.

 

Going forward at the New Luika Gold Mine ("NLGM"), Shanta is developing the Ilunga reserve as an open pit. The strip ratios of Ilunga and all future operations will be significantly lower than those adopted previously (<50%) and surface mining costs will therefore be lower than in the past. For the second half of 2016 specifically, cash costs are expected to reduce significantly as production is supplemented from the ROM stockpile as a result of the accelerated mining program in the first half of the year.

 

In addition to the impact of the amortisation of waste mining for the open pits, the Company has provided amortisation for the capital it will spend on the development of its major projects and this is referred to as Future Development Expenditure (FDE). For H1 2016, FDE included in the cost of sales was US$9.9 million. The FDE is a non-cash cost and is ahead of the future capital expenditure program which will assist in providing smoother and more beneficial amortisation for the profitability of the mining operations in the future.

 

Administration and exploration expenditure amounted to US$4.4 million; this was lower compared to the comparable period which included termination payments as well as additional exchange rate losses incurred in the H1 2015. An operating profit of US$0.1 million was recorded, impacted principally by the higher amortisation charges arising from the FDE. Net finance costs amounted to US$3.2 million (H1 2015: US$3.7 million), due to the lower average borrowing costs, predominantly due to the transfer to the Investec lending facility.

 

The loss before tax of US$3.0 million (US$6.9 profit before tax before FDE) is an improvement from the loss before tax of US$10.3 million in H1 2015, but again, it is important to highlight the non-cash impact of the FDE. The loss after tax for the Period amounted to US$4.7 million (loss after tax of US$8.3 million for H1 2015), giving a loss per share of US$0.946 cents (H1 2015 US$1.781 cents).

 

Costs

 

The Company continues to identify and implement efficiency improvements across the business as well as improve its performance management reporting and business process optimisation resulting in total costs coming in below market guidance. Cash costs and AISC for the Period thus amounted to US$437 /oz and US$632 /oz respectively, down from US$993 /oz and US$1,310 /oz for H1 2015; a testimony to the excellent work and efficiencies being achieved.

 

Cash cost - Mining, processing and mine administration costs

All in Sustaining cost - Cash cost plus royalty, interest, general administration & corporate costs and stay in business capital expenditure

 

Financial Position

 

Total assets excluding cash balances decreased from US$133.7 million at 31 December 2015 to US$130.5 million, due mainly to increased amortisation charges and future development expenditure amortisation (totalling US$ 21.1 million: non-cash) offset by the additional investment in underground and surface capital expenditure.

 

At 30 June 2016, inventories amounted to US$25.9 million, up from US$10.7 million at 31 December 2015, as a result of the bullion on hand at period end and the increased ROM ore stock pile. The building of this stockpile helped deliver the lower mining costs for the half year and almost four months ore inventory now resides at the process plant. Total liabilities increased by US$2.3 million in the half. Borrowings remained at the similar levels and trade payables dropped by US$0.4 million offset by an increase in the deferred tax liability of US$1.5 million.

 

Cash flow

 

The improved production and grade, coupled with an increase in gold price and investment in working capital, positively impacted cash generation which amounted to US$17.2 million (H1 2015: US$4.4 million). Capital expenditure amounted to US$13.3 million with US$13.0 million related to underground equipment and infrastructure, alongside additional surface projects to provide power, water security and tailings storage requirements for the future life of mine. 

 

Cash generated from operations improved by US$12.8 million after adjustments for working capital movements of US$17.5 million. The cash balance at 30 June was US$30.5 million, up from US$19.6 million at 31 December 2015. Net debt at Period end thus amounted to US$39.5 million, (US$41.5 million at 31 December 2015).

 

The remainder of the Investec standby facility (US$10.0 million) was drawn down in the first half of 2016.  The equity placement of US$10.75 million was closed in May 2016 and purchase of US$10 million Convertible Loan Notes was concluded in June 2016 to enhance the financial position of the Company and provide the necessary resources to fund the current underground development. Based on current plans, the Company has now passed its peak debt position.

