Quarterly Operational Report December 2015

RNS Number : 5439M
South32 Limited
21 January 2016
 

South32 Limited

(Incorporated in Australia under the Corporations Act 2001)

(ACN 093 732 597)

ASX, LSE, JSE Share Code: S32

ISIN: AU000000S320

South32 Limited

QUARTERLY OPERATIONAL REPORT DECEMBER 2015

 

·   By optimising the performance of our high quality operations and balance sheet we have delivered a significant reduction in net debt during the December 2015 half year, despite the challenging external environment. Our current estimate for net debt at 31 December 2015 is US$115M.

·    A significant increase in ore grades and recoveries underpinned a 13% increase in Cannington zinc production to a record 41.8kt.

·   A further improvement in concentrator performance at Australia Manganese contributed to a 6% increase in ore production to a record 1.6Mt.

·     Strong and stable hydrate production at Worsley Alumina supported a 2% increase in saleable alumina production to a record 2.0Mt.

·     Ore production at South Africa Manganese was impacted by the temporary suspension of operations during the period. The strategic review, which is nearing completion, will define the optimal configuration and production profile for the South Africa Manganese mines and smelter to ensure cash outflows are mitigated in this difficult pricing environment.

·   While FY16 production guidance is maintained for the majority of our upstream operations, we have lowered our estimate for Illawarra Metallurgical Coal production by 7% to 8.3Mt after difficult geological conditions were encountered during the period.

·   The Appin Area 9 project is 95% complete, with commissioning expected to start in the March 2016 quarter. The project, which sustains Illawarra Metallurgical Coal production capacity, is now more than 30% below the original budget of US$845M and three months ahead of schedule.

 

Graham Kerr, South32 CEO said:

 

"Following another solid quarter of operating performance we remain on track to meet production guidance for the majority of our upstream operations.

 

"Our relentless focus on safety, volume, costs and capital expenditure has allowed us to reduce net debt by almost US$300 million in the December 2015 half year, despite continuing weakness in commodity markets.

 

"In order to protect our strong financial position in the currently challenging environment we have already cut or suspended production at our South Africa Manganese ore mines and Alumar, Metalloys, TEMCO and South Africa Aluminium smelters. Further decisive action will be taken as we seek to maximise short-term cash flow while preserving longer-term value."

  

 

 

 

Production summary

 

 

 

 

 

 

 

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

QoQ

Alumina production (kt)

2,633

2,666

1%

 

1,398

1,364

1,302

(5%)

Aluminium production (kt)

517

485

(6%)

 

256

244

241

(1%)

Energy coal production (kt)

17,405

17,037

(2%)

 

8,882

8,698

8,339

(4%)

Metallurgical coal production (kt)

3,858

3,298

(15%)

 

2,018

2,079

1,219

(41%)

Manganese ore production (kt)

2,733

2,346

(14%)

 

1,377

1,437

909

(37%)

Manganese alloy production (kt)

223

131

(41%)

 

121

65

66

2%

Payable nickel production (kt)

21.2

17.5

(17%)

 

10.5

8.7

8.8

1%

Silver production (koz)

12,235

11,878

(3%)

 

5,534

6,278

5,600

(11%)

Lead production (kt)

98.6

97.5

(1%)

 

49.6

49.1

48.4

(1%)

Zinc production (kt)

37.0

41.8

13%

 

17.0

19.6

22.2

13%

 

Unless otherwise noted: percentage variance relates to the relative performance during the December 2015 half year compared with the December 2014 half year (HoH) or the December 2015 quarter compared with the September 2015 quarter (QoQ); production and sales volumes are reported on an attributable basis. Variance analysis relates to HoH performance, as defined above.

 

CORPORATE UPDATE

 

·  During the December 2015 half year, South32 invested US$7M on exploration, of which US$2M will be capitalised. Our exploration activities focused on metallurgical coal and silver in Australia, and nickel in Colombia.

·    A review of corporate functional support completed during the December 2015 half year is expected to deliver an annualised saving of approximately US$30M in FY16 Group and Unallocated costs. Corporate functional expenditure of approximately US$100M is expected in the 2016 financial year.

