The Directors of Thor Mining PLC ("Thor" or the "Company") (AIM, ASX: THR) the Australian gold, tungsten and molybdenum explorer and developer, today lodged the following December 2012 quarterly report with the Australian Securities Exchange (ASX) as required by the listing rules of ASX.

 

QUARTERLY REPORT OCTOBER TO DECEMBER 2012

 

Highlights

Outlook for March 2013 Quarter

 

TUNGSTEN & MOLYBDENUM

Molyhil NT

·      Regulatory approvals activities

·      Ongoing marketing & financing activities.

·      DFS enhancement studies.

·      Preliminary X-ray Fluorescence (XRF) geochemical reconnaissance identifies new anomalies.

 

 

 

 

·      Ongoing marketing & financing activities.

·      Ongoing enhancement program.

·      Exploration - review and test nearby prospects.

 

 

GOLD

Spring Hill NT

·      Resource increase to 450,000oz above 150m depth.

·      Additional mineralisation intersected by drilling 150 to 250 metres.

 

 

 

 

·      Continued evaluation of potential for profitable production.

·      Annual wet season interruption to field activities.

 

GOLD & NICKEL

Dundas WA

·      Geochemical assessment of surface samples for nickel potential.

·      Potential for nickel prospectivity recognised in a small part of the tenement.

 

 

·      Further on site geochemical sampling for nickel potential.

·      Preparation for follow up air core and RC drilling.

 

MOLYHIL TUNGSTEN-MOLYBDENUM PROJECT (NT) (100% THOR)

 

December quarter activities were devoted to negotiations to secure agreements for off-take and project finance, as well as pursuing a number of optimisation opportunities

Discussions with potential customers for project concentrates are ongoing.  While it is difficult to forecast the terms and timing of any agreement, Directors remain confident that a positive outcome will be achieved to allow development at Molyhil to commence.

CONCENTRATE QUALITY

A number of potential customers have identified relatively high molybdenum levels in the scheelite concentrate, which while acceptable in some markets, is an issue for others.  Subsequent testwork has successfully demonstrated a reduction in the molybdenum level in the scheelite concentrate to less that 0.5% Mo, resulting in a much more marketable product.

Pit slope

Ongoing work on our mining plan parameters has resulted in recognition that a steepening of the pit slope angle, and the consequent improved waste to ore ratio, has the potential to increase substantially the material considered economic to extract from the mine.  In consequence Thor is planning 3 additional diamond drill holes, placed to assess steeper slope potential.  While the impact of this work on any slope changes cannot be anticipated, and the subsequent effect on ore reserve calculations will depend also upon updated commercial factors, previous internally modelled outcomes of steepening the pit slope from the existing 48.3 suggest a substantial positive impact on both the mine life and the project economic returns.

 

METAL PRICES

The selling price in Europe of Tungsten APT now sits at US$330/mtu, while the price of Molybdenum Roasted Concentrates remains steady at just over US$11.00/lb.

 

Tungsten Exploration program

 

Initial stages of exploration on the Molyhil project tenements continued during the quarter. Field inspection and XRF geochemical surveys commenced over several of the Initial targets identified from hyperspectral and aeromagnetic data sets (figure 3). While the primary objective of the field work was to locate new economic mineralisation, the secondary objective is to evaluate targeting and exploration techniques.

 

Presentation of XRF results has been deferred until further assessment is completed to ensure some initial tungsten and molybdenum values have not been influenced by contamination from historic mining operations.

 

Initial field results indicate the airborne hyperspectral scanning is an effective targeting tool and that there may be potential to further develop the technique to locate blind deposits by identifying mineral alteration halos associated with economic mineralisation.

 

Further targeting and field assessment work is envisaged prior to implementation of reconnaissance drilling.

 

 

SPRING HILL PROJECT - NT (THOR acquiring earn-in rights to up to 80% equity)

PROJECT EQUITY

Transfer documents have been provided to the Northern Territory Department of Resources to formally process the increase in equity to 51%.  Following Ministerial approval, and the allotment to Western Desert Resources Limited (WDR) of 21,666,667 CDI shares, the transfer will be complete.  Further, Thor has expended in excess of 50% of the additional A$1,500,000 necessary for its equity holding to be increased to 80%.

RESOURCE UPGRADE

Following the receipt of all assays and quality control data, an independent resource update estimate was commissioned from McDonald Speijers. The result of the Spring Hill resource estimate update is an Indicated Resource of 450,000 oz gold within 10.0Mt @ 1.40 grams per tonne (g/t) gold using a 0.5 g/t cutoff grade, to a maximum depth of 150 metres, which is designated as the limit for open pit mining. Table 1 details the resource at 0.5 and 1.0g/t cutoff grades. The entire resource is classified as Indicated.