 

Exploration

The renewed emphasis on (brownfields) exploration to extend the life of NLGM continued in the first half of 2016.

Particularly favourable intersections on strike and at depth from two drilling campaigns at the Ilunga prospect were announced in April and July 2016.  Highlights of the two drilling campaigns are presented below:

Phase 1 drilling programme at the Ilunga prospect

A nine hole drilling programme (eight reverse circulation ("RC") pre-collars with diamond tails, and one RC hole) intersected discernible, albeit variable evidence of mineralisation at depth in all holes, including:

·     4 metres ("m") at 6.54 grammes per tonne ("g/t") gold from 143 m in hole CSR466;

·     14.73 m at 14.31 g/t gold from 166.89 m in hole CSD081 including

o   1.91 m at 3.76 g/t gold from 166.89 m;

o   5.29 m at 21.54 g/t gold from 170.24 m; and

o   3.06 m at 23.19 g/t gold from 178.61 m.

·     1.74 m at 16.26 g/t gold from 205.17 m in hole CSD083;

·     2.38 m at 23.37 g/t gold from 132.16 m in hole CSD084;

·     2.28 m at 9.67 g/t gold from 152.41 m in hole CSD085; and

·     4.74 m at 4.54 g/t gold from 181.52 m in hole CSD088

Phase 2 drilling programme at the Ilunga prospect

The Phase 2 upgrade drilling programme, included 20 drill holes in total, all of which intersected visually distinctive mineralised zones confirming the continuity of the Ilunga prospect both along strike and at depth. Encouraging mineralised intersections achieved included:

·     13 m at 4.19 g/t gold from 80 m in hole CSR 482

o   Including 10 m at 5.3 g/t

·     2.06 m at 10.46 g/t gold from 265.5 m in hole CSD096

·     3.2 m at 40.64 g/t gold from 277.1 m in hole CSD096

·     8.3m at 1.97 g/t gold from 234.81 m in hole CSD098

o   Including 2.14 m at 4.58 g/t

·     1.38 m at 10.19 g/t gold from 130.96 m in hole CSD100

·     2.93 m at 18.62 g/t gold from 157.87 m in hole CSD 100

 

Ilunga is within the current mining licence area approximately 2.5km from the ROM stockpile.  An additional 100m of mineralisation was added to the west of the current 400 metre strike length while the eastern limit of mineralisation was successfully defined.  The deposit plunges to the west and remains open on strike in that direction, albeit with some fault displacement.  As reported in April and July, strongly mineralised intersections were picked up at increasing depths from 100 metres (from previous exploration limits) to approaching 300 metres depth.  On-going work at Ilunga includes surface and structural mapping to the west to identify further extensions of this exciting prospect.

The existing Ilunga total resource has a strike of 400 metres and a depth of 100 metres for 0.8 million tonnes at 3.5 g/t for 92,000 oz. The recent drilling extends the resource on strike and at depth and the results are in the process of being modelled and independently evaluated with the intention of updating the resource for Ilunga in the current quarter.  These in turn will be updated in the mine plan and are expected to add an extension to open pit currently in development and also in a potential underground operation.

Going forward, further exploration is planned for Shamba (current total resource 0.4 million tonnes at 2.1 g/t for 24,000 oz) which sits inside the mining licence, 2 km to the west of the process plant.  On the prospecting licences surrounding New Luika Gold Mine, on-going grass-roots exploration continues to generate targets for drilling.  An example of such a deposit is the Askari target that was reported in February 2016, the highlights of which are presented below:

Askari drill programme of 2,699 m encountered mineralisation in 24 of 26 holes including:

·     4 m @ 8.6 grams per tonne gold from 76 m in hole SGR164;

·     4 m @ 31.2 g/t from 61 m in hole SGR165;

·     8 m @ 7.2 g/t from 108 m in hole SGR167;

·     3 m @ 11.6 g/t from 93 m in hole SGR168.

