Reduces Copper Production
BHP Billiton Limited
8 November 2001
BHP Billiton Limited is issuing this announcement to fulfil disclosure
obligations arising from its secondary listing on the London Stock Exchange.
The text of this release is identical to that issued by BHP Billiton Plc
earlier.
Date: 8 November 2001
Number: 31/01
BHP BILLITON BASE METALS REDUCES COPPER PRODUCTION
BHP Billiton Base Metals today announced its intention to temporarily reduce
copper production by an estimated 170,000 tonnes per annum. The reductions
will occur from the Escondida and Tintaya operations in South America.
The action has been taken in response to the current serious fall in demand
for copper arising from unfavourable global economic conditions.
President of BHP Billiton Base Metals Brad Mills said the announcement
demonstrates Base Metals' commitment to managing its resources for the
long-term benefit of shareholders and other stakeholders.
'Notwithstanding the relative efficiency of our world class portfolio of
copper assets, our decision is a response to the significant decline in market
demand. In the current environment of rapidly rising inventories it makes no
sense to produce copper for which there are no end-users of the metal.
Combined LME/Comex stocks are at 940,000 tonnes and growing.'
Production at the Escondida copper operation in Chile will be reduced,
effective immediately, by 10 per cent, which is equivalent to approximately
80,000 tonnes per annum. At the Tintaya operations in southern Peru, total
sulphide production will be curtailed, effective 8 January 2002,
removing an additional 90,000 tonnes per annum.
At Escondida, the grade of ore fed to the concentrator will be lowered by
selective mining and a lower cut-off grade during the period of production
curtailment. Higher grade ore will be reserved for processing when market
conditions improve.
Mr Mills added: ' The impact of the decision to reduce production will be
reviewed at the end of the fiscal year. If better market conditions exist, we
will resume previous production levels. Alternatively, if market conditions
deteriorate further, we would consider maintaining production cuts, or further
decreasing production.
'The Escondida Phase IV development and construction of the Tintaya oxide
plant will continue as planned. BHP Billiton remains fully committed to
realising the potential of its extensive portfolio of low-cost development
opportunities, most notably, the Escondida Phase IV expansion, sulphide leach
development and the development of the Escondida Norte resource base.
Escondida has the potential to add over 450,000 tonnes per annum of new
production at a cash cost of less than US$0.40/lb.'
Attempts are being made to minimise the impact of the production cutbacks on
employees, communities and other stakeholders during this period.
The cuts in production are not expected to materially impact the financial
results of the BHP Billiton Group.
The BHP Billiton Group holds a 57.5 per cent interest in Escondida. The other
owners are affiliates of Rio Tinto Plc (30 per cent), Mitsubishi Corporation
(6 per cent), Mitsubishi Materials Corporation (2 per cent), Nippon Mining and
Metals Company Limited (2 per cent) and the International Finance Corporation
(2.5 per cent). The BHP Billiton Group holds a 99 per cent interest in Tintaya,
the remaining interest is held by Peruvian shareholders.
Two teleconferences will be held on Friday November 9 :
Conference £1 Melbourne 10.00am Australian Eastern Summer Time
(London 11.00pm)
(New York 6.00pm)
Conference £2 London 10.00am
(South Africa 12.00midday)
(New York 5.00am)
****
Further news and information can be found on our Internet site:
www.bhpbilliton.com
South Africa/United Kingdom Australia
Michael Campbell, Investor & Media Dr. Robert Porter, Investor Relations
Relations
Tel: +27 11 376 3360 Tel: + 61 3 9609 3540
Mobile: +27 82 458 2587 Mobile: +61 419 587 456
email: Michael.J.Campbell@bhpbilliton.com email: Robert.Porter@bhpbilliton.com
Ariane Gentil, Manager Communications Mandy Frostick, Media Relations
Tel: +44 20 7747 3977 Tel: +61 3 9609 4157
Mobile: +44 7881 518 715 Mobile: +61 419 546 245
email: Ariane.Gentil@bhpbilliton.com email: Mandy.J.Frostick@bhpbilliton.com
United States
Francis McAllister, Investor Relations
Tel: +1 713 961 8625 Mobile: +1 713 480 3699
email: Francis.R.McAllister@bhpbilliton.com
BHP Billiton Limited BHP Billiton Plc
ABN 49 004 028 077 Registration number 3196209
Registered in Australia Registered in England and Wales
Registered Office: 600 Bourke Street Registered Office: 1-3 Strand London
Melbourne Victoria 3000 WC2N 5HA United Kingdom
Telephone +61 3 9609 3333 Telephone +44 20 7747 3800
Facsimile +61 3 9609 3015 Facsimile +44 20 7747 3900
The BHP Billiton Group is headquartered in Australia
COPPER PRODUCTION TELECONFERENCE
Following BHP Billiton Base Metal's announcement of a planned reduction in its
copper production, we invite you to participate in a teleconference involving
BHP Billiton Base Metal's senior management - Brad Mills, President Base
Metals; Ken Pickering, President & Chief Development Officer and Bruce Turner,
President, Minera Escondida Ltda.
