Steppe Cement Limited
15 December 2005
Steppe Cement Limited
Market Update on Proposals to Expand Production Capacity and Financing - 15
December 2005
The directors of Steppe Cement are pleased to update the market on proposals to
refurbish the Company's two dry-process clinker production kilns.
Clinker Production Capacity
Since admission to AIM in September 2005, the Company has continued to operate
its four wet-process kilns (numbers 1 to 4) which have a combined annual clinker
production capacity of 600,000 tonnes. At the same time the Company has
progressed with studies to recommence production from its two dry-process kilns
(numbers 5 and 6) which have been mothballed since 1995.
Each of the dry-process kilns had a clinker production capacity of 1 million
tonnes per annum prior to them being mothballed.
The findings of the studies into the dry-process lines and proposals of the
Company arising there from are:
Line number 5 which was commissioned in 1975, had some design faults that
require the cyclones, kiln and cooler to be rebuilt. The Company proposes to
maintain the crushers, raw materials, coal and cement mills. Filters and control
equipment will be upgraded to western standards. It is anticipated that this
substantial refurbishment will cost US$73 million inclusive of interest and
taxes during construction and will take 18 to 24 months to complete. The company
has tendered 3 out of 9 packages and it expects that the kiln will be
re-commissioned before the end of 2007. It will have a capacity of 1 million
tons of clinker (1.3 million tons cement).
Line number 6 was commissioned in 1983 with an improved design from that used on
the number 5 line and the Company has been advised by its technical consultants
that it can be refurbished and re-commissioned at a cost estimated at
approximately US$20 million. A project management team has been recruited to
undertake this project and work has commenced. Present estimates are that this
work will be unlikely to be completed before the winter of 2006/7 On
re-commissioning the number 6 line will have a maximum design capacity of 0.8
million tons per annum of clinker (1.0 million tons of cement).
Financing Proposals for the Expansion of Production Capacity: EBRD loan
agreement, proposed bond issue and new equity capital
The Company has signed a loan agreement with the European Bank for
Reconstruction and Development (EBRD) whereby EBRD will provide loans of US$35
million towards the dry-process kiln refurbishment costs. An agreement has also
been signed with Halyk Finance of Kazakhstan, whereby Halyak Finance will
distribute to Kazakh domestic investors two fixed coupon, medium term, Tenge
denominated bonds, equivalent in total to US$15 million. The balance required to
finance the two re-furbishment projects, of US$43 million, will be met by
internally generated funds and by a proposed share placing which it is
anticipated will raise approximately US$20 million of new equity.
The Company has received expressions of interest from several parties wishing to
subscribe to new equity and anticipates that it will complete such an issue no
later than January 2006.
The material terms of the two loan facilities are summarised as follows:
EBRD (US$35 million principal): Repayment term 10 equal instalments from May
2008 to November 2012, establishment fee 1% Front-end plus 0.5% commitment fee
on funds not drawn down, coupon LIBOR +3.75%.
Halyk Finance (Two tranches of Tenge 1,025 million-equivalent to US$7.5 million
each principal): Repayment term 5 years, establishment fee 1%, coupon 9%pa.
Future Production and Demand
During 2005, the shortage of cement production capacity in Kazakhstan was met by
imports of 1.5 million tonnes from neighbouring countries. It is anticipated by
the Company that demand will increase further in 2006 and beyond as the Kazakh
GDP continues to grow in tandem with the increase in production of oil and other
commodities. Kazakhstan's ability to import cement is limited by railway
capacity and the Company believes that it is vital for the economy of the
country that it increases its production capacity as quickly as possible. From
700,000 tons of cement in 2005 the Company expects to be able to produce 800,000
tons in 2006, 1.5 million tons in 2007, and 2.5 million tons in 2008.
This information is provided by RNS
The company news service from the London Stock Exchange
*A Private Investor is a recipient of the information who meets all of the conditions set out below, the recipient:
Obtains access to the information in a personal capacity;
Is not required to be regulated or supervised by a body concerned with the regulation or supervision of investment or financial services;
Is not currently registered or qualified as a professional securities trader or investment adviser with any national or state exchange, regulatory authority, professional association or recognised professional body;
Does not currently act in any capacity as an investment adviser, whether or not they have at some time been qualified to do so;
Uses the information solely in relation to the management of their personal funds and not as a trader to the public or for the investment of corporate funds;
Does not distribute, republish or otherwise provide any information or derived works to any third party in any manner or use or process information or derived works for any commercial purposes.
Please note, this site uses cookies. Some of the cookies are essential for parts of the site to operate and have already been set. You may delete and block all cookies from this site, but if you do, parts of the site may not work. To find out more about the cookies used on Investegate and how you can manage them, see our Privacy and Cookie Policy
To continue using Investegate, please confirm that you are a private investor as well as agreeing to our Privacy and Cookie Policy & Terms.