 

The priority of the Askari target, as with all targets, is reviewed in light of the results of on-going work in the portfolio.  At present, the best opportunities for further exploration have been within the existing mining licence; as in the case of Ilunga.  Notwithstanding, Shanta will complete a Lidar survey in the second half of 2016 and continues with its target generation.

 

Corporate

 

The Company has maintained a prudent hedging policy and was able to realise an average price of US$1,193 /oz in the period with 26,313 oz sold under hedging contracts. As at 30 June 2016, 42,000 oz had been sold forward to 31 December 2016 at an average price of US$1,242/oz. As the market shows continued strength, the older and lower value hedges are delivered against and the balance of the existing hedges continues to improve. These hedge positions continue to provide certainty as NLGM transitions into underground mining during its capital program.

 

Outlook

 

As previously communicated in the Q2 production and operation update on 19 July 2016, for the second half of 2016, NLGM's grade is expected to be slightly lower than that achieved in the first half at an average grade of around 5 g/t. Consequently, total gold production for the year is expected to remain within guidance, albeit towards the upper end. Planned ore grades are expected to increase from Q2 2017 as the underground ore reserves in Bauhinia Creek are accessed. Average annual production from 2016 - 2020 as provided in the Base Case Mine Plan in September 2015 is 84,000 oz over the 5 years within the current reserve base.

 

With the completion of Luika Pit in June and Bauhinia Creek Pit expected to complete in Q3 2016, surface mining will transition to the Ilunga open pit for the remainder of 2016 and into 2017. The Company expects cash costs to be lower in the second half of the year in comparison to the first half.  However, lower grades and consequently lower gold production will see higher AISC in the second half of the year than the first resulting in AISC 2016 guidance of US$730 - 780 /oz, an improved position from the previous guidance at US$750 - 800 /oz.

 

The near mine exploration and development campaign is a key component of the Company's ongoing strategy, as newly proven reserve ounces will be duly incorporated into the NLGM mine plan extending the project's life and further improving the project economics. The Company intends to provide an updated Resources and Reserves statement at the end of Q3 2016 to be incorporated into an updated mine plan.

 

Beyond NLGM, Singida is now being pursued as an active development project as announced on 15 July 2016. The Company intends to have a pilot mining operation underway by the end of Q1 2017.

 

 

SHANTA GOLD LIMITED

Consolidated Statement of Comprehensive Income 

for the six months ended 30 June 2016

 

 

 

 

 

 

 

 

 

 

 

Note

6 months

 

6 months

 

Year

 

 

 ended

 

ended

 

ended

 

 

30-Jun-16

 

30-Jun-15

 

31-Dec-15

 

 

US$'000

 

US$'000

 

US$'000

 

 

Unaudited

 

Unaudited

 

Audited

Revenue

 

55,660

 

31,912

 

95,705

(Loss)/Gain on non-hedge derivatives and other commodity contracts

 

(1,227)

 

-

 

2,253

Cost of sales

 

(49,985)

 

(32,743)

 

(96,394)

Other cost of sales

 

(16,793)

 

(27,131)

 

(54,075)

Amortisation

 

(33,192)

 

(5,612)

 

(42,319)

 

 

4,448

 

(831)

 

1,564

Gross profit/(loss)

Other costs

 

(4,376)

 

(5,804)

 

(12,689)

Administration expenses

 

(3,141)

 

(4,749)

 

(10,255)

Exploration and evaluation costs

 

(1,235)

 

(1,055)

 

(2,434)

 

 

 

 

 

 

 

Operating profit/(loss)

 

72

 

(6,635)

 

(11,125)

Finance income

 

88

 

127

 

112

Finance expense

 

(3,194)

 

(3,835)

 

(7,097)

(Loss) before taxation

 

(3,034)

 

(10,343)

 

(18,110)

 

 

 

 

 

 

 

Taxation

 

(1,687)

 

2,044

 

804

 

 

 

 

                   

 

 

 Current

 

(188)

 

-

 

(287)

 Deferred

 

(1,499)

 

2,044

 

1,091

 

 

 

 

 

 

 

(Loss) for the Period / year attributable to equity holders of the parent company

