Tharisa Q4 FY2023 Production Report

Tharisa PLC
17 October 2023
 

Tharisa plc

(Incorporated in the Republic of Cyprus with limited liability)

(Registration number HE223412)

JSE share code: THA

LSE share code: THS

A2X share code: THA

ISIN: CY0103562118

LEI: 213800WW4YWMVVZIJM90

('Tharisa' or the 'Company')

 

PRODUCTION REPORT FOR THE FOURTH QUARTER AND YEAR ENDED 30 SEPTEMBER 2023

Tharisa, the platinum group metals (PGMs) and chrome co-producer dual-listed on the Johannesburg and London stock exchanges, announces its production results for Q4 and financial year ended FY2023[1] and cash balance as at the year end.

Quarter highlights

‒      Lost Time Injury Frequency Rate ('LTIFR') of 0.11 per 200 000-man hours worked

‒      Annual output

‒      Chrome production for the year at 1 580.1 kt (FY2022: 1 582.7 kt) with Q4 at 413.4 kt (Q3 FY2023 378.8 kt)

‒      PGM production for the year at 144.7 koz (FY2022: 179.2) with Q4 at 30.7 koz (Q3 FY2023: 37.0 koz)

‒      Strong increase in reef mining volumes quarter on quarter, up 27.5% to 1 158.9 kt (Q3 FY2023: 908.8 kt)

‒      Average annual metallurgical grade chrome concentrate prices up 26.2% at US$263/t (FY2022: US$209/t)

‒      Significant quarter-on-quarter PGM price decrease of 21.5% to US$ 1 331/oz (Q3 FY2023: US$ 1 695/oz) (6E basis) accelerated the annual price retreat of 26.1% with average prices received at US$1 893/oz (FY2022: US$2 564/oz)

‒      The continued weakening of PGM prices and macro economics has resulted in a prudent and strategic decision to extend the Karo Platinum Project timeline for commissioning by 12 months to June 2025, with the opportunity to accelerate the timeline as markets become more favourable

‒      The Karo Platinum Project has progressed well, and the revised timeline is aligned to funding availability and provides flexibility

‒      Group cash on hand increased to US$268.8 million (30 June 2023: US$242.6 million), and debt of US$142.2 million (30 June 2023: US$101.1 million), resulting in a net cash position of US$126.6 million (30 June 2023: US$141.5 million)

‒      Production guidance for FY2024 is set between 145 koz and 155 koz PGMs (6E basis) and 1.7 Mt to 1.8 Mt of chrome concentrates


Key Operating Numbers



Quarter ended 30 Sep 2023 

Quarter ended 30 Jun 2023 

Quarter on quarter movement % 

Quarter ended 30 Sep 2022 

Year      ended   30 Sep     2023 

Year      ended   30 Sep     2022 

Year on year movement % 

Reef mined

kt

1 158.9

908.8

27.5 

1 314.7

4 177.3

5 505.4

(24.1)

Reef milled

kt

1 310.2

1 302.2

0.6 

1 446.8

5 409.8

5 608.2

(3.5)

PGMs produced (6E)

koz

30.7

37.0

(17.0)

45.3

144.7

179.2

(19.3)

Chrome concentrates produced (excluding third party)

kt

413.4

378.8

9.1 

416.2

1 580.1

1 582.7

(0.2)

Average PGM basket price

US$/oz

1 331

1 695

(21.5)

2 400

1 893

2 564

(26.2)

Average metallurgical grade chrome concentrate contract price - 42% basis

US$/t

291

292

(0.3)

226

263

209

25.8 

 

Phoevos Pouroulis, CEO of Tharisa, commented:

"The divergence in commodity prices could not have been more visible than the past quarter which saw us touching 52-week highs in the chrome market based on solid fundamentals, but these fundamentals were distinctly lacking in the PGM market, which saw prices drop more rapidly and lower than the market anticipated, resulting in broad based challenges for the PGM market on the supply side.

While current markets are volatile and unpredictable, we believe in the medium term outlook for PGMs underpinned by a supply side constrained economy, this supported by a robust chrome market driven by stable demand.

At Tharisa, our co-product model showed its resilience once again, supported by a strong recovery in chrome production in the second half of the year and benefiting from a 26% increase in price. The earlier operational mining challenges and resulting ore mix from our own ore and purchased ore did have a negative impact on PGM recovery and thus production, however, this was supported by a strong focus and recovery in chrome in the second half of the year. The waste contractor is now firmly in place, and we see a recovery in waste mining volumes for FY2024, however, we remain cautious on our production outlook as evidenced by our guidance for the coming year.

Our margins remain strong due to our mechanised low cost operations, with a continued disciplined capital allocation strategy, ensuring investment in our existing businesses, providing sustainable growth and return to shareholders.

