BP PLC
18 September 2006
BP SAYS THAT REPAIR OF SUBSEA EQUIPMENT
WILL DELAY THUNDER HORSE UNTIL 2008
Following a series of tests carried out over the past four months that revealed
metallurgical failure in components of the subsea system, BP announced today
that it plans to retrieve and rebuild all the sea-bed production equipment from
its Thunder Horse field in the deepwater Gulf of Mexico.
BP said the problem became evident when it conducted pre-commissioning tests by
pumping water through the system to establish system integrity. The equipment
passed all the normal industry standard tests and regulatory requirements. But
when the company carried out more prolonged and rigorous testing, as an
additional safety precaution, a failure occurred on a subsea weld.
As a consequence of the failure, BP said it had decided to retrieve both the
damaged sea-bed manifold and a second manifold for further examination and
onshore testing. The second manifold displayed a similar failure during testing
last week.
In view of these failures, BP today said it would now retrieve and replace all
the subsea components it believes could be at risk. This work will be done over
the course of the next year and the company said it does not expect production
from Thunder Horse to begin before the middle of 2008.
It said it was too early to estimate the additional costs involved in replacing
the affected systems.
Notes to Editors:
• The Thunder Horse field was discovered in 1999. It is designed to use the
largest production drilling quarters semi-submersible platform in the
world.
• The platform weighs more than 50,000 tons and will produce from water
depths of about 6,000 feet, from some of the highest temperature and
highest pressure wells in the Gulf of Mexico.
• The facility is designed to process 250,000 barrels of oil a day and 200
million standard cubic feet per day.
• Oil and gas will be transported to existing shelf and onshore
interconnections via the Mardi Gras transportation system.
• BP operates the development (75 per cent interest), with co-venturer
ExxonMobil owning the balance.
• BP began deepwater Gulf of Mexico operations in the mid-1980s. BP now
produces about 270,000 barrels of oil equivalent per day from nearly two
dozen fields, including BP-operated facilities at Pompano, Marlin, Horn
Mountain and Na Kika.
Further information:
BP Press Office, London, tel: +44 (0)20 7496 4076
BP Press Office, Houston, tel: +1 281 366 5174
- ENDS -
This information is provided by RNS
The company news service from the London Stock Exchange D
*A Private Investor is a recipient of the information who meets all of the conditions set out below, the recipient:
Obtains access to the information in a personal capacity;
Is not required to be regulated or supervised by a body concerned with the regulation or supervision of investment or financial services;
Is not currently registered or qualified as a professional securities trader or investment adviser with any national or state exchange, regulatory authority, professional association or recognised professional body;
Does not currently act in any capacity as an investment adviser, whether or not they have at some time been qualified to do so;
Uses the information solely in relation to the management of their personal funds and not as a trader to the public or for the investment of corporate funds;
Does not distribute, republish or otherwise provide any information or derived works to any third party in any manner or use or process information or derived works for any commercial purposes.
Please note, this site uses cookies. Some of the cookies are essential for parts of the site to operate and have already been set. You may delete and block all cookies from this site, but if you do, parts of the site may not work. To find out more about the cookies used on Investegate and how you can manage them, see our Privacy and Cookie Policy
To continue using Investegate, please confirm that you are a private investor as well as agreeing to our Privacy and Cookie Policy & Terms.