·   South32's Underlying effective tax rate (ETR) largely reflects the geographic distribution of the Group's profit. The corporate tax rates applicable to South32 include: Australia 30%; South Africa 28%; Colombia 39%; and Brazil 34%. It should, however, be recognised that permanent differences have a disproportionate effect on the Group's tax rate when commodity prices and profit margins are compressed. In this context, an Underlying ETR1 of approximately 35% is now expected for the December 2015 half year and this will rise for the full year should commodity prices and margins remain compressed.

·   South32 capital expenditure guidance for FY16 of US$700M was predicated on several assumptions, including an average AUD:USD exchange rate of 0.78 and average USD:ZAR exchange rate of 12.42. Updated capital expenditure guidance will be provided when the Company reports its December 2015 half year financial results to reflect the general appreciation of the US dollar against a basket of producer currencies, and the Group's ongoing efforts to optimise its investment activities.

·    The Group's current estimate for net debt2 at 31 December 2015 is US$115M (US$196M at 30 September 2015 and US$402M at 30 June 2015) and includes finance leases totalling US$595M (US$575M at 30 September 2015 and US$631M at 30 June 2015). Our cash balance also incorporates a US$46M benefit following the resolution of legacy tax disputes during the December 2015 half year. The Group's strong balance sheet remains a key point of differentiation and we are firmly committed to an investment grade credit rating.

 

 

Upstream production guidance (South32's share)

FY15

FY16e

Worsley Alumina

 

 

Alumina production (kt)

3,819

3,950

Brazil Alumina

 

 

Alumina production (kt)

1,328

1,320

South Africa Energy Coal3

 

 

Domestic coal production (kt)

18,123

16,650

Export coal production (kt)

16,150

15,300

Illawarra Metallurgical Coal

 

 

Metallurgical coal production (kt)

7,455

(Revised) 6,900

Energy coal production (kt)

1,471

(Revised) 1,350

Australia Manganese

 

 

Manganese ore production (kt)

2,942

3,050

South Africa Manganese

 

 

Manganese ore production4 (kt)

2,273

(Remains under review)

Cerro Matoso

 

 

Payable nickel production (kt)

40.4

36.5

Cannington

 

 

Payable silver production (koz)

22,601

21,650

Payable lead production (kt)

183

175

Payable zinc production (kt)

72

80

 

 

WORSLEY ALUMINA

(86% share)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Alumina production (kt)

1,953

1,993

2%

 

1,060

1,031

962

(9%)

(7%)

Alumina sales (kt) 

1,943

1,898

(2%)

 

1,068

930

968

(9%)

4%

 

Worsley Alumina saleable production increased by 2% (or 40kt) to a record 1,993kt in the December 2015 half year as the operations processed stockpiled alumina hydrate and benefitted from additional operating efficiency gains. The 2% decline in sales reflected a timing difference as one shipment slipped into the March 2016 quarter.

Planned calciner maintenance in the December 2015 quarter led to a 7% QoQ reduction in saleable alumina production. The next major calciner outage is now scheduled for the December 2016 quarter. FY16 saleable alumina production guidance remains unchanged at 3.95Mt.

 

SOUTH AFRICA ALUMINIUM

(100%)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Aluminium production (kt)

356

352

(1%)

 

176

178

174

(1%)

(2%)

Aluminium sales (kt) 

352

363

3%

 

178

185

178

0%

(4%)

 

South Africa Aluminium saleable production of 352kt was largely unchanged in the December 2015 half year, while the 2% reduction in quarterly production volumes reflected our decision to suspend production in 22 pots in September 2015. This suspension of activity is expected to deliver an incremental improvement in cash flow as planned pot relining activity is deferred. A loss of 18kt is anticipated should the 22 pots remain offline for the remainder of FY16, with a marginal YoY reduction in production likely.