The teleconference will provide details on the strategic rationale for the
reduction in copper production and the opportunity to ask questions of the
Base Metals' senior management.
Two teleconferences will be held. Details of the times are provided below.
Call in arrangements are provided on the following pages:
Teleconference £1
Thursday 8 November
New York 6.00 pm
London 11.00 pm
Friday 9 November
Melbourne/Sydney 10.00am
Teleconference £2
Friday 9 November
New York 5.00 am
London 10.00am
South Africa 12.00pm
Melbourne/Sydney 9.00pm
A recording of Teleconference £1 will be available for playback on the
following numbers, approximately one hour after completion of Teleconference £
1.
Australia: 1800 655 401 International: 61 3 9414 6837
Please note the playback facility is only available through the phone numbers
listed above.
For further information, please contact Lina Alifraco on +61 3 9609 2692 or
e-mail melinda.d.buse@bhpbilliton.com
Yours sincerely,
Robert Porter
Vice President Investor Relations & Communication
ConferLinka
Participants Call-In Reference Guide
'BHP Billiton TeleConference £1'
Question Queuing Conference
Date: 09/11/01 Friday
Start Time: 10:00 AM Melbourne time
(6.00pm US)
(8.00pm Chile)
(11.00pm UK)
(1.00am South Africa)
(7.00am Singapore & Hong Kong)
(8.00am Japan)
Reservation number: 2748075
Your Call-In numbers are: 1800 686 443 (Australia)
USA 1800 2767498
UK 0800 8566164
Singapore 800 6161711
Japan 0053 1610035
HongKong 800 900197
All Others + 61 3 9290 0968
REMEMBER: To participate in a ConferLink Question Queuing conference, you
will need a touchtone phone.
- To register a question press*1
- To cancel your question press*2
- For help during the conference press*0
* Approximately 10-15 minutes before the scheduled time, please dial
your Call-in number.
* You will be greeted by a conference administrator who will note your
name and telephone number. You may be asked to test your telephone to ensure
that you will be able to register questions. You will then be placed on hold
music until the conference is due to commence.
* At the start of the conference your line will be taken off hold music
and you will be placed in Listen only (mute) mode.
* If at any time during the conference you wish to ask a question or
make a comment, press (*1) to register your question. If you decide to cancel
your question at any time press (*2). Your questions and the answers will be
heard by all parties on the conference. When you have finished asking your
questions and received answers you will be placed back in Listen only mode.
* If you are disconnected for any reason during the conference redial
your Call-in number.
* At the end of the conference, the presenter will inform you that the
conference has concluded.
PHONE: 1800 011 080
FAX: 1800 636 776
EMAIL: conferlink@telstra.com.au
ConferLinka
Participants Call-In Reference Guide
'BHP Billiton Teleconference £2'
Question Queuing Conference
Date: 09/11/01 Friday
Start Time: 10:00 AM London
12:00 noon South Africa
(5.00am US)
(7.00am Chile)
(6.00pm Singapore & Hong Kong)
(7.00pm Japan)
(9.00pm Melbourne)
Reservation number: 2748352
Your Call-In number is: + 61 3 9290 0961 (International)
Or Freecall for these countries:
USA 1800 2767498
UK 0800 8566164
Singapore 800 6161711
Japan 0053 1610035
HongKong 800 900197
Australia 1800 686 443
REMEMBER: To participate in a ConferLink Question Queuing conference, you
will need a touchtone phone.
- To register a question press*1
- To cancel your question press*2
- For help during the conference press*0
* Approximately 10 minutes before the scheduled time, please dial your
Call-in number.
* You will be greeted by a conference administrator who will note your
name and telephone number. You may be asked to test your telephone to ensure
that you will be able to register questions. You will then be placed on hold
music until the conference is due to commence.
* At the start of the conference your line will be taken off hold music
and you will be placed in Listen only (mute) mode.
* If at any time during the conference you wish to ask a question or
make a comment, press (*1) to register your question. If you decide to cancel
your question at any time press (*2). Your questions and the answers will be
heard by all parties on the conference. When you have finished asking your
questions and received answers you will be placed back in Listen only mode.
* If you are disconnected for any reason during the conference redial
your Call-in number.
* At the end of the conference, the presenter will inform you that the
conference has concluded.
PHONE: 1800 011 080
FAX: 1800 636 776
EMAIL: conferlink@telstra.com.au