FOR IMMEDIATE RELEASE
19 MAY 2010
BISICHI MINING PLC
INTERIM MANAGEMENT STATEMENT
Bisichi Mining PLC ('Bisichi'), the UK mining company with direct coal mining
operations in South Africa, is pleased to provide the following update about
its operations:
The challenging environment experienced in the second half of 2009 by Black
Wattle Colliery ('Black Wattle'), our direct coal mining operation in South
Africa, has continued into the first half of 2010.
This is principally due to the following reasons:
* The Rand continues to be strong against the US Dollar.
* Coal prices in all of the group markets continue to remain low.
* A late wet season has reduced opencast production
Although this challenging environment will affect profitability in the first
half of 2010, we remain extremely positive about the remainder of the year for
Black Wattle Colliery. As stated in the Annual Report, the Bisichi Management
has taken several steps to address this challenging environment that are
focused on increasing production including:
* Increasing the capacity of the washing plant from 130,000 to 170,000 metric
tonnes per month;
* Expanding the rail siding by installing a third rail line;
* Increasing our own opencast production; and
* Buying-in high quality coal from nearby reserves.
Although the implementation of some of these steps has been delayed by a late
wet season in the first half of 2010, the benefits of this increased production
are expected to come through as planned in the second half of 2010.
Overall production to date for the first four months of the year has averaged
120,000 metric tonnes per month compared to 90,000 metric tonnes in the second
half of 2009, but there has been a reduction in the comparable profitability.
This situation has arisen because the lower cost opencast production has been
impacted adversely by the heavy rain mentioned above and production has been
replaced by higher cost buy-in coal. An average overall monthly production of
160,000 metric tonnes is expected in the second half of 2010 as our own
opencast production increases.
In terms of markets, the physical demand for Black Wattle product remains
strong both domestically and internationally. To date Black Wattle has not been
materially affected by the current rail strike action in South Africa, but an
extended continuation of this strike may impact revenue.
Finally, income from Bisichi's UK properties remains steady, with no
significant change from the second half of 2009.
Mr Andrew Heller, Managing Director of Bisichi said: "With all of Black
Wattle's remaining opencast permissions being granted in February 2010, Black
Wattle is now in a strong position to fully utilise the increased capacity of
its expanded washing plant and rail siding, the benefits of which will be seen
in the second half of 2010."
For further information, please call:
Andrew Heller, Bisichi Mining PLC 020 7415 5030
*A Private Investor is a recipient of the information who meets all of the conditions set out below, the recipient:
Obtains access to the information in a personal capacity;
Is not required to be regulated or supervised by a body concerned with the regulation or supervision of investment or financial services;
Is not currently registered or qualified as a professional securities trader or investment adviser with any national or state exchange, regulatory authority, professional association or recognised professional body;
Does not currently act in any capacity as an investment adviser, whether or not they have at some time been qualified to do so;
Uses the information solely in relation to the management of their personal funds and not as a trader to the public or for the investment of corporate funds;
Does not distribute, republish or otherwise provide any information or derived works to any third party in any manner or use or process information or derived works for any commercial purposes.
Please note, this site uses cookies. Some of the cookies are essential for parts of the site to operate and have already been set. You may delete and block all cookies from this site, but if you do, parts of the site may not work. To find out more about the cookies used on Investegate and how you can manage them, see our Privacy and Cookie Policy
To continue using Investegate, please confirm that you are a private investor as well as agreeing to our Privacy and Cookie Policy & Terms.