 

 

Spring Hill Resource Estimate* - Nov 2012

Cutoff

(g/t Au)

Tonnage

(Mt)

Grade

(g/t Au)

Contained Gold
(000 oz) **

0.5

10.0

1.40

450

1.0

4.0

2.32

300

*All classified as Indicated

Table 1:  2012 Spring Hill Resource Estimate McDonald Speijers, November 2012.

Thor Mining PLC holds equity rights to 80% of this resource

 

The updated resource represents a 9.5% increase in contained metal over the previous estimate completed in 2003 (Table2). The 9.5% increase in resource above 150 metres depth is a good result given the primary target of the recent drilling has been beneath 150 metres.


2012 Estimate

(cutoff 1g/t Au)

2003 Estimate

Comment

Total resource (000t)

4,000

3,600

11% increase

Gold grade (g/t)

2.32

2.34


Contained gold (000 oz)¹

300

274

9.5% increase

Vertical Limit of resource

150 metres

150 metres

Mineralisation open at depth

Table 2: 2012 Spring Hill resource estimate relative to the 2003 estimate

 

The following table details the resource grouped by ore type (oxide/transition & unweathered). The 4.6 million tonne oxide resource bodes well for a potential mining operation due to its relative ease of treatment.

 

(cut off grade 0.5 g/t)

Tonnes

(Mt)

Grade

g/t Au

Contained Gold

(K oz)

Zone of Oxidation

4.6

1.28

190

Transition Zone

1.3

1.41

59

Unweathered Zone

4.06

1.54

201

Total

10.0

1.4

450

 

Upcoming exploration work on the project is planned to comprise low cost Reverse Circulation (RC) or percussion drilling of shallow satellite targets.

 

DUNDAS PROJECT - WA (60% THOR)

 

Nickel and copper assays for existing calcrete geochemistry samples were collected for part of E63/1102 at the Dundas project in Western Australia.  Sample analyses were conducted using an Olympus Innovex field portable XRF. Quality control data were collected via the analysis of certified reference standards, blanks and duplicates. The results are within acceptable limits for nickel and copper.

 

Results of the additional analyses indicate three areas of elevated nickel, one area of elevated copper and one area of coincident copper and nickel. Sample spacing is at a broad reconnaissance level and the identified areas will require follow up infill sampling to determine their significance. This work is anticipated to take place early in 2013.

 

 

Prioritising expenditure on Molyhil and Spring Hill has prevented commissioning of drilling the gold targets at Dundas.  Testing these targets will be conditional upon working capital availability

 

CORPORATE AND FINANCE

 

During the quarter, the Company raised additional funds through the issue of 97.5 million ordinary shares, in placements to sophisticated investors in the UK.  These issues raised AUD$1,109,000 before associated costs.

 

The Company is in discussion with various parties to secure necessary funds to carry out the programs suggested in this report.  It is expected that an announcement detailing the results of these discussions will be made shortly. 

 

 

Competent Persons Statement

 

The information in this report that relates to exploration results is based on information compiled by Richard Bradey, who holds a BSc in applied geology and an MSc in natural resource management and who is a Member of The Australasian Institute of Mining and Metallurgy.  Mr Bradey is an employee of Thor Mining PLC.  He has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'.  Richard Bradey consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

 

The information in this report that relates to the Spring Hill Mineral Resource is based on information compiled by Diederik Speijers who is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Speijers is the principal of consulting firm McDonald Speijers.  He has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'.  Diederik Speijers consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

 

 

Enquiries:

 

Mick Billing

+61 (8) 7324 1935

 

Thor Mining PLC

Executive Chairman

Allan Burchard

+61 (8) 7324 1935

 

Thor Mining PLC

CFO/Company Secretary

Gerry Beaney/ David Hignell

+44 (0) 207 383 5100

 

Grant Thornton Corporate Finance

 

Nominated Adviser

Nick Emerson/

Renato Rufus

+44 (0) 1483 413500

Simple Investments

Broker

Alex Walters/

Emma Wigan

+44 (0) 7771 713608

+44 (0) 207 839 9260

Cadogan PR

Financial PR

 

Updates on the Company's activities are regularly posted on Thor's website www.thormining.com, which includes a facility to register to receive these updates by email.


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCNKDDKNBKKKDN

Companies

Thor Energy (THR)
UK 100

Latest directors dealings