 

 

MOZAL ALUMINIUm

(47.1% share)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Aluminium production (kt)

135

133

(1%)

 

67

66

67

0%

2%

Aluminium sales (kt) 

137

121

(12%)

 

73

53

68

(7%)

28%

 

Mozal Aluminium saleable production of 133kt was largely unchanged in the December 2015 half year. Production increased marginally in the December 2015 quarter following a modest reduction in the number of load-shedding events during the period. The 12% decline in sales reflected the scheduling of shipments between periods. Aluminium production is expected to remain broadly unchanged in FY16.

 

 

Brazil Alumina

(Refinery 36% share, Smelter 40% share)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Alumina production (kt)

680

673

(1%)

 

338

333

340

1%

2%

Alumina sales (kt) 

694

661

(5%)

 

371

320

341

(8%)

7%

Aluminium production (kt)

26

0

(100%)

 

13

0

0

(100%)

N/A

Aluminium sales (kt) 

25

0

(100%)

 

13

0

0

(100%)

N/A

 

Brazil Alumina saleable alumina production of 673kt was largely unchanged in the December 2015 half year and FY16 alumina production guidance of 1.32Mt remains unchanged. The 5% decline in sales reflected a timing difference as one shipment slipped into the March 2016 quarter.

Aluminium production was first curtailed at Brazil Alumina in July 2013 and the suspension of all smelting activity was announced in March 2015. With the economics unlikely to support the recommencement of smelting activity we have sold forward power for the 2017 calendar year and served termination notice on our contract with Eletronorte for the remaining years of the contract. As a result of this decision, power sales are not expected to contribute to Underlying EBIT beyond FY16 as a minor provision will be booked in our June 2016 financial year statements to reflect the anticipated cash outflow associated with this contract across the 2017 and 2018 financial years. Unhedged power sales, inclusive of this provision, are now expected to contribute approximately BRL235M to Underlying EBIT in FY16 and will be skewed to the first half.

 

 

South Africa Energy Coal

(100%)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Energy coal production (kt)

16,525

16,379

(1%)

 

8,499

8,292

8,087

(5%)

(2%)

Domestic sales (kt) 

9,137

9,080

(1%)

 

4,734

4,246

4,834

2%

14%

Export sales (kt)

7,913

8,021

1%

 

4,174

4,132

3,889

(7%)

(6%)

 

South Africa Energy Coal saleable production of 16.4Mt was broadly unchanged in the December 2015 half year as operational efficiencies at the Khutala underground mine and the Wolvekrans Middelburg Complex mitigated the impact of the planned closure of the opencast mine at Khutala. FY16 saleable production guidance remains unchanged at 31.95Mt (16.65Mt domestic, 15.30Mt export).

 

 

illawarra metallurgical coal

(100%)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Metallurgical coal production (kt)

3,858

3,298

(15%)

 

2,018

2,079

1,219

(40%)

(41%)

Metallurgical coal sales (kt)

3,447

3,147

(9%)

 

1,830

1,999

1,148

(37%)

(43%)

Energy coal production (kt)

880

658

(25%)

 

383

406

252

(34%)

(38%)

Energy coal sales (kt)

799

609

(24%)

 

426

391

218

(49%)

(44%)

 

Illawarra Metallurgical Coal saleable production decreased by 17% (or 782kt) to 3.96Mt in the December 2015 half year as challenging geological conditions were encountered at the Appin and Dendrobium mines, and a planned longwall move was completed during the December 2015 quarter. Another two longwall moves are expected to be completed in the March 2016 quarter, consistent with the mine plan. Accordingly, FY16 saleable coal production has been lowered by 7% to 8.25Mt (metallurgical coal 6.9Mt, energy coal 1.35Mt).

The Appin Area 9 project is 95% complete, with commissioning expected to start in the March 2016 quarter. The project, which sustains Illawarra Metallurgical Coal production capacity, is now more than 30% below the original budget of US$845M and three months ahead of schedule.

