Revised Feasibility Study - New Luika Gold Mine

Shanta Gold Limited ("Shanta Gold" or the "Company") Revised Feasibility Study - New Luika Gold Mine The Board of Shanta Gold is pleased to announce the results of a revision to the feasibility study for the New Luika Gold Mine ("NLGM"). This revision has its origin in the resource estimate update that was announced on 5 May 2011. The study has determined a significantly improved net present value of $66.15 million from $37.5 million for the project as advised in the preliminary study on 6 July 2010. The improvement has resulted from both improved grades and additional tonnage available over the 12 year life of mine determined at present. The results of the revised feasibility study are set out below: +----------------------------------------+---------+ | Total tons mined (million) | 45.8 | +----------------------------------------+---------+ | Total tons treated (million | 5.6 | +----------------------------------------+---------+ | Annual treatment rate (tons) | 547,000 | +----------------------------------------+---------+ | Total construction cost | $29.4 | +----------------------------------------+---------+ | Total gold produced (million ounces) | 0.445 | +----------------------------------------+---------+ | Average annual production of gold (oz) | 40,484 | +----------------------------------------+---------+ | Escalated average cost per ounce (US$) | 1,015 | +----------------------------------------+---------+ | Return on investment | 71% | +----------------------------------------+---------+ | Net present value (11%) | $66.15m | +----------------------------------------+---------+ The purchase of the mills was announced on 23 November 2010. The rated capacity of the mills is 100 tonnes per hour (tph). The revised feasibility plans to treat ore at 50tph from mining operations and to treat 25tph sourced from free dig lower grade gravels available at the Luika pit. In addition, the carbon in leach (CIL) tank design has been increased to ensure 12 hours of contact time at a 100tph throughput rate. A further technical change has been to provide for onsite power generation for the full load required at NLGM. The Tanzanian power supply infrastructure, while providing cheaper power is unreliable at present and independence from the national grid is required to ensure continuous production. Increases in the size of the ore resource and improved grades have meant that the mining and treatment schedule has been revised to bring the Bauhinia Creek orebody into production as soon as possible. This has meant that waste stripping has been brought forward from year 1 to commence immediately and, as a result, the amount of working capital required has increased by approximately US$13m. Based on the revised mine planning the feasibility study estimates that gold production, mining grade and cost per ounce in the first three years are expected to be as follows: +------+---------------+-------+----------------+ |   | Gold produced | Grade | Cost per ounce | | | | G/ton | | +------+---------------+-------+----------------+ | 2012 | 65-70,000 | 4.24 | 470-510 | +------+---------------+-------+----------------+ | 2013 | 55-60,000 | 3.56 | 610-660 | +------+---------------+-------+----------------+ | 2014 | 55-60,000 | 3.56 | 625-675 | +------+---------------+-------+----------------+ Construction of NLGM has been underway since first quarter 2011. Pre- stripping of the first operational pit (Bauhinia Creek) has been underway for the last 4 weeks.  The following is the expected timetable for the completion of the mine: +----------------------------+----------------------+ | Mill foundation completion | 31 July 2011 | +----------------------------+----------------------+ | Mill delivery | 31 July 2011 | +----------------------------+----------------------+ | Leach tank construction | July - September2011 | +----------------------------+----------------------+ | Crusher installation | July - August2011 | +----------------------------+----------------------+ | Smelt house construction | October 2011 | +----------------------------+----------------------+ | Plant commissioning | November 2011 | +----------------------------+----------------------+ | Gold production | December 2011 | +----------------------------+----------------------+ Walton Imrie, Executive Chairman, said "the excellent outcome of drilling in 2010 has translated into a significant improvement in the returns expected from the New Luika Gold Mine, and with particularly robust cash flows in the early years of operation. My thanks go to the teams responsible for the improvement in the resource and for the outstanding efforts in completing the revision to the feasibility in short order." For further information: Shanta Gold Limited http://www.shantagold.com Walton Imrie Mobile: +27 (0) 82 444 2851 Walter Vorwerk Mobile: +27 (0) 83 308 0080 Gareth Taylor Mobile: +255(0)757732484 Fairfax I.S. PLC Ewan Leggat/Laura Littley +44 (0) 20 7598 5368 Tavistock Communications Emily Fenton/Ed Portman +44 (0) 20 7920 3150 This announcement is distributed by Thomson Reuters on behalf of Thomson Reuters clients. The owner of this announcement warrants that: (i) the releases contained herein are protected by copyright and other applicable laws; and (ii) they are solely responsible for the content, accuracy and originality of the information contained therein. Source: Shanta Gold Limited via Thomson Reuters ONE [HUG#1523939]
UK 100

Latest directors dealings