4th Quarter and full year production report FY2019

RNS Number : 1889P
Tharisa PLC
09 October 2019
 

Tharisa plc

(Incorporated in the Republic of Cyprus with limited liability)

(Registration number HE223412)

JSE share code: THA

LSE share code: THS

A2X share code: THA

ISIN: CY0103562118

('Tharisa' or the 'Company')

Fourth quarter and full year production report for the year ended 30 September 2019

Strong quarterly performance demonstrates ability to deliver on Vision 2020

 

Salient features for the quarter ended 30 September 2019

‒     Quarterly operational improvement with reef tonnes mined up 8.0% to 1 248.2 kt and tonnes milled up 6.9% to 1 291.2 kt

‒     Platinum Group Metals ('PGMs') recovery was 84.7% with production up 11.4% to 38.0 koz (Q3 2019: 34.1 koz)

‒     Chrome recovery at 61.0% (Q3 FY 2019: 65.5%) with production up 2.4% to 341.9 kt (Q3 334.0 kt)

‒     Third party chrome concentrate production at 69.4 kt, up 17.4% from Q3 2019

‒     Stripping ratio quarter on quarter has increased by 24.1% to 10.3 m3:m3 (Q3 2019: 8.3 m3:m3)

‒     Continued investment in fleet capacity and upgrades with second Caterpillar 6050 to be commissioned in Q1 of financial year 2020

Salient features for the year ended 30 September 2019

‒     Reef tonnes mined and milled at 4 627.1 kt and 4 836.0 kt respectively

‒     PGMs recovery at 82.1% with production of 139.7 koz

‒     Chrome recovery at 62.0% with chrome production at 1 290.0 kt

‒     Third party chrome concentrate production of 241.1 kt

‒     PGM price of US$1 081/oz, an increase of 17.1% from 2018

‒     Chrome price received down 12.9% to US$162/t 

‒     Pit layout substantially complete with pit design optimisation now underway

Commenting on the production results, Tharisa CEO Phoevos Pouroulis, said:

 

"In the year under review Tharisa significantly reset its mining operations, with a revised pit layout, an improvement in waste stripping, and the debottlenecking of the production plants.  Though this translated into lower production than last year's record performance, the significant work done provides Tharisa with a clear path to delivering on our Vision 2020 strategy. The key remaining investment to achieve our production goal, the Vulcan plant, is under construction and remains firmly on track for commissioning in calendar Q4 2020. We have focussed our energy in the right places and have invested in both our workforce and machinery, which will ensure we have the right tools to achieve our targets. Extremely pleasing is our Zimbabwean development pipeline, especially with Karo Platinum completing phase one of the exploration programme with positive results apparent at this early stage."

 

Safety

Safety is one of Tharisa's core values and the Company continues to strive for zero harm at its operations. An LTIFR of 0.27 per 200 000 man hours worked was recorded at the end of the quarter.

Production update

The production update for the quarter and year ended 30 September 2019 is as follows:



Quarter ended 30 Sep 2019 

Quarter ended 30 Jun 2019 

Quarter on quarter movement

%

Quarter ended 30 Sep 2018 

Year ended 30 Sep 2019 

Year ended 30 Sep 2018 

Reef mined

kt

1 248.2

1 155.4

8.0 

1 179.7

4 627.1

4 875.0

Stripping ratio

m3: m3

10.3

8.3

24.1 

7.2

8.3

7.9

Reef milled

kt

1 291.2

1 207.3

6.9 

1 216.7

4 836.0*

5 105.3

PGM flotation feed

kt

965.2

889.1

8.6 

892.8

3 605.9

3 718.1

PGM rougher feed grade

g/t

1.44

1.45

(0.7)

1.48

1.47

1.51

PGM recovery

%

84.7

82.1

3.2 

84.1

82.1

84.1

6E PGMs produced

koz

38.0

34.1

11.4 

35.7

139.7

152.2

Average PGM contained metal basket price

US$/oz

1 211

1 064

13.8 

928

1 081

923

Average PGM contained metal basket price

ZAR/oz

17 792

15 297

16.3 

13 067

15 531

12 038

Cr2O3 ROM grade

%

18.3

17.8

2.8 

18.3

18.1

18.2

Chrome recovery

%

61.0

65.5

(6.9)

64.5

62.0

66.0

Chrome yield

%

26.5

27.7

(4.3)

27.9

26.7

28.4

Chrome concentrates produced (excluding third party)

kt

341.9

334.0

2.4 

339.2

1 290.0

1 448.0

Metallurgical grade

kt

252.4

259.4

(2.7)

240.3

977.9

1 080.3

Specialty grades

kt

89.5

74.6

20.0 

98.9

312.1

367.7

Third party chrome production

kt

69.4

59.1

17.4 

56.0

241.1

221.8

Metallurgical grade chrome concentrate contract price

US$/t CIF China

148

174

(14.9)

164

162

186

Metallurgical grade chrome concentrate contract price

ZAR/t CIF China

2 203

2 525

(12.8)

