First Quarter Report to 30 September 2018

RNS Number : 8264F
Sylvania Platinum Limited
31 October 2018
 

 

 

 

 

 

 

                             _____________________________________________________________________________________________________________________________

 

31 October 2018

 

 

Sylvania Platinum Limited

 ("Sylvania", "the Company" or "the Group")

 AIM (SLP)

 

First Quarter Report to 30 September 2018

 

The Directors are pleased to present the results for the quarter ended 30 September 2018 ("Q1" or the "quarter").  Unless otherwise stated, the consolidated financial information contained in this report is presented in USD.

 

Achievements

·      19,137 4E PGM ounces produced in Q1;

·      Group EBITDA of $7.1 million;

·      Total operating costs down 2% in ZAR terms and 12% in USD quarter on quarter;

·      Cash balance up 26% quarter on quarter to $17.7 million from $14.0 million;

·      Capital expenditure in line with planned expansion for Project Echo;

·      Millsell operation achieved four years lost time injury (LTI) free during the quarter; and

·      Completed the non-UK Shareholders buy-back program on 24 August 2018 and a total of 2,407,481 shares were cancelled.

 

Challenges

·      Utility infrastructure and supply of power continues to present challenges to existing operations and the execution of expansion projects;

·      The consistently low Platinum price continues to put pressure on the gross basket price, although weaker ZAR and strong Palladium and Rhodium prices are mitigating factors; and  

·      Lower recovery efficiencies at Millsell MF2 module, due to challenges with fines flotation mechanisms, are currently being upgraded.

 

Opportunities

·      Project Echo MF2 module for Mooinooi on track for commissioning in H2 FY2019;

·      Relocation of redundant Steelpoort chrome circuit to Lesedi in progress to improve chrome removal ahead of flotation and to enable higher PGM feed; and

·      Company continues to generate sufficient cash reserves to fund capital expansion projects.

 

 

Commenting on the Q1 results, Sylvania's CEO Terry McConnachie said:

 

"The SDO teams have once again performed consistently by producing 19,137 ounces this quarter, the second highest quarterly production in the history of the Company.  Preceded by last quarter's production record, this period was impacted by some operational instability and 'teething' issues at Doornbosch and Mooinooi, which have since been resolved and Management continues to focus on optimisation initiatives on operations.  As promised, we have endeavoured to keep costs controlled and our cash reserves remain at a level which will enable the Company to continue to fund capital projects and Project Echo moving forward."

 

USD

Unit

Unaudited

Unit

ZAR

Q4 FY2018

Q1 FY2019

% Change

% Change

Q1 FY2019

Q4 FY2018





Production





643,019

635,051

T

Plant Feed

T

-1%

635,051

643,019

2.46

2.44

g/t

Feed Head Grade

g/t

-1%

2.44

2.46

338,167

328,127

T

PGM Plant Feed Tons

T

-3%

328,127

338,167

3.75

3.75

g/t

PGM Plant Feed Grade

g/t

0%

3.75

3.75

49.67%

48.39%

%

PGM Plant Recovery

%

-3%

48.39%

49.67%

20,278

19,137

Oz

Total 4E PGMs

Oz

-6%

19,137

20,278

27,062

25,723

Oz

Total 6E PGMs

Oz

-5%

25,723

27,062









1,167

1,149

$/oz

Average gross basket price

R/oz

5%

16,263

15,509













Financials





16,243

14,230

$'000

Revenue (4E)

R'000

-3%

200,032

205,372

1,653

1,634

$'000

Revenue (by products)

