24 April 2018
Goldplat plc ('Goldplat' or 'the Company')
Operational Update
Goldplat plc, the AIM listed gold producer, with international gold recovery operations based in South Africa and Ghana and a gold mine in Kenya, is pleased to announce an operational update for the three months ended 31 March 2018 (the 'Quarter').
Overview
Production for the Quarter
Overall production of 6,966 ounces of gold and gold equivalents was achieved during the Quarter, with operating profitability continuing at the recovery operations together with a continued reduction in losses made at Kilimapesa Gold Mine ('Kilimapesa'). In line with our commitment to build production output and profitability, the sourcing of by-product material for processing at the recovery operations and improving operational efficiencies at Kilimapesa remain primary areas of strategic focus for the Company. During the Quarter, sourcing of material for Gold Recovery Ghana was slower than anticipated, however several batches of new material are in the final stages of contract completion. Losses continued at Kilimapesa due to lower grades and problems with the impact crusher at Plant 2.
Gold Equivalent Ounces | ||||
for the month period ending 31 March 2018 | ||||
Goldplat Plc - Group | Year ending | |||
3rd Qtr | 9 Months | 9 Months | 12 Months | |
Actual | Actual | Actual | Previous | |
Mar-18 | Mar-18 | Mar-17 | Jun-17 | |
Equivalent Gold | Equivalent Gold | Equivalent Gold | Equivalent Gold | |
Oz | Oz | oz | oz | |
Gold Equivalent Production | ||||
Goldplat Recovery (Pty) Ltd | 4,533 | 18,501 | 17,518 | 29,418 |
Gold Recovery Ghana Ltd | 1,192 | 4,789 | 8,391 | 10,031 |
Kilimapesa Gold (Pty) Ltd | 1,241 | 3,922 | 2,154 | 3,408 |
Total | 6,966 | 27,212 | 28,063 | 42,857 |
Gold Equivalent Sold | ||||
Goldplat Recovery (Pty) Ltd | 3,852 | 15,272 | 12,732 | 22,570 |
Gold Recovery Ghana Ltd | 339 | 5,032 | 7,909 | 8,327 |
Kilimapesa Gold (Pty) Ltd | 1,380 | 4,100 | 1,993 | 3,215 |
Total | 5,571 | 24,404 | 22,634 | 34,112 |
Gold Equivalent Transferred | ||||
Goldplat Recovery (Pty) Ltd | 1,180 | 4,130 | 5,080 | 6,173 |
Total | 1,180 | 4,130 | 5,080 | 6,173 |
Gold Equivalent Sold and Transferred | ||||
Goldplat Recovery (Pty) Ltd | 5,032 | 19,402 | 17,812 | 28,743 |
Gold Recovery Ghana Ltd | 339 | 5,032 | 7,909 | 8,327 |
Kilimapesa Gold (Pty) Ltd | 1,380 | 4,100 | 1,993 | 3,215 |
Total | 6,751 | 28,534 | 27,714 | 40,285 |
Goldplat Recovery (Pty) Ltd ('GPL'), South Africa
Goldplat Recovery Ghana ('GRG'), Ghana
Kilimapesa Gold ('KPG')
International marketing and sourcing
Gerard Kisbey-Green, CEO of Goldplat plc, commented:
"The conclusion of the Rand Refinery dispute and the completion of the elution circuit at GRG were key highlights of the Quarter. As we continue to focus on building gold production and increasing profitability, we look forward to progressing the turnaround at Kilimapesa and securing new strategic supply contracts at an international level for our recovery operations."
** ENDS **
For further information visit www.goldplat.com, follow on Twitter @GoldPlatPlc or contact:
Gerard Kisbey-Green | Goldplat plc (CEO) | Tel: +27 (71) 8915775 |
Colin Aaronson / Jen Clarke | Grant Thornton UK LLP (Nominated Adviser) | Tel: +44 (0) 20 7383 5100 |
James Joyce / Jessica Cave | WH Ireland Limited (Broker) | Tel: +44 (0) 207 220 1666 |
Charlotte Page / Susie Geliher | St Brides Partners Ltd (Financial PR) | Tel: +44 (0) 20 7236 1177 |
The information contained within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.
About Goldplat
Goldplat plc is an AIM quoted gold producer with two market leading recovery operations in South Africa and Ghana and an operational gold mine in Kenya. The Company produced 42,857 ounces of gold during FY 2017, with 40,285 gold equivalent ounces sold and transferred, resulting in an operating profit from continuing operations of £2.9m for the year. This result does not benefit from the increased processing capacity that was achieved at the Kilimapesa Gold Mine towards the end of FY 2017, with operational profitability achieved during last two months of FY 2017. Accordingly, the Company believes it is well placed to build upon production and profitability during FY 2018.
The Company's strategy is focussed on utilising cash flow generated from its flagship gold recovery and mining operations to self-fund the sustainable growth and expansion of its niche gold recovery business model internationally. The Company is also committed to increasing its primary mining production output through acquisition / gaining interests in producing or near-production assets, preferably in Africa. Goldplat retains exposure to a small exploration project in Ghana, in which Ashanti Gold Corp. is earning an interest via an earn-in option agreement.