 

 

australia manganese

(60% share)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Manganese ore production (kt)

1,499

1,589

6%

 

773

857

732

(5%)

(15%)

Manganese ore sales (kt)

1,459

1,499

3%

 

725

749

750

3%

0%

Manganese alloy production (kt)

83

85

2%

 

48

44

41

(15%)

(7%)

Manganese alloy sales (kt)

77

76

(1%)

 

44

38

38

(14%)

0%

 

Australia Manganese saleable ore production increased by 6% (or 90kt) to a record 1,589kt in the December 2015 half year as the operation continued to optimise concentrator performance. The 15% reduction in saleable ore production in the December 2015 quarter was anticipated, ensuring FY16 production guidance remains unchanged at 3.05Mt. A higher strip ratio, planned maintenance and seasonal factors are expected to impact performance in the June 2016 half year.

Saleable manganese alloy production increased by 2% (or 2kt) to 85kt in the December 2015 half year. In response to market conditions, TEMCO has suspended production at one of its four furnaces for a minimum of three months. While production will be impacted in the June 2016 half year, customer commitments will continue to be met from inventory.

The Premium Concentrate Ore (PCO2) project is expected to increase GEMCO production capacity by 0.5Mt to 5.3Mtpa (100% basis). The project is now expected to be delivered under budget with first production anticipated in the June 2016 quarter, as planned.

 

 

SOUTH AFRICA manganese

(60% share)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Manganese ore production (kt)

1,234

757

(39%)

 

604

580

177

(71%)

(69%)

Manganese ore sales (kt)

1,189

879

(26%)

 

590

518

361

(39%)

(30%)

Manganese alloy production (kt)

140

46

(67%)

 

73

21

25

(66%)

19%

Manganese alloy sales (kt)

134

50

(63%)

 

65

25

25

(62%)

0%

 

South Africa Manganese saleable ore production decreased by 39% (or 477kt) to 757kt in the December 2015 half year following the suspension of operations at Wessels and Mamatwan in November 2015. South Africa Manganese saleable alloy production decreased by 67% (or 94kt) to 46kt following the suspension of three of the four high-carbon ferromanganese furnaces at Metalloys in May 2015. A strategic review, which is nearing completion, will define the optimal configuration and production profile for the South Africa Manganese mines and smelter to ensure cash outflows are mitigated in this difficult pricing environment.

 

 

cerro matoso

(99.9% share)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Payable nickel production (kt)

21.2

17.5

(17%)

 

10.5

8.7

8.8

(16%)

1%

Payable nickel sales (kt)

20.6

17.5

(15%)

 

10.1

8.7

8.8

(13%)

1%

 

Cerro Matoso payable nickel production decreased by 17% (or 3.7kt) to 17.5kt in the December 2015 half year as the average ore grade declined, consistent with the mine plan. FY16 production guidance of 36.5kt remains unchanged.

The higher grade La Esmeralda deposit has the potential to deliver an uplift in the average ore grade between 2018 and 2022. A new social and environmental licence to allow access to the ore body was granted in December 2015.

 

 

cannington

(100%)

 

South32's share

1H15

1H16

HoH

 

2Q15

1Q16

2Q16

2Q15
vs
2Q16

1Q16
vs
2Q16

Silver production (koz)

12,235

11,878

(3%)

 

5,534

6,278

5,600

1%

(11%)

Silver sales (koz)

12,715

11,898

(6%)

 

5,631

6,203

5,695

1%

(8%)

Lead production (kt)

98.6

97.5

(1%)

 

49.6

49.1

48.4

(2%)

(1%)

Lead sales (kt)

99.7

95.5

(4%)

 

48.5

48.7

46.8

(4%)

(4%)

Zinc production (kt)

37.0

41.8

13%

 

17.0

19.6

22.2

31%

13%

Zinc sales (kt)

33.5

41.2

23%

 

18.0

19.0

22.2

23%

17%

 

Cannington payable silver production decreased by a modest 3% (or 357koz) to 11.9Moz in the December 2015 half year as the average silver ore grade remained largely unchanged. Conversely, a significant increase in the average zinc ore grade and recovery underpinned a 13% increase in zinc production to a record 41.8kt. FY16 production guidance remains unchanged (payable silver 21.65Moz, payable lead 175kt, payable zinc 80kt) as the mine plan will deliver an increase in the ratio of zinc to lead concentrate over the remainder of the year.