R'000

10%

22,964

20,905

2,195

1,370

$'000

Sales adjustments

R'000

-31%

19,261

27,756

20,092

17,234

$'000

Net revenue

R'000

-5%

242, 257

254,032









11,052

9,726

$'000

Operating costs

R'000

-2%

136,754

139,732

615

464

$'000

General & administration

R'000

-16%

6,524

7,773

8,600

7,075

$'000

Group EBITDA

R'000

-8%

99,477

108,682

65

182

$'000

Net Interest

R'000

212%

2,560

820

3,914

3,785

$'000

Net profit

R'000

8%

53,220

49,489









1,508

1,205

$'000

Capital Expenditure

R'000

-11%

16,942

19,070









14,017

17,719

$'000

Cash Balance

R'000

41%

249,126

177,217











R/$

Ave R/$ rate

R/$

11%

14.06

12.64













Unit Cost/Efficiencies





553

508

$/oz

SDO Cash Cost Per 4E PGM oz

R/oz

2%

7,137

6,996

415

378

$/oz

SDO Cash Cost Per 6E PGM oz

R/oz

1%

5,310

5,242

562

531

$/oz

Group Cash Cost Per 4E PGM oz

R/oz

5%

7,461

7,101

421

395

$/oz

Group Cash Cost Per 6E PGM oz

R/oz

4%

5,551

5,323

550

540

$/oz

All-in sustaining cost (4E)

R/oz

9%

7,592

6,953

612

593

$/oz

All-in cost (4E)

R/oz

8%

8,338

7,740

1   The Sylvania cash generating subsidiaries are incorporated in South Africa with the functional currency of these operations being ZAR.  Revenues from the sale of PGMs are incurred in USD and then converted into ZAR.  The Group's reporting currency is USD as the parent company is incorporated in Bermuda.  Corporate and general and administration costs are incurred in USD, GBP and ZAR. 

 


A. OPERATIONAL OVERVIEW

 

Health, safety and environment

During the past quarter, the Millsell operation achieved the significant safety milestone of being LTI- free for four years, and all SDO operations performed well without any significant health or environmental incidents during the period.  Lesedi remains seven years LTI-free, while Tweefontein and Doornbosch plants both remain more than six years LTI-free. 

 

Operational performance

The SDO delivered a solid performance of 19,137 ounces for Q1 which is the second highest quarterly performance for operations.  While PGM plant feed grade remained static quarter on quarter, the PGM plant feed tons and recovery efficiency were both 3% lower, resulting in a 6% decrease in PGM ounces compared to the Q4 FY2018 record performance. 

 

The lower PGM plant feed tons were primarily due to the downtime and feed instability associated with the commissioning of a new process circuit at Doornbosch during the quarter as well as some operational challenges at Mooinooi during September 2018 that have since been resolved.  PGM recovery efficiencies were impacted by a lower percentage of fresh current arisings feed to some operations compared to the previous quarter as well as oil-contaminated feed material received at the Mooinooi operation that negatively impacted the PGM flotation process.

 

The SDO cash costs for the period in ZAR terms increased 2% to ZAR7,137/ounce, which was attributable to lower ounce production as a result of lower than planned current arisings supplemented with lower grade dump tons. In USD terms, cash costs decreased by 8% to $508/ounce, assisted by an 11% weakening of the ZAR in the ZAR/USD exchange rate during the period.  Capital expenditure reduced 20% quarter-on-quarter based on the current capital project schedule and in line with Project Echo construction plan.

 

Operational focus areas  

Operational challenges experienced at Millsell after the commissioning of the Millsell MF2 module earlier this year resulted in some design changes and upgrades to flotation mechanisms which will enable improved PGM recoveries during Q2.

 

Process circuit modifications, utilising enhanced fine screening technology for more efficient upgrading of PGMs, at Doornbosch, Millsell and Tweefontein will be completed in Q2, and optimisation of these new circuits will be done post-commissioning in order to further improve PGM feed grades and ounce production.

 

Operational opportunities 

The Project Echo MF2 module for Mooinooi, which is being fast-tracked to counter the previously communicated delay in the execution of the Tweefontein MF2 module of Project Echo, is progressing well and is planned to enable SDO to deliver on the Group production forecast of 76,000 to 78,000 ounces as announced in the Annual Report in August 2018.

