Thor Mining PLC
04 April 2006
THOR MINING PLC
Feasibility Study on Molyhil Project
Dated: 4 April 2006
Thor Mining PLC ('Thor') the mineral exploration and development company
focussed on advancing tungsten and molybdenum projects in the Northern Territory
of Australia today announces the commencement of a definitive feasibility study
on the Molyhil Tungsten and Molybdenum Project (the 'Molyhil Project') following
the completion of a positive Scoping Study..
Highlights
• Scoping study on Molyhil Project completed on schedule which confirmed
an indicative positive pre tax cash inflow of A$140m over initial
4 years.;
• Scoping study was based on an initial 4 year open pit mining operation
with an estimated A$20 million capital cost.;
• Definitive feasibility study targeted for completion in the December
quarter; and
• New program of in fill and resource extension drilling to commence at
Molyhil in April/May 2006;
Scoping study results
The scoping study assisted in identifying the priorities for the definitive
feasibility study and the highlights of the outcomes for the Molyhil Project
included the following:
• 300,000 tonne per annum open pit mining operation for the initial 4 years
production;
• forecasted cash operating cost of A $80 per tonne; and
• estimated capital cost of A $20M.
These outcomes were based on assumptions including:
• Current concentrate commodity prices which are:
Tungsten Ore Min 65% WO3 USD: $240 mtu
Molybdenum roasted concentrates (oxide) MoS2 57% USD: $24 per lb
• Exchange rate US$ 0.75: A$1.00.
Based on the above and other outcomes and assumptions the scoping study
indicates that the Molyhil Project could have a positive pre tax operational
cash flow of up to A$140m over a 4 year mine life.
Definitive feasibility study
As a result of the completion of the scoping study, the Directors of Thor have
decided to proceed immediately with a definitive feasibility study which is
targeted for completion in the December quarter of 2006.
This study will be completed by Merit Engineers Pty Ltd, utilising the same
principal consultants that have been used for the completed Scoping Study.
Several aspects are already underway.
As part of this study, additional drilling will be undertaken during the second
quarter 2006. The objectives of this drilling include:
- selected deep drilling to test below proposed open pit;
- geotechnical holes, for the proposed tailings dam and open pit;
- bore-field set up; and
- Thring Creek anomaly.
The definitive feasibility study is being undertaken to complete further studies
and drilling and do a sensitivity analysis to verify all of the outcomes and
assumptions identified during the scoping study. Until the definitive
feasibility study has been completed Thor cannot make any representation or
warranty (express or implied) as to the accuracy, reliability, reasonableness or
completeness of the scoping study outcomes and assumptions.
Scoping study details
Following completion of the upgraded Molyhil Project JORC resource estimate, as
announced in January 2006, Thor engaged Merit Engineers Pty Ltd to define
capital and operating costs for the Molyhil Project, initially up to scoping
study level.
Thor also engaged Australian Mining Consultants ('AMC') to prepare the open pit
design and mine planning for the proposed project development.
Metallurgical test work is ongoing at Independent Metallurgical Laboratories ('
IML') supervised by Merit, together with Thor's non-executive director, Mr Greg
Durack, who is a metallurgist by profession.
A schedule setting out the terms of reference for both the scoping study and the
definitive Feasibility study on the Molyhil Project is available.
Resources
In January 2006, independent geological consultant, Continental Resource
Management Pty Ltd ('CRM'), completed an updated estimation of the resources at
the Molyhil Project in accordance with 2004 JORC guidelines.
This resource was used as the foundation of the scoping study.
The Molyhil Project deposit remains open at depth and has been interpreted from
geophysical data to extend to 400-500 metres vertical depth or at least 250
metres below the current resource boundary. There is, therefore, considered to
be significant potential to further increase the Molyhil resource with deeper
drilling.
Mining
The nature and the physical characteristics of the Molyhil resource allow mining
by straightforward open pit methods using conventional equipment and mining
techniques. The scoping study recommends that mining contractors be used for
this phase of production.
AMC has completed a proposed mine plan for the project.
Metallurgy
During 2005 a bulk sample of material from Molyhil was shipped to Perth and
processed using a pilot-scale plant at Nagrom. This test work program achieved
excellent recoveries of up to 51% WO3 and 78% MoS2.
A new test work program commenced in early 2006 designed to simplify the
proposed process flow sheet.
Metallurgical test work using material extracted from Molyhil has now been
ongoing for two months. This test work program is expected to be the longest
lead time item in the compilation of the definitive feasibility study.
Infrastructure
There is currently minimal infrastructure at the Molyhil Project site and the
Scoping Study has assumed that the following key infrastructure items will need
to be constructed:
- Camp and communications;
- Water supply;
- Upgrade of a nearby airfield; and
- Upgrade of access roads.
Principal consultants
The Scoping Study has been completed with the assistance of the following
principal consultants:
- Merit Engineers Pty Ltd;
- Continental Resource Management;
- Australian Mining Consultants; and
- Independent Metallurgical Laboratories.
CRM consents to the inclusion of the information relating to the mineral
resources in this announcement in the form and context in which it appears.
This press release includes certain statements, estimates and projections with
respect to the anticipated future performance of the Molyhil Project. Those
statements, estimates or projections are based on assumptions about future
events and management actions that may not necessarily take place and are
subject to significant uncertainties, many of which are outside the control of
Thor. Those assumptions may, or may not, prove correct. No representation is
made as to the accuracy of those statements, estimates or projections.
Enquiries:
John W Barr +61 418 912 885 Thor Mining PLC Executive Chairman
John Simpson 020 7512 0191 ARM Corporate Finance Ltd Nominated Adviser
Abigail Singleton 020 7429 6666 Conduit PR Public Relations
Updates on the Company's activities are regularly posted on Thor's website
www.thormining.com, which includes a facility to register to receive these
updates by email.
This information is provided by RNS
The company news service from the London Stock Exchange
*A Private Investor is a recipient of the information who meets all of the conditions set out below, the recipient:
Obtains access to the information in a personal capacity;
Is not required to be regulated or supervised by a body concerned with the regulation or supervision of investment or financial services;
Is not currently registered or qualified as a professional securities trader or investment adviser with any national or state exchange, regulatory authority, professional association or recognised professional body;
Does not currently act in any capacity as an investment adviser, whether or not they have at some time been qualified to do so;
Uses the information solely in relation to the management of their personal funds and not as a trader to the public or for the investment of corporate funds;
Does not distribute, republish or otherwise provide any information or derived works to any third party in any manner or use or process information or derived works for any commercial purposes.
Please note, this site uses cookies. Some of the cookies are essential for parts of the site to operate and have already been set. You may delete and block all cookies from this site, but if you do, parts of the site may not work. To find out more about the cookies used on Investegate and how you can manage them, see our Privacy and Cookie Policy
To continue using Investegate, please confirm that you are a private investor as well as agreeing to our Privacy and Cookie Policy & Terms.