 

(4,721)

 

(8,299)

 

(17,306)

Basic (loss) per share (cents)

3

(0.946)

 

(1.781)

 

(3.727)

 

  

 

SHANTA GOLD LIMITED

Consolidated Statement of Comprehensive Income 

As at period ended 30 June 2016

 

 

 

 

 

 

6 months ended

 

6 months ended

 

Year ended

 

 

 30 June 2016

 

 30 June 2015

 

31-Dec-15

 

 

Unaudited

 

Unaudited

 

Audited

 

 

US$'000

 

US$'000

 

US$'000

(Loss) after taxation

 

(4,721)

 

(8,299)

 

(17,306)

Other comprehensive income:

 

 

 

 

 

 

Exchange differences on translating subsidiary which can subsequently be reclassified to profit or loss

 

(42)

 

36

 

100

Total comprehensive (loss) attributable to equity shareholders of parent company

 

(4,763)

 

(8,263)

 

(17,206)



 

SHANTA GOLD LIMITED

Consolidated Statement of Financial Position

As at period ended 30 June 2016

 

 

 

 

 

 

 

 

 

 

 

Note

30-Jun

 

30-Jun

 

31-Dec

2016

2015

2015

 

 

US$'000

 

US$'000

 

US$'000

 

 

Unaudited

 

Unaudited

 

Audited

Non-current assets

 

 

 

 

 

Intangible assets

 

23,216

 

23,243

 

23,201

Property, Plant and Equipment

 

71,170

 

117,814

 

91,093

Total non-current assets

 

94,386

 

141,057

 

114,294

Current assets

 

 

 

 

 

 

Inventories

 

25,934

 

10,123

 

10,737

Trade and other receivables

 

10,225

 

7,152

 

8,717

Restricted cash

 

500

 

500

 

500

Cash and cash equivalents

 

29,998

 

5,861

 

19,117

Total current assets

 

66,657

 

23,636

 

39,071

 

 

 

 

 

 

 

Total assets

 

161,043

 

164,693

 

153,365

 

 

 

 

 

 

 

Capital and reserves

 

 

 

 

 

 

Share capital

 

92

 

77

 

76

Share premium

 

143,871

 

133,246

 

133,766

Other reserves

 

7,393

 

10,349

 

9,539

Retained deficit

 

(69,283)

 

(58,284)

 

(66,712)

Total equity

 

82,073

 

85,388

 

76,669

Non-Current liabilities

 

 

 

 

 

 

Loans and borrowings

4

31,813

 

55,792

 

54,076

Decommissioning provision

 

6,218

 

9,328

 

5,979

Deferred taxation

 

8,194

 

5,742

 

6,696

Total non-current liabilities

 

46,225

 

70,862

 

66,751

Current liabilities

 

 

 

 

 

 

Trade payables and accruals

 

5,450

 

6,396

 

5,883

Loans and borrowings

4

27,295

 

2,047

 

4,062

Total current liabilities

 

32,745

 

8,443

 

9,945

 

 

 

 

 

 

 

Total liabilities

 

78,970

 

79,305

 

76,696

 

 

 

 

 

 

 

Total equity and liabilities

 

161,043

 

164,693

 

153,365

 

SHANTA GOLD LIMITED

Consolidated changes in Equity 

for the six months ended 30 June 2016

                  

 

Share Capital

Share Premium

Share Option Reserve

Convertible Debt Reserve

Translation Reserve

Shares to be Issued Reserve

Retained Deficit

Total Equity

 

US$'000

US$'000

US$'000

US$'000

US$'000

US$'000

US$'000

US$'000

 

 

 

 

 

 

 

 

 

At 1 January 2016

76

133,766

3,202

5,374

881

82

(66,712)

76,669

Loss for the Period

-

-

-

-

-

-

(4,721)

(4,721)

Other comprehensive income for the year

-

-

-

-

(42)

-

-

(42)

Repurchase of Convertible Debt

-

-

-

(2,150)