Finalisation adjustments and the provisional pricing of Cannington concentrates will reduce Underlying EBIT by US$19M in the December 2015 half year (-US$43M in the June 2015 financial year; -US$40M December 2014 half year). Outstanding concentrate sales (containing 5.2Moz of silver, 45.7kt of lead and 16.0kt of zinc) were revalued at 31 December 2015. The final price of these sales will be determined in the second half of the 2016 financial year.

 

 

Notes:

1.   Provisional unaudited Underlying ETR for the December 2015 half year.

2.   Provisional unaudited net debt balance as at 31 December 2015.

3.   10% of South Africa Energy Coal is owned by an Employee Share Ownership Plan (ESOP) and a broad-based black economic empowerment (B-BBEE) consortium. The interests owned by the ESOP and B-BBEE consortium were acquired using vendor finance, with the loans repayable to South32 via distributions attributable to these parties, pro rata to their share in South Africa Energy Coal. Until these loans are repaid, South32's interest in South Africa Energy Coal is accounted at 100%.

4.   Consistent with the presentation of South32's segment information, South Africa Manganese ore production and sales have been reported at 60%. The Group's financial statement will continue to reflect a 54.6% interest in South Africa Manganese ore.

5.   Underlying EBIT is earnings before net finance costs, taxation and any earnings adjustments. Underlying EBIT is reported net of South32's share of net finance costs and taxation of equity accounted investments. Underlying EBITDA is Underlying EBIT, before depreciation and amortisation.

6.   Figures in italics indicate that this figure has been adjusted since it was previously reported.

7.   The following abbreviations have been used throughout this report: grams per tonne (g/t); tonnes (t); thousand tonnes (kt); thousand tonnes per annum (ktpa); million tonnes (Mt); million tonnes per annum (Mtpa); thousand ounces (koz); million ounces (Moz); thousand wet metric tonnes (kwmt); thousand dry metric tonnes (kdmt); megawatt (MW); Australian Securities Exchange (ASX); London Stock Exchange (LSE); and Johannesburg Stock Exchange (JSE). 

 

operating performance

South32's share

1H15

1H16

 

2Q15

3Q15

4Q15

1Q16

2Q16

Worsley Alumina
(86% share)

 

 

 

 

 

 

 

 

Alumina hydrate production (kt)

1,956

1,970

 

976

931

987

990

980

Alumina production (kt)

1,953

1,993

 

1,060

937

929

1,031

962

Alumina sales (kt)

1,943

1,898

 

1,068

866

1,048

930

968

South Africa Aluminium
(100%)

 

 

 

 

 

 

 

 

Aluminium production (kt)

356

352

 

176

168

175

178

174

Aluminium sales (kt)

352

363

 

178

166

177

185

178

Mozal Aluminium
(47.1% share)

 

 

 

 

 

 

 

 

Aluminium production (kt)

135

133

 

67

65

65

66

67

Aluminium sales (kt)

137

121

 

73

66

70

53

68

Brazil Alumina
(alumina 36% share, aluminium 40% share)

 

 

 

 

 

 

 

 

Alumina production (kt)

680

673

 

338

311

337

333

340

Alumina sales (kt)

694

661

 

371

285

330

320

341

Aluminium production (kt)

26

0

 

13

12

2

0

0

Aluminium sales (kt)

25

0

 

13

13

3

0

0

South Africa Energy Coal
(100%)

 

 

 

 

 

 

 

 

Energy coal production (kt)

16,525

16,379

 

8,499

9,240

8,508

8,292

8,087

Domestic sales (kt)

9,137

9,080

 

4,734

4,921

4,358

4,246

4,834

Export sales (kt)

7,913

8,021

 

4,174

4,354

4,123

4,132

3,889

Illawarra Metallurgical Coal
(100%)

 

 

 

 

 

 

 

 

Metallurgical coal production (kt)

