Songa Venus achieved an operating efficiency of 100% during the month continuing working for Petronas Carigali in Malaysia.

Songa Mercur achieved 86% financial efficiency during the month as the rig experienced problems with the BOP system during the first part of the month.  These problems were resolved and rectified with majority of time on contractual day rate, and the rig have since operated well continuing working for Zarubezhneft in Cuba.

Songa Dee achieved an operating efficiency of 95% during the month continuing working for Statoil.

Songa Delta achieved an operating efficiency of 98% during the month, continuing working for Statoil.

Songa Trym continued its upgrade project outside CCB during the month.  For further details, reference is given to the separate press release issued.    

Songa Eclipse achieved an operating efficiency of 100% during the days working for Total E/P Angola prior to delivery to Seadrill January 3, 2013. 

4 February 2013
Limassol, Cyprus

This information is subject of the disclosure requirements pursuant to section 5-12 of the Norwegian Securities Trading Act.




This announcement is distributed by Thomson Reuters on behalf of Thomson Reuters clients.

The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and other applicable laws; and
(ii) they are solely responsible for the content, accuracy and originality of the
information contained therein.

Source: Songa Offshore SE via Thomson Reuters ONE

HUG#1675398
UK 100

Latest directors dealings