-

-

2,150

-

Shares issued

16

10,105

-

-

-

-

-

10,121

Share based payments

-

-

46

-

-

-

-

46

At 30 June 2016 (Unaudited)

92

143,871

3,248

3,224

839

82

(69,283)

82,073

 

 

 

 

 

 

 

 

 

At 1 January 2015

76

132,865

4,067

5,374

781

416

(50,228)

93,351

Profit for the Period

-

-

-

-

-

-

(8,299)

(8,299)

Comprehensive income for the Period

-

-

-

-

36

-

-

36

Shares issued

1

381

(243)

-

-

(310)

243

72

Share based payments

-

-

228

-

-

-

-

228

At 30 June 2015 (Unaudited)

77

133,246

4,052

5,374

817

106

(58,284)

85,388

 

 

 

 

 

 

 

 

 

At 1 January 2015

76

132,865

4,067

5,374

781

416

(50,228)

93,351

Profit  for the year

-

-

-

-

-

-

(17,306)

(17,306)

Other comprehensive income for the year

-

-

-

-

100

-

-

100

Share based payments

-

-

367

-

-

-

-

367

Shares issued

-

491

-

-

-

(334)

-

157

Exercised options

-

410

(410)

-

-

-

-

-

Lapsed options

-

-

(822)

-

-

-

822

-

At 31 December 2015 (Audited)

76

133,766

3,202

5,374

881

82

(66,712)

76,669

                                                                  

 

SHANTA GOLD LIMITED

Consolidated Statement of Cash flows 

for the six months ended 30 June 2016

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note

30-Jun

 

30-Jun

 

31-Dec

 

 

2016

2015

2015

 

 

 

 

US$'000

 

US$'000

 

US$'000

 

 

 

 

Unaudited

 

Unaudited

 

Audited

 

 

 

 

 

 

 

 

 

 

 

Net cash flows from operating activities

5

17,214

 

4,383

 

35,017

 

 

 

 

 

 

 

 

 

 

 

Investing activities

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Purchase of intangible assets

 

(14)

 

(35)

 

(71)

 

 

Purchase of property, plant and equipment

 

(182)

 

(630)

 

(2,048)

 

 

Assets under construction

 

(13,089)

 

(3,681)

 

(8,509)

 

 

Open pit development expenditure

 

-

 

(10,423)

 

(18,904)

 

 

Proceeds from disposal of asset

 

-

 

32

 

-

 

 

 

 

 

 

 

 

 

 

 

Net cash flows (used in) investing activities

 

(13,285)

 

(14,737)

 

(29,532)

 

 

 

 

 

 

 

 

 

 

 

Financing activities

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Share capital issued

 

10,121

 

-

 

-

 

 

Loans repaid

 

(11,171)

 

(25,076)

 

(25,237)

 

 

Equipment loan advanced /(repaid)

 

1,628

 

(290)

 

(579)

 

 

Finance lease payments

 

(65)

 

(65)

 

(165)

 

 

Loan interest paid

 

(3,561)

 

(2,378)

 

(4,398)

 

 

Loans received, net of issue costs

 

10,000

 

29,146

 

29,133

 

 

 

 

 

 

 

 

 

 

 

Net cash flows from/(used in) financing activities

 

6,952

 

1,337

 

(1,246)

 

 

 

 

 

 

 

 

 

 

 

 

 

Net (decrease)/increase in cash and cash equivalents

 

10,881

 

(9,017)

 

4,239

 

 

Cash and cash equivalents at beginning of Period

 

19,117

 

14,878

 

14,878

 

 

 

 

 

 

 

 

 

 

 

 

 

Cash and cash equivalents at end of Period/year

 

29,998

 

5,861

 

19,117

 

 

 

 
                 

 



 

SHANTA GOLD LIMITED

Notes to the Consolidated Financial Statements                             

for the six months ended 30 June 2016

 

1.     General information

 

Shanta Gold Limited (the "Company") is a limited company incorporated in Guernsey. The Company is listed on the London Stock Exchange's AIM market.  The address of its registered office is Suite A, St Peter Port House, St Peter Port, Guernsey. The interim consolidated financial statements were approved by the board and authorised for issue on 16 August 2016.