3,858

3,298

 

2,018

1,614

1,983

2,079

1,219

Metallurgical coal sales (kt)

3,447

3,147

 

1,830

1,810

2,067

1,999

1,148

Energy coal production (kt)

880

658

 

383

185

406

406

252

Energy coal sales (kt)

799

609

 

426

272

307

391

218

Australia Manganese
(60% share)

 

 

 

 

 

 

 

 

Manganese ore production (kt)

1,499

1,589

 

773

682

761

857

732

Manganese ore sales (kt)

1,459

1,499

 

725

686

700

749

750

Manganese alloy production (kt)

83

85

 

48

41

43

44

41

Manganese alloy sales (kt) 

77

76

 

43

26

36

38

38

South Africa Manganese
(60% share)

 

 

 

 

 

 

 

 

Manganese ore production (kt)

1,234

757

 

604

548

492

580

177

Manganese ore sales (kt)

1,189

879

 

590

614

407

518

361

Manganese alloy production (kt)

140

46

 

73

68

38

21

25

Manganese alloy sales (kt) 

134

50

 

65

70

47

25

25

 

 

South32's share

1H15

1H16

 

2Q15

3Q15

4Q15

1Q16

2Q16

Cerro Matoso

(99.9% share)

 

 

 

 

 

 

 

 

Ore mined (kwmt)

3,339

3,017

 

1,827

1,826

1,156

1,531

1,486

Ore processed (kdmt)

1,335

1,312

 

678

698

596

639

673

Ore grade processed (%, Ni)

1.72

1.53

 

1.69

1.63

1.59

1.55

1.52

Payable nickel production (kt) 

21.2

17.5

 

10.5

10.6

8.6

8.7

8.8

Payable nickel sales (kt)

20.6

17.5

 

10.1

11.0

9.0

8.7

8.8

Cannington

(100%)

 

 

 

 

 

 

 

 

Ore mined (kt)

1,748

1,743

 

925

813

857

910

833

Ore processed (kt)

1,669

1,657

 

850

791

829

838

819

Payable silver ore grade processed (g/t, Ag)

272

266

 

246

247

235

272

260

Payable lead ore grade processed (%, Pb)

7.0

7.0

 

7.0

6.3

6.4

6.9

7.1

Payable zinc ore grade processed (%, Zn)

3.5

3.7

 

3.2

3.2

3.5

3.4

4.0

Payable silver production (koz)

12,235

11,878

 

5,534

5,130

5,236

6,278

5,600

Payable silver sales (koz)

12,715

11,898

 

5,631

4,972

6,144

6,203

5,695

Payable lead production (kt)

98.6

97.5

 

49.6

40.1

44.3

49.1

48.4

Payable lead sales (kt)

99.7

95.5

 

48.5

40.3

48.8

48.7

46.8

Payable zinc production (kt)

37.0

41.8

 

17.0

16.4

18.9

19.6

22.2

Payable zinc sales (kt)

33.5

41.2

 

18.0

17.1

16.2

19.0

22.2

 

Further information

Investor Relations

 

MEDIA Relations

Leng Lau

 

Jill Thomas

T

+61 8 9324 9008

 

T

+61 8 9324 9191

M

+61 (0) 408 202 698

 

M

+61 (0) 423 259 190

E

Leng.Lau@south32.net

 

E

Jill.Thomas@south32.net

 

 

 

 

 

Susie Bath

 

Tony Johnson

T

+61 8 9324 9647

 

T

+61 8 9324 9190

M

+61 (0) 418 933 792

 

M

+61 (0) 439 500 799

E

Susie.Bath@south32.net

 

E

Tony.Johnson@south32.net

 

 

 

 

 

Paul Formosa

 

 

 

T

+61 8 9324 9376

 

 

 

M

+61 (0) 431 152 742

 

 

 

E

Paul.Formosa@south32.net

 

 

 

 

 

 

 

 

21 January 2016
JSE Sponsor: UBS South Africa (Pty) Ltd


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCFMGZMVMFGVZG
UK 100

Latest directors dealings