Results of Chunya Feasbility and Issue of Equity
SHANTA GOLD LIMITED
RESULTS OF CHUNYA FEASIBILITY AND ISSUE OF EQUITY
5 July 2010
Shanta Gold Limited ("Shanta Gold" or the "Company") is pleased to announce the
completion of its Feasibility Study on the Chunya gold project in the Lupa
goldfield in southern Tanzania. The study was conducted and coordinated by
Environmental, Process and Mining Consultants (Pty) Ltd ("EPMC") a South African
based consultancy with a proven track record and many years of successful
performance.
Overview of feasibility study results:
   ·    The study supports a 360,000 tonnes per annum metallurgical process
plant fed from a number of open pit operations all within 3 km of the
metallurgical plant which could produce an average of 28,400 ounces of gold per
annum over an eleven year production life. Construction is estimated to take
one year. A 50 tonnes per hour capacity plant consisting of crushing and
screening, comminution, conventional CIL and smelting is forecast to achieve an
89% recovery in dore bars.
   ·    Average operating cash cost of US$643/ounce.
   ·    Capital estimated at US$23.1 million with a payback period of two
years.
   ·    A robust project internal rate of return (IRR) of 39% and when
discounted at 7% a net present value (NPV) of US$37.5 million at a base case
gold price of US$1100.
   ·    Mine construction is expected to be completed within nine months of
project start-up.
The Company has been investigating various avenues of financing for the project
and these will which are anticipated to be finalised in due course.
The opportunity exists to double the mine's capacity to exploit the additional
resource already evaluated and any further ore resulting from ongoing
discoveries. Initial incremental capital estimates for the expansion are US$5
million (to double capacity) and the plant layout has been designed to
accommodate such expansion.
Project Summary
EPMC of Johannesburg, South Africa conducted  the feasibility study to evaluate
the economic potential of developing a small to medium scale mining operation at
Shanta Gold's Chunya gold project in southern Tanzania. In doing so EPMC project
managed the additional inputs from specific specialist consulting groups
including Geologix (Pty) Ltd (ore resource consultants), Epoch Resources (Pty)
Ltd (tailings design and EIA), Mintek (metallurgy), DRA Engineering Ltd
(process design and infrastructure) and MINOPEX (Minerals Operations Executive
(Pty) Limited) (process plant operations).
The study demonstrated the feasibility of a series of open pits with a combined
life in excess of 10 years, exploiting the resources delineated by Shanta during
the past three years and calculated by Geologix, independent resource
consultants to the Company. A key element in designing the mine has been to
implement a selective mining strategy supported by grade control drilling across
mining blocks of 3mx3m. The mined ore will be hauled to a 360,000 tonnes per
annum capacity process facility, comprising a crushing and screening section,
followed by a mill circuit and then a conventional carbon in leach ("CIL")
circuit. Gold recovery will be by smelting to dore bars.
The capital expenditure to develop the mine is estimated at about US$23.19
million. Capital recoupment is anticipated to be achieved within two years. This
estimate is based on new equipment and Shanta plans to reduce capital through
appropriate second hand purchasing.
The feasibility study projects production of an average of 28,400 ounces of gold
per annum at an average cash cost of US$643 per ounce. The level of annual gold
production is dependent on the pit being exploited and rises from 28,000 ounces
in Year 2 to 44,000 ounces in Year 8 and then decreases to the end of the mine
life, when low grade stockpiles are processed.
The project has an IRR of 39% and a NPV of US$37.53 million at a gold price of
US$1,100 per ounce. At a 10% discount rate the NPV amounts to US$29.96 million.
These results are based on constant money value modelling.
Sensitivity analysis of a number of the key variables has demonstrated the
project should be robust and be able to withstand changes in capital, operating
cost gold price and grade.
The project as designed does not fully exploit the possible resource upside at
Chunya and potential exists to expand the plant capacity further, as well as to
exploit additional open pittable resources that may be discovered through the
ongoing exploration programme. This is demonstrated by the fact that the current
open pit designs stop on high grade boundaries, and further drilling is thus
expected to extend economic ore zones beyond existing pit designs. Possible
extensions and new ore bodies currently being tested are described in an
announcement released on 30 June 2010. A preliminary estimate of the capital
required to double the capacity is US$5 million.
Further upside is indicated by a common high grade zone in the core of most of
the ore bodies that could in future be exploited by underground mining methods
on completion of the economic open pit stage. This has not been considered in
this study. Additionally, in the feasibility, no account has been taken of by-
product silver, which occurs at a ratio of approximately 2:1 in the ore bodies.
The Company proposes to use both contractor mining and contractor process
operation and discussions are underway with competent contractors in this
regard.
Shanta Gold is exploring financing options for the development of the mine at
Chunya and has a number of advanced discussions underway.
Feasibility study financing
The feasibility study was commissioned during May 2009, at the risk of third
parties, and Shanta Gold entered into preliminary conditional agreements to
raise finance to pay for the feasibility study from parties associated with the
preparation there-of. Funds were to be raised at a price of 8p per share with a
warrant attached for every two shares subscribed for with a strike price of 10p
per warrant, such warrants to have a term of 2 years from the date of grant and
to be exercised if the Shanta share price exceeds 15p for 15 consecutive trading
days 12 months after the date of grant. Â The price of ordinary shares averaged
2.92p per share during the month of May 2009. Participants in the financing
agreed not to dispose of the shares for 90 days from the date of allotment.
DRA (process engineers to the feasibility study) subsequently agreed to accept
shares in lieu of cash due for work completed directly for the feasibility study
and agreed to contribute additional funding. Some participants in the fund
raising required South African foreign exchange control approvals prior to
providing the funds and agreements were dependant on this being obtained.
As a result of the conditional agreements and described above, the Company has
today agreed to issue a total of 11,540,033 shares at 8p per share and
5,770,016 warrants to the parties in connection with the financing and in lieu
of fees due. Of the total issue of shares, 9,906,046 shares have been placed for
cash to raise £792,483.68 (before expenses) and 1,633,987 shares have been
issued in lieu of fees due to be paid in cash. The parties involved in the
financing have agreed that they will not sell any of the shares issued to them
within 90 days of the date of issue.
DRA will receive 1,633,987 shares at 8p per share and 816,994 warrants in
respect of work completed and 4,901,961 shares at 8p per share and 2,450,980
warrants in respect of the financing.
Application will be made to the London Stock Exchange plc for 11,540,033 shares
to be admitted to trading on AIM and it is expected that admission will take
place at 8.00 a.m. on 9 July 2010. The shares will, when issued, rank pari
passu in all respects with the Company's existing ordinary shares.
Following the issue of 11,540,033 ordinary shares of 0.01p each as described
above, the Company will have a total of 127,032,887 voting shares in issue.
For further information:
Shanta Gold Limited
http://www.shantagold.com
Walton Imrie
Mobile: +27 (0) 82 444 2851
David Scott
Mobile: + 255 (0) 784 366146
Gareth Taylor
Mobile: +255(0)757732484( )
Walter Vorwerk
Moblie: +27 (0)83Â 308 0080
Fairfax I.S. PLC
Ewan Leggat/Laura Littley
+44 (0) 20 7598 5368
[HUG#1429715]
This announcement is distributed by Thomson Reuters on behalf of Thomson Reuters clients.
The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and other applicable laws; and
(ii) they are solely responsible for the content, accuracy and originality of the information contained therein.
All reproduction for further distribution is prohibited.
Source: Shanta Gold Limited via Thomson Reuters ONE