 

2.     Basis of preparation

 

The consolidated interim financial statements have been prepared using policies based on International Financial Reporting Standards (IFRS and IFRIC interpretations) issued by the International Accounting Standards Board ("IASB") as adopted for use in the EU. The consolidated interim financial statements have been prepared using the accounting policies which will be applied in the Group's financial statements for the year ended 31 December 2016.

 

The consolidated interim financial statements for the Period 1 January 2016 to 30 June 2016 are unaudited and incorporate unaudited comparative figures for the interim Period 1 January 2015 to 30 June 2015 and the audited comparative figures for the year to 31 December 2015. It does not include all disclosures that would otherwise be required in a complete set of financial statements and should be read in conjunction with the 2015 Annual Report.

 

The half year financial information for the six months ended 30 June 2016 set out in this document does not comprise the Group's statutory accounts as defined in Companies (Guernsey) Law 2008 accordingly this half year financial information is not considered to be the company's statutory accounts. The statutory accounts for the year ended 31 December 2015, which were prepared under EU endorsed IFRS, have been delivered to the Registrar of Companies. The auditors reported on these accounts; their report was unqualified and did not include reference to any matters to which the auditor drew attention by way of emphasis.

 

The same accounting policies, presentation and methods of computation are followed in the interim consolidated financial statements as were applied in the Group's latest annual audited financial statements except that in the current financial year, the Group has adopted a number of revised Standards and Interpretations. However, none of these has had a material impact on the Group's reporting.

 

In addition, the IASB has issued a number of IFRS and IFRIC amendments or interpretations since the last annual report was published. It is not expected that any of these will have a material impact on the Group.

 

 

 

 

 

 

  

 

 

SHANTA GOLD LIMITED

Notes to the Consolidated Financial Statements                             

for the six months ended 30 June 2016

 

3.   (Loss) per share

 

Basic (loss) per share is calculated by dividing the (loss)/profit attributable to the ordinary shareholders by the weighted average number of ordinary shares outstanding during the Period/year.

 

There were share incentives outstanding at the end of the Period that could potentially dilute basic earnings per share in the future.

 

Due to the loss for the Period ended 30 June 2016, the share options would be anti-dilutive and therefore diluted LPS is the same as Basic LPS.

 

 

Unaudited

Unaudited

Audited

 

30 June 2016

30 June 2015

31-Dec-15

 

(Loss)

 Weighted average number of shares

Per share amount

(Loss)

Weighted average number of shares

Per share amount

(Loss)

Weighted average number of shares

Per share amount

US$'000

(thousands)

(Cents)

US$'000

(thousands)

(Cents)

US$'000

(thousands)

(Cents)

Basic LPS

 

(4,721)

 

499,138

 

(0.946)

(8,299)

466,605

(1.781)

 (17,306)

464,389

 

 

(3,727)

 

 

4.     Loans and borrowings

 

 

 

 

Unaudited

 

Unaudited

 

Audited

6 months ended 30 June 2016

6 months ended 30 June 2015

Year ended 31 December 2015

$'000

$'000

$'000

Amounts payable within one year

 

 

 

 

 

 

Promissory notes (a)

 

3,032

 

-

 

-

Loan from Investec Bank (b)

 

23,356

 

1,003

 

3,356

Loan from related parties(f)

 

-

 

337

 

-

Equipment Finance(d)

 

769

 

579

 

579

Finance lease(e)

 

138

 

128

 

127

 

 

27,295

 

2,047

 

4,062

Amounts payable after one year

 

 

 

 

 

 

Promissory notes (a)

 

-

 

2,845

 

2,929

Loan from Investec Bank (net of arrangement costs) (b)

 

14,788

 

28,143

 

25,877

Convertible loan notes (c)

 

14,202

 

22,645

 

23,446

Equipment Finance(d)

 

2,596

 

1,737

 

1,448

Finance lease (e)

 

