Market Abuse Regulation (MAR) Disclosure
Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement
4 May 2020
Union Jack Oil plc
("Union Jack" or the "Company")
West Newton Community Update
Union Jack Oil plc (AIM: UJO), a UK focused onshore hydrocarbon production, development and exploration company, notes that Rathlin Energy (UK) Limited ("Rathlin"), the Operator of PEDL183, communicated the following to local residents as part of its participation in the West Newton Community Liaison Group. Union Jack holds a 16.665% interest in this licence, containing the West Newton A-1 discovery well and the recent successful West Newton A-2 conventional appraisal well.
"We hope you and your families are safe, healthy and managing under the current circumstances.
This update is to let you know that we are moving our programme of works forward, in line with the
latest government and public health guidance on Covid-19. We continue to follow the advice closely.
West Newton A
We secured a permit variation from the Environment Agency on Friday 24 April 2020. This enables us to
recommence our well test using a pumpjack (nodding donkey) and a smaller incinerator unit. Once the
required personnel and equipment are available the testing operations will recommence.
West Newton B
Pre-construction works started during the week commencing 6 April 2020. To date, additional land
drainage has been installed in the affected fields. Two water monitoring boreholes, which are a condition
associated with our West Newton B Environment Agency permit, have also been installed and baseline
sampling will be undertaken.
On 4 May 2020, work commenced on the construction of the West Newton B access track. This activity is
the subject of an archeological watching brief and is expected to take five to six weeks.
Road closures, agreed by East Riding of Yorkshire Council, have been instated for safety reasons on
Pasture Lane. Our traffic management plan for the construction phase of operations is now in effect and
works are restricted to Monday to Saturday between the hours of 07:00 and 18:00.
In due course, site construction works will commence on the West Newton B drilling site. This work will
include a full archeological strip, map and record study, following which, site construction will begin. The
site construction works are anticipated to take between five and six weeks.
Drilling of the West Newton B-1 well will commence following the completion of the access track and site
construction activities and the conductor setting operations.
During the course of these operations, we will keep our community neighbours informed of our activities
through website updates, the West Newton Liaison Committee and other periodic notices. We are, of
course, available to address any questions or concerns."
For further information, please contact:
Union Jack Oil plc +44 (0)78 0154 0358
David Bramhill
SP Angel Corporate Finance LLP +44 (0)20 3470 0470
Nominated Adviser and Broker
Richard Morrison
Richard Hail
Caroline Rowe
Cassiopeia Services Ltd +44 (0)7949 690 338
Public Relations
Stefania Barbaglio