Volspruit Project Update, South Africa

RNS Number : 1697P
Sylvania Platinum Limited
29 September 2011
 



Sylvania Platinum Limited

 

(ASX: SLP, AIM: SLP)

 

VOLSPRUIT PROJECT UPDATE, SOUTH AFRICA

 

 

The directors of Sylvania Platinum Limited ("Sylvania Platinum" or the "Company"), the low cost producer of Platinum Group Metals, are pleased to announce that the Company has submitted the Mining Right Application ("Application") for the Volspruit Project ("the Project") located in the Northern limb of the Bushveld Igneous Complex to the Department of Mineral Resources ("DMR").

 

Project Highlights

 

·      The Project has the following two main components:

 

Volspruit Mine Project to be developed by Sylvania Platinum consisting of mine and 
concentrator; and

Volspruit Smelter / Refinery Project currently planned to be developed in a 50:50 joint venture.

 

·      The Application was submitted simultaneously with the transfer of the prospecting rights from Pan 
Palladium South Africa (Pty) Limited ("Pan Palladium"), a wholly-owned subsidiary of the Company, to the newly formed, Volspruit Mining Company (Pty) Limited ("Volspruit"), a subsidiary of Pan Palladium. 

 

Volspruit provides for a 26% Black Economic Empowerment shareholding partner in accordance 
with South African legislation.

 

·      The Company structure submitted with the Application is in line with advice received from taxation consultants regarding the best company structure for the Project.

 

·      A decision by the DMR on the Application is expected during 2012.

 

The commencement of the Application began in July 2011 with the uploading of the Mine Works Programme, the Social Labour Plan and Company Structure documents into the DMR submissions database. The uploading of all required documents has now been concluded and the Application accepted by the DMR.

 

The Environmental Scoping Document is required to be submitted within 30 days of the submission of the Application and is a key milestone in the Environmental Impact Assessment process. At the first public meeting for the Interested and Affected Parties, a part of the Environmental Impact Assessment process, a request was made to extend the time for comment by fourteen days which was agreed to by the Company. As such, the Final Environmental Scoping Document will be submitted by the middle of October 2011.

 

The ability to proceed with the Project now depends on the granting of the Mining Right as well as the approval of the Environmental Management Plan. A decision on both these submissions is due during 2012. An independent expert review of the project has been conducted by Venmyn Rand (Pty) Limited and the project has been found to be economically viable.

 

Commenting today Terry McConnachie, CEO of Sylvania Platinum, said: "The submission of the Mining Right Application is another key milestone in the advancement of the Volspruit Project."

 

 Ends

 

For further information please contact: 

 

South Africa
Terence McConnachie (CEO)

 Sylvania Platinum Limited
+27 (11) 673 1171

 

Louis Carroll (FD/Joint Company Secretary)
Sylvania Platinum Limited
+44 (0) 7969 170 622

 

Australia

Richard Rossiter (Chairman)
Sylvania Platinum Limited

+61 (4) 1868 8338

 

Grant Button (Director/Joint Company Secretary)

Sylvania Platinum Limited
+61 (8) 9226 4777

 

United Kingdom
Martin Eales

RBC Europe Limited

+44 (0) 20 7653 4000

 

Anthony Rowland/ Ben Wright
Ambrian Partners Limited
+44 (0) 20 7634 4700

 

 

Laurence Read/Beth Harris

Threadneedle Communications

+44 (0) 20 7653 9855

 

 

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEKLBLFKFEBBF
UK 100