227

 

422

 

376

 

 

31,813

 

55,792

 

54,076

 

SHANTA GOLD LIMITED

Notes to the Consolidated Financial Statements                             

for the six months ended 30 June 2016

(a) Promissory Notes

Promissory notes relate to Promissory Note 2 of US$3.1 million issued in consideration for the acquisition of Boulder and are repayable on 15 April 2017. During the previous year Promissory Note 1 of US$2.4 million was repaid on 15 April 2015. The notes bear an annual interest of 2.6% and are payable semi-annually in arrears. The promissory notes are recognised at fair value and subsequently accounted at amortised cost. The fair value of the notes has been determined by discounting the cash flows using a market rate of interest which would be payable on a similar debt instrument obtained from an unconnected third party. Using a market interest rate of 9% and a contractual rate of 2.6%, the fair value of the promissory notes of US$3.1 million was calculated to be US$2.5 million.

 

(b) Loan from Investec Bank in South Africa relates to a drawdown of US$ 40 million from two facilities totalling US$40 million obtained in May 2015 and fully drawn in April 2016.The facilities bear an annual interest rate of 3-month USD LIBOR +4.9% and are secured on the bank account which is credited with gold sales, the shares in Shanta Mining Company Limited (SMCL) and a charge over the assets of SMCL.

 

Facility A is for US$20 million and was used to pay the outstanding FBN Bank Ltd loan, accrued interest of US$101,000 and loan arrangement fees of US$600,000. Capital repayments of US$1.25 million are due every quarter end commencing on 30 June 2016.

 

Facility B of US$20 million is a standby facility to be drawn as and when required to meet working capital requirements. US$10 million of the facility was drawn in May 2015 and a further US$10 million was drawn down on 1 April 2016.

 

Repayment of the drawn facility amount commences in the quarter ending 30 June 2016 and can be extended at the option of SMCL to begin repayments from June 30, 2017.

 

Both these facilities are secured by means of

•       A deed  of debenture  setting  out  the  fixed  and floating charge debenture governed by Tanzanian law over all assets and undertakings of  SMCL  and made between the Investec and the Security Agent, including any immovable property, moveable property, the Mining Licences, the relevant Prospecting Licences  and  surface  right  lease  or  access  agreements and the assignment/charge  over  Investec's rights under and in  terms  of all bank accounts, material documents, insurances and insurance proceeds and all loans against any other member of the Group but excluding assets over which a Permitted Security Interest has been created;

•       A  deed of debenture setting out the fixed and  floating charge debenture  governed  by  Tanzanian  law  over  all  assets  and undertakings of Shield  Resources  Limited and  made  between  Shield  Resources  Limited and  the Security Agent, including any immovable property, moveable property, the relevant Prospecting   Licences   and   surface   right  lease   or  access  agreements   and   the assignment/charge over Shield  Resources'  rights  under and  in terms of all  bank accounts,  insurances,  insurance  proceeds  and  all  loans  and  claims  of  Shield Resources against  any  other  member of the  Group but excluding assets  over which a Permitted Security Interest has been created;

•       Together there is a registered charge of US$55,000,000 (which includes a margin facility for gold forward sales of up to US$15,000,000) against the mineral and prospecting rights of both Shanta Mining Company Limited and Shield Resources Limited;

 

SHANTA GOLD LIMITED

Notes to the Consolidated Financial Statements                             

for the six months ended 30 June 2016

 

•     Shareholder Pledge which means each written deed entitled share pledge governed by Tanzanian law in terms of which each of Shanta Gold and Shanta Holdings pledges the shares it holds in the Borrower in favour of the Security Agent and assigns and charges all its loans and claims against the Borrower and other members of the Group in favour of the Security Agent and the Shield Resources Pledge which means  each  written  deed  entitled  share  pledge governed by Tanzanian law in terms of which  Boulder Investments pledges the shares it holds as Agent and assigns and charges all its loans and claims against Shield Resources in favour of the Security Agent;

 

Guarantees from Shanta Gold Limited, Shanta Gold Holdings Limited and Shield Resources Limited have been issued in favour of the Security Agent in respect of the above loan facilities.