 

The Lesedi chrome plant project, comprising of the dismantling and relocation of the redundant Steelpoort chrome circuit, has commenced and is expected to be completed in the second half of the financial year. This will enable chrome removal ahead of Lesedi's PGM plant, aligned with the standard SDO operating model employed at existing operations in the Group, and will contribute towards higher PGM feed grades and ounce production at the operation.

 

B. FINANCIAL OVERVIEW

 

Financial performance

The gross basket price for PGMs for the quarter was $1,149/ounce, a 2% decrease on Q4 FY2018 $1,167/ounce. The decrease in ounces quarter on quarter as well as the slightly lower basket price resulted in the net revenue dropping 14% to $17.2 million.  This is however in line with the Board's expectation for the quarter. 

 

The total operating costs decreased 2% in ZAR terms (the SDO functional currency) to ZAR137.0 million compared to the ZAR140.0 million in Q4 FY2018.  However, SDO cash costs per ounce increased 2% in ZAR terms from ZAR6,996/ounce to ZAR7,137ounce. The Group cash cost increased 5% from ZAR7,101/ounce in Q4 FY2018 to ZAR7,461/ounce, due to lower ounces in Q1 compared to Q4 FY2018.

 

The all-in sustaining cost for the Group increased by 9% against Q4 FY2018 to ZAR7,592/ounce (Q4: ZAR6,953/ounce).  The Group all-in cost for the quarter is ZAR8,338/ounce, an 8% increase on the ZAR7,740/ounce recorded in Q4 FY2018 due again to the lower production quarter on quarter. 

 

The Group general and administrative costs decreased 16% quarter on quarter in ZAR terms from ZAR7.7 million to ZAR6.5 million.

 

The surplus cash held and invested in ZAR earned interest at an average rate of 7%.  This cash will be used to fund the balance of Project Echo and other production optimisation projects. The increase in cash invested resulted in an increase in the net interest earned for the quarter.

 

The Group cash balance at 30 September 2018 was $17.7 million (including guarantees), a $3.7 million increase on the previous quarter's $14.0 million. Cash generated from operations before working capital movements was $7.1 million with net changes in working capital amounting to a decrease of $1.9 million due mainly to the increase in trade debtors which have a four-month payment pipeline.  An amount of $1.2 million was spent on capital and the impact of exchange rate fluctuations on cash held at the quarter end was a reduction of $0.3 million.

 

Financial management

Sylvania reports and generates its revenues in USD, however the operations' functional currency is ZAR.  This requires strict cashflow controls and management to ensure ongoing growth in cash reserves.  The Company remains committed to funding all planned capital projects and expansion from internal cash reserves.

 

Platinum has remained in the $800 range during the quarter, however Palladium has continued its steady increase over the quarter, increasing 15% from July 2018 and averaging $951 for Q1. Rhodium increased 10% from June to September 2018, and appears to be continuing this upward trend.  The increase in the by-product metal prices has also assisted in keeping the basket price at a favorable level, albeit lower than for the previous quarter.

 

In light of the current South African political environment, the ZAR/USD exchange rate remains just as volatile trading above ZAR14.00 to the USD for most of the quarter.  Although not under management's control, the metal prices and the ZAR/USD exchange rate continue to be monitored. 

 

C. EXPLORATION AND OPENCAST MINING PROJECTS

 

Northern Limb Projects

The Company has not pursued its exploration activities during the quarter, but will continue to defend title as and when this becomes necessary, until an improvement in market conditions warrants further development.   

  

D. CORPORATE ACTIVITIES

 

Share buy-back programme

The Share Buyback Programme (the Programme) closed on 24 August 2018. The Company purchased 2,407,481 Ordinary $0.01 Shares (Ordinary Shares) from small non-UK based shareholders at a price of A$0.1619 per Ordinary Share, representing 57.6% of the shares on offer under the Programme.

 

The shares purchased under the programme have been cancelled bringing the Company's issued share capital to 290,241,404 Ordinary Shares, of which a total of 4,206,885 Ordinary Shares are held in treasury. The total number of Ordinary Shares with voting rights in Sylvania is 286,034,519 Ordinary Shares.