Given the current PGM basket price weakness and uncertain global economic outlook, we have taken the measured decision to extend the Karo Platinum timeline out to commissioning by June 2025, with the opportunity to accelerate the timeline as markets become more favourable. The Karo Platinum Project has progressed well, and the revised timeline is aligned to funding availability and provides flexibility to navigate volatile market conditions.

Our growth strategy remains firmly intact, with continuous optimisation at the Tharisa Mine, investment in downstream beneficiation, and our commitment to the development of the multi-generational Tier 1 Karo Platinum Project."


Health & Safety

‒      The health and safety of our stakeholders remains a core value to the Group and Tharisa continues to strive for zero harm at its operations

‒      LTIFR of 0.11 per 200 000-man hours worked

Market Update

‒      The chrome market continues to support sustainable pricing which is driven by supply-demand fundamentals. Reduced port inventory in China highlights the tight market balance underpinned by the growth in Chinese domestic ferrochrome and stainless steel industries. Supply chain complexities are exacerbated by constrained rail and port logistics in South Africa together with the effect of erratic electricity supply from Eskom 

‒      PGM market remains under continued pricing pressure with uncertainty of the macro global economic outlook having a direct effect on the demand for the precious metals. This is overlain by further indecisiveness on the future of the internal combustion engine (ICE). During the latter half of Q4 FY2023 with the steep decline in PGM prices, analysts have cautioned that higher cost producers within the PGM industry are not profitable at these commodity prices. The 'higher for longer' concerns of the global interest rate market have impacted prices for now and we see muted upside in the short term for PGM prices. In the medium to longer term demand drivers including the hydrogen economy, possible supply cuts at unprofitable PGM producers, project delays and capital discipline versus demand for the ICE, will require a recovery in PGM prices to ensure demand is met by supply

Operational Update

‒      Improved quarterly reef mined of 1 158.9 kt (Q3 FY2023: 908.8 kt)

‒      Annual reef mined down 24.1% to 4 177.3 kt (FY2022: 5 505.4 kt) due to inclement weather and constrained pit flexibility

‒      Total annual reef tonnes milled flat at 5 409.8 kt (FY2022:  5 608.2 kt) as strategic ROM ore purchases supplemented own mine production with Q4 FY2023 milling at 1 310.2 kt (Q3 FY2023: 1 302.2 kt)

‒      Annual chrome production at 1 580.1kt (FY2022: 1 582.7 kt)

‒      Grade of 17.9% Cr2O3 (FY2022: 17.4%)

‒      Recovery at 67.6% (FY2022: 68.3%)

‒      Quarterly chrome production at 413.4 kt (Q3 FY2023: 378.8 kt)

‒      Grade of 18.7% Cr2O3 (Q3 FY2023: 17.8%)

‒      Recovery at 70.0% (Q3 FY2023: 67.9%)

‒      Vulcan contributing to strong chrome recovery

‒      Annual PGM production at 144.7 koz (FY2022: 179.2 koz)

‒      Rougher feed grade of 1.64 g/t (FY2022: 1.70 g/t)

‒      Recovery of 66.5% (FY2022: 76.6%) as a result of ore mix from oxidised material and purchased ROM impacting recoveries

‒      Quarterly PGM production at 30.7 koz (Q3 FY2023: 37.0 koz)

‒      Rougher feed grade of 1.57 g/t (Q3 FY2023: 1.67 g/t)

‒      Recovery of 62.7% (Q3 FY2023: 69.0%)

Karo Platinum Update

‒      One LTI recorded on the project for the year under review

‒      The PGM price environment has necessitated a review of the commissioning timeline of the Karo Platinum Project

‒      First ore in mill (FOIM) now planned for June 2025

‒      Project team has divided major workstreams into smaller commitments to ensure continued development aligned with funding availability

‒      Manufacturing of key long-lead items nearing completion  

‒      Revised workstreams designed to accelerate the project implementation should the PGM market become more favourable

‒      Pilot mining is continuing as planned to optimise mining design

‒      Additional current resource to reserve conversion underway

 

Cash Balance and Debt Position

Tharisa had a cash balance of US$268.8 million (30 June 2023: US$242.6 million) at the end of the quarter, and debt of US$142.2 million (30 June 2023: US$101.1 million), resulting in a net cash position of US$126.6 million (30 June 2023: US$141.5 million).

 

Guidance

Production guidance for FY2024 is set between 145 koz and 155 koz PGMs (6E basis) and 1.7 Mt to 1.8 Mt of chrome concentrates.

 

Any forward looking statements have not been reported on or reviewed by Tharisa's auditors.