 

(c) The convertible loan notes relate to the original US$25 million fixed coupon convertible loan notes which were due for repayment on 13 April 2017 and contain a conversion option at a price of US$0.4686 per 1 Company share. The notes incurred an interest charge of 8.5% per annum and interest is payable half yearly in April and October. They are not secured against any assets of any Group Company. The Group has determined them to be a compound financial instrument requiring a proportion of the loan to be classified as equity. The equity element represents the difference between the fair value of a similar liability with no equity conversion option and the fair value of the existing convertible notes in issue. Accreted interest is charged to the statement of comprehensive income over the life of the notes.

 

In May 2016, and following consultation with the convertible loan note holders, the Company has reached an agreement with a requisite 75 per cent. majority to complete a buyback of $10.0 million of the notes and to extend the repayment term of the remaining notes by two years to April 2019. As part of the Restructuring, the coupon applicable to the notes will increase from 8.5 per cent. to 13.5 per cent. for the remainder of the term of the notes.

 

(d) Equipment Loan

The loan is in respect of a crusher/screening plant acquired from Sandvik SRP AB, Sweden and is payable in 20 equal quarterly instalments commencing on 15 August 2014 and bears interest at a rate of 6% per annum. A further loan facility consisting of two tranches totalling € 4.63 million for 7 pieces of mining equipment and bears interest at rate of 7% and is repayable in 36 instalments commencing in June 2016 - Tranche A and September 2016 - Tranche B on a quarterly basis

 

(e) Finance Lease

This is in respect of a lease to acquire Heavy Fuel Oil (HFO) fuel storage tanks from Oryx Oil Company Limited for a capital amount of US$667,591 repayable monthly over sixty months commencing on 1 August 2014.  This is classified as a finance lease because the rentals period amounts to the estimated useful economic life of the asset and after five years, the assets will be bought outright by the Company by paying a nominal amount.

 

(f)Related party loan

This loan was fully repaid in H2 2015 and full details are contained in the Annual Report of the Company for 2015.

 

SHANTA GOLD LIMITED

Notes to the Consolidated Financial Statements                             

for the six months ended 30 June 2016

  

5.   Net Cash flows from Operating activities

 

 

 

 

30-Jun-16

 

30-Jun-15

 

31-Dec-15

 

US$'000

 

US$'000

 

          US$'000

(Loss) before tax

 

(3,034)

 

(10,343)

 

(18,110)

Adjustments for:

 

 

 

 

 

 

Depreciation / depletion of assets

 

33,192

 

5,612

 

43,015

Amortisation / write off of intangible assets

 

239

 

-

 

78

(Gain)/loss on disposal of assets

 

-

 

(32)

 

368

Share based payment costs

 

46

 

295

 

527

Loss/(Gain) on non-hedge derivatives

 

1,312

 

-

 

(1,312)

Exchange (gain)/loss

 

(42)

 

(157)

 

276

Finance income

 

(88)

 

(47)

 

(112)

Finance expense

 

3,194

 

3,835

 

7,097

Fair value of warrants

 

-

 

(48)

 

-

 

 

 

 

 

 

 

Operating cash (outflow)/inflow before movement in working capital

 

34,819

 

(885)

 

31,827

 

 

 

 

 

 

 

Movements in working capital:

 

 

 

 

 

 

(Increase)/decrease in inventories

 

(15,197)

 

2,584

 

1,970

(Increase)/decrease in receivables

 

(1,875)

 

2,431

 

1,718

(Decrease)/Increase in payables

 

(433)

 

253

 

(260)

 

 

17,314

 

4,383

 

35,255

Taxation paid

 

(188)

 

-

 

(287)

Interest received

 

88

 

 -

 

49

Net cash flow from operating activities

 

17,214

 

4,383

 

35,017

 

 

6.   Events after the reporting Period

 

     There were no significant transactions after the reporting date.

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
IR LFFSLTFIRLIR