Operational UpdateGoldplat plc / Ticker: GDP / Index: AIM / Sector: Mining & Exploration
4 September 2015
Goldplat plc ('Goldplat' or 'the Company')
Operational Update
Goldplat plc, the AIM listed African gold producer, is pleased to announce significant progress on capital projects and new contracts aimed at improving the production and efficiency of its gold recovery operation in South Africa, Goldplat Recovery (Pty) Limited, ('GPL') which processes by-products from the mining process to recover gold.
Capital projects
A new electric boiler has been installed and is currently being commissioned at GPL. Although this boiler has been installed in anticipation of the installation of the first 4 tonne elution column acquired from DRD Gold (scheduled for October 2015), the immediate effect has been the ability to improve the utilisation of the two existing 1 tonne elution columns and to increase throughput to 5 tonnes of loaded carbon per day from these two columns. This is expected to have a significant impact on the treatment of backlog material (as reported 17 June 2015) and is aligned with Goldplat's strategy to capture more of the gold recovery value chain in-house.
The new woodchip wash plant was commissioned in mid-August 2015 and has had a positive impact allowing for an additional 2kg of gold production per month from the existing wood chip stockpiles. Payback of the ZAR2.5 million capital expenditure is expected to be 6 to 7 months.
Contracts
GPL has entered into a contract with its third party refining partner, Rand Refinery whereby GPL will toll-process a large batch of by-product material for Rand Refinery. This is expected to yield silver and gold for which GPL will be paid treatment and refining charges. The high grade circuit will be dedicated to processing the material under this contract for an initial two months and it will take a further four months to complete the elutions. Material previously planned to be processed through the high grade circuit will be processed through the low grade circuit which is scheduled to be commissioned in mid-September 2015. The commissioning of the new 4 tonne elution column is timely in order to support this very important project which would not have been possible had Goldplat not strategically increased its elution capacity at GPL.
Where Rand Refinery has not been able to accept and process certain Goldplat material (which is now mostly being processed in-house and through Aurubis Refinery in Germany), they have now begun accepting batches of ashes again albeit in limited quantities and on an ad-hoc basis.
Gerard Kisbey-Green, CEO of Goldplat plc commented: "We are very pleased to announce the completion of certain capital projects, which we believe will have an immediate positive impact on flexibility and ultimately profitability of the operations. Particularly satisfying is the fact that despite the cashflow problems experienced throughout the past 18 months, Goldplat has managed to, and continues to manage to finance strategic and essential capital projects internally. The management and operational teams are committed to completing projects on time and within budget so as to meet financial plans going forward.
Regarding Rand Refinery, we are pleased that despite the challenges, the relationship between Goldplat and Rand Refinery is strong and that we continue to find mutually beneficial ways to work together."
** ENDS **
For further information visit www.goldplat.com or contact:
Gerard Kisbey-Green, CEO | Goldplat plc | Tel: +27 (71) 8915775 |
Ewan Leggat/Katy Birkin | SP Angel Corporate Finance LLP | Tel: +44 (0) 20 3470 0470 |
Andrew Raca/Justin McKeegan | VSA Capital | Tel: + 44 (0)20 3005 5000 |
Felicity Winkles/Charlotte Heap | St Brides Partners Ltd | Tel: +44 (0) 20 7236 1177 |
Goldplat plc, is an AIM-listed gold recovery services company with two market leading operations in South Africa and Ghana. The Company's strategy is focussed on utilising its cash flow generated from flagship gold recovery operations in Africa to self-fund sustainable growth and expansion of niche gold recovery business model. The Company also has a small gold mining and exploration portfolio in Kenya, Burkina Faso and Ghana and is evaluating various opportunities to create value or monetise these assets.
This announcement is distributed by NASDAQ OMX Corporate Solutions on behalf of NASDAQ OMX Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: Goldplat plc via Globenewswire
HUG#1949698