 

Production Numbers



Quarter ended 30 Sep 2023 

Quarter ended 30 Jun 2023 

Quarter on quarter movement % 

Quarter ended 30 Sep 2022 

Year      ended   30 Sep     2023 

Year      ended   30 Sep     2022 

Year on year movement % 

Reef mined

kt

1 158.9

908.8

27.5 

1 314.7

4 177.3

5 505.4

(24.1)

Stripping ratio

m3: m3

14.0

14.2

(1.4)

13.3

12.8

12.8

Reef milled

kt

1 310.2

1 302.2

0.6 

1 446.8

5 409.8

5 608.2

(3.5)

PGM flotation feed

kt

970.6

996.5

(2.6)

1 108.1

4 122.0

4 274.5

(3.6)

PGM rougher feed grade

g/t

1.57

1.67

(6.0)

1.67

1.64

1.70

(3.5)

PGM recovery

%

62.7

69.0

(9.1)

76.2

66.5

76.6

(13.2)

6E PGMs produced

koz

30.7

37.0

(17.0)

45.3

144.7

179.2

(19.3)

Platinum produced

koz

17.3

20.9

(17.2)

25.0

80.3

99.0

(18.9)

Palladium produced

koz

5.2

6.6

(21.2)

7.9

24.8

30.0

(17.3)

Rhodium produced

koz

3.0

3.4

(11.8)

4.4

13.5

17.2

(21.5)

Average PGM contained metal basket price

US$/oz

1 331

1 695

(21.5)

2 400

1 893

2 564

(26.2)

Platinum price

US$/oz

940

1 034

(9.1)

887

981

968

1.3 

Palladium price

US$/oz

1 227

1 441

(14.9)

2 077

1 594

2 107

(24.3)

Rhodium price

US$/oz

3 841

6 959

(44.8)

13 746

8 992

14 962

(39.9)

Average PGM contained metal basket price

ZAR/oz

24 842

31 544

(21.2)

40 850

34 107

40 437

(15.7)

Cr2O3 ROM grade

%

18.7

17.8

5.1 

17.3

17.9

17.4

2.9 

Chrome recovery

%

70.0

67.9

3.1 

69.6

67.6

68.3

(1.0)

Chrome yield

%

31.6

29.1

8.6 

28.8

29.2

28.2

3.5 

Chrome concentrates produced (excluding third party)

kt

413.4

378.8

9.1 

416.2

1 580.1

1 582.7

(0.2)

Metallurgical grade

kt

338.4

306.0

10.6 

325.9

1 356.9

1 233.2

10.0 

Specialty grades

kt

75.0

72.8

3.0 

90.3

223.2

349.5

(36.1)

Third party chrome production

kt

58.9

56.2

4.8 

38.2

201.9

188.2

7.3 

Average metallurgical grade chrome concentrate contract price - 42% basis

US$/t

291

292

(0.3)

226

263

209

25.8 

Metallurgical grade chrome concentrate contract price

ZAR/t CIF China

5 273

5 519

(4.5)

3 867

4 840

3 345

44.7 

Average exchange rate

ZAR:US$

18.7

18.7

17.0

18.2

15.8

15.2 

 

 

Paphos, Cyprus

 

17 October 2023

 

JSE Sponsor

Investec Bank Limited

Connect with us on LinkedIn to get further news and updates about our business.

 

Investor Relations Contacts:

Ilja Graulich (Head of Investor Relations and Communications)

+27 11 996 3500

+27 83 604 0820

igraulich@tharisa.com

 

 

 

Broker Contacts:

Peel Hunt LLP (UK Joint Broker)

Ross Allister / Georgia Langoulant

+44 207 7418 8900

 

BMO Capital Markets Limited (UK Joint Broker)

Thomas Rider / Nick Macann

+44 207 236 1010

 

Berenberg (UK Joint Broker)

Matthew Armitt / Jennifer Lee / Detlir Elezi

+44 203 207 7800

 

About Tharisa

Tharisa is an integrated resource group critical to the energy transition and decarbonisation of economies. It incorporates exploration, mining, processing and the beneficiation, marketing, sales, and logistics of PGMs and chrome concentrates, using innovation and technology as enablers. Its principal operating asset is the Tharisa Mine, located in the south-western limb of the Bushveld Complex, South Africa. The mechanised mine has an 18 year pit life and can extend operations underground by at least 40 years. Tharisa also owns Karo Platinum, a low-cost, open-pit PGM asset under construction and located on the Great Dyke in Zimbabwe. The Company is committed to reducing its carbon emissions by 30% by 2030 and the development of a roadmap is continuing to be net carbon neutral by 2050. Tharisa plc is listed on the Johannesburg Stock Exchange (JSE: THA) and the Main Board of the London Stock Exchange (LSE: THS).

 



[1] Tharisa's financial year is from 01 October to 30 September

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 

Companies

Tharisa (DI) (THS)
UK 100

Latest directors dealings