 

 

 

 

 

 

CORPORATE INFORMATION

 

Registered and postal address:

Sylvania Platinum Limited


Clarendon House


2 Church Street


Hamilton HM 11


Bermuda



SA Operations postal address:

PO Box 976


Florida Hills, 1716


South Africa



 

Sylvania Website: www.sylvaniaplatinum.com

 

CONTACT DETAILS

 

For further information, please contact:


Terence McConnachie (Chief Executive Officer)

+44 777 533 7175



Nominated Advisor and Broker


Liberum Capital Limited

+44 (0) 20 3100 2000

Richard Crawley / Chris Britton




Communications


Alma PR Limited

+44 (0) 7580 216 203

Josh Royston / Helena Bogle


 

This announcement is released by Sylvania Platinum Limited and contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 ("MAR"), and is disclosed in accordance with the Company's obligations under Article 17 of MAR.

For the purposes of MAR and Article 2 of Commission Implementing Regulation (EU) 2016/1055, this announcement is being made on behalf of the Company by Terence McConnachie.

ANNEXURE

 

GLOSSARY OF TERMS FY2019

The following definitions apply throughout the period:

4E PGMs

4E PGM ounces include the precious metal elements Platinum, Palladium, Rhodium and Gold

6E PGMs

6E ounces include the 4E elements plus additional Iridium and Ruthenium

AGM

Annual General Meeting

AIM

Alternative Investment Market of the London Stock Exchange

All-in sustaining cost

Production costs plus all costs relating to sustaining current production and sustaining capital expenditure.

All-in cost

All-in sustaining cost plus non-sustaining and expansion capital expenditure

ASX

Australian Securities Exchange

Current risings

Fresh chrome tails from current operating host mines processing operations

DMR

Department of Mineral Resources

EBITDA

Earnings before interest, tax, depreciation and amortisation

EA

Environmental Authorisation

EIA

Environmental Impact Assessment

EIR

Effective interest rate

EMPR

Environmental Management Programme Report

GBP

Great British Pound

IASB

International Accounting Standards Board

IFRIC

International Financial Reporting Interpretation Committee

IFRS

International Financial Reporting Standards

I&APs

Interested and Affected Parties

Lesedi

Phoenix Platinum Mining Proprietary Limited, renamed Sylvania Lesedi

LSE

London Stock Exchange

LTI

Lost time injury

MF2

Milling and flotation technology

MPRDA

Mineral and Petroleum Resources Development Act

MRA

Mining Right Application

MTO

Mining Titles Office

NOMR

New Order Mining Right

NWA

National Water Act 36 of 1998

Option Plan

Sylvania Platinum Limited Share Option Plan

PGM

Platinum group metals comprising mainly platinum, palladium, rhodium and gold

PAR

Pan African Resources Plc

Phoenix

Phoenix Platinum Mining Proprietary Limited, renamed Sylvania Lesedi

Pipeline ounces

6E ounces delivered but not invoiced

Pipeline revenue

Revenue recognised for ounces delivered, but not yet invoiced based on contractual timelines

Pipeline sales adjustment

Adjustments to pipeline revenues based on the basket price for the period between delivery and invoicing

Programme

Sylvania Platinum Share Buyback Programme

Project Echo

Secondary PGM Milling and Flotation (MF2) program announced in FY2017 to design and install additional new additional fine grinding mills and flotation circuits at Millsell, Doornbosch, Tweefontein and Mooinooi.

Revenue (by products)

Revenue earned on Ruthenium, Iridium, Nickel and Copper

RoM

Run of mine

SDO

Sylvania dump operations

Shares

Common shares

Sylvania

Sylvania Platinum Limited, a company incorporated in Bermuda

USD

United States Dollar

WIP

Work in progress

WULA

Water Use Licence Application

UK

United Kingdom of Great Britain and Northern Ireland

ZAR

South African Rand

 


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
QRFWGGWWUUPRUQG
UK 100