Large Combustion Plant Direct

RNS Number : 7895I
Scottish & Southern Energy PLC
24 November 2008
 



24 November 2008


SCOTTISH AND SOUTHERN ENERGY PLC

ARTICLE 5(1) OF THE LARGE COMBUSTION PLANT DIRECTIVE


Scottish and Southern Energy plc ('SSE') is applying to the Environment Agency for what should be the final extension of its existing derogations under Article 5 (1) of the Large Combustion Plant Directive, in respect of Fiddler's Ferry and Ferrybridge power stations.


The extension, to 7 January 2009, is to allow SSE to continue to operate the plant opted in to the Directive, while undertaking the hot commissioning of flue gas desulphurisation equipment. SSE continues to expect to do this during December, in line with the timetable set out in its interim results statement on 12 November 2008and is applying for the extension to allow maximum operational flexibility during the process.







This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCFKQKDQBDDODB

Companies

SSE (SSE)
UK 100