2 313

2 525

2 415

Average exchange rate

ZAR:US$

14.7

14.4

2.1 

14.1

14.4

13.1

*    includes the processing of 99.0 kt of commissioning tails through the processing plants for the year ended 30 September 2019

 

Mining

Reef tonnes mined continued the trend of steady improvement at the Tharisa Mine with an increase of 8.0% as compared to the previous quarter, to 1 248.2 kt (Q3 2019: 1 155.4 kt), bringing total tonnes mined for the 2019 year to 4 627.1 kt, slightly down from the previous year's 4 875.0 kt. Reef tonnes milled saw an improvement of 6.9% for the quarter to 1 291.2 kt (Q3 2019: 1 207.3 kt) resulting in total reef milled of 4 836.0 kt (2018: 5 105.3 kt) for the year under review.

The revised pit layout has been largely completed and the previously mined in-pit material has been removed. The stripping ratio quarter on quarter has increased by 24.1% to 10.3 m3:m3 (Q3 2019: 8.3 m3:m3) resulting in an annualised stripping ratio of 8.3 m3:m3.

A second Caterpillar 6050 face shovel is scheduled to be operational before the end of December 2019, with various other capital items ordered or delivered, resulting in further improvements in the overall fleet age profile, capacity and efficiency.

Processing

PGM production increased by 11.4% to 38.0 koz (6E basis) (Q3 2019: 34.1 koz) compared to the previous quarter with recoveries increasing by 3.2% to 84.7% (Q3 2019: 82.1%). Annualised PGM recoveries were steady at 82.1% (2018: 84.1%). PGM grade for the quarter was maintained at 1.44 g/t (Q3 2019: 1.45 g/t) resulting in a rougher feed grade of 1.47 g/t for the year.

Chrome concentrate production quarter on quarter increased by 2.4% to 341.9 kt (Q3 2019: 334.0 kt) delivering overall production of 1 290.0 kt (2018: 1 448.0 kt) for the year. Chrome recoveries were down quarter on quarter at 61.0% (Q3 2019: 65.5%) with recoveries for the year at 62.0% (2018: 66.0%) as a result of instability in the average feed grade into the plant which is being rectified as the mine increases its run of mine stockpile ahead of the crushing circuit. Quarterly grade improved by 2.8% from 17.8% to 18.3%, giving an annualised CR203 ROM grade of 18.1% compared to 18.2% in the previous year. Of the total chrome concentrate produced for the quarter 252.2 kt was metallurgical grade, while specialty grade production increased by 20.0% to 89.5 kt.

The chrome production for the quarter from the K3 chrome plant was 69.3 kt (Q3 2019: 59.1 kt) with total K3 production for the year being 241.1 kt (2018: 221.8 kt).

Market update

The average PGM contained metal basket price for the quarter was US$1 211/oz (ZAR17 792/oz), an increase of 13.8% in US$ terms and 16.3% in ZAR terms, while year on year average PGM prices received were up by 17.1% to US$ 1 081/oz (2018: US$ 923/oz) and 29.0% up to ZAR 15 531/oz (2018: ZAR 12 038 /oz).

The average chrome price received for the quarter was down 14.9% at US$148/t (Q3 2019: US$174/t) with an annualised 12.9% decrease in price received to US$162/t (2018: US$186/t). Disappointingly, spot prices have thus far failed to rise above US$160/t.

Outlook

Construction on the Vulcan Plant has commenced, with civil works due to be completed before Christmas. Orders for long lead items have been placed and the construction schedule is on track for cold commissioning in calendar year 2020.

 

Tharisa is on track to achieve its Vision 2020 targets of 2 Mt chrome concentrate and 200 koz of PGMs on an annualised basis by the end of calendar year 2020.

Tharisa's FY2020 production guidance is 155 koz to 165 koz PGMs (6E basis) and 1.45 Mt to 1.55 Mt of chrome concentrates.

The above information has not been reported on or reviewed by Tharisa's auditors.

 

Paphos, Cyprus

09 October 2019

JSE Sponsor

Investec Bank Limited

Investor relations contacts:

Ilja Graulich (Head of Investor Relations and Communications)

+27 11 996 3500

+27 83 604 0820

igraulich@tharisa.com

Daniel Thöle (Investor Relations and Communications)

+27 11 996 3500

 

Financial PR contacts:

Bobby Morse / Augustine Chipungu

+44 020 7466 5000

tharisa@buchanan.uk.com 

Broker contacts:

Peel Hunt LLP (UK Joint Broker)

Ross Allister / James Bavister / David McKeown

+44 207 7418 8900

BMO Capital Markets Limited (UK Joint Broker)

Jeffrey Couch / Thomas Rider

+44 020 7236 1010

Berenberg (UK Joint Broker)

Matthew Armitt / Detlir Elezi

+44 20 3207 7800

Nedbank Limited (acting through its Corporate and Investment Banking division) (RSA Broker)

Shabbir Norath

+27 11 295 6575

 


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLUWOSRKAARRAA

Companies

Tharisa (DI) (THS)
UK 100

Latest directors dealings