17 February 2014
OPG Power Ventures plc
("OPG" or the "Company")
Trading update for the three months ended 31 December 2013
OPG Power Ventures plc, the developer and operator of power generation plants, presents a trading update for the three months ended 31 December 2013 (Q3 FY14).
Operational Highlights
· Q3 FY14 generation of 518 million units up 8% on Q2 FY14 (Q3 FY13: 301 million units)
· Total year-to-date generation up 129% on nine months ended 31 Dec 2012
· C3 unit fully ramped up; average Plant Load Factor (PLF) achieved across all units of 100% in the quarter (Q2 FY14: 93%)
· Average year-to-date PLF across all units of 96% up from 90% in nine months ended 31 Dec 2012
· Q3 FY14 Underlying Rupee Revenue of Rs 2.67 bn compared with Rs 4.82 bn in full year FY13
· Entered into a 15 year Long Term Variable tariff arrangement with TANGEDCO for C3, providing foreign exchange protection on imported coal
· Full year results expected to meet market expectations
Project Highlights
· 300 MW Gujarat (2x150 MW units) - within budget and on track for commissioning by Sep 2014
· 160 MW Chennai IV - within budget and on track for commissioning by Dec 2014
Parameter |
Quarter ended 31 Dec 13 |
Quarter ended 30 Sep 13 |
Quarter ended 31 Dec 12 |
Nine Months ended 31 Dec 13 |
Nine Months ended 31 Dec 12 |
Full year ended 31 Mar 13 |
Generation (Mn units) |
|
|
|
|
|
|
Chennai I |
161 |
164 |
155 |
493 |
448 |
617 |
Chennai II |
178 |
172 |
146 |
512 |
146 |
315 |
Chennai III |
178 |
143 |
- |
355 |
- |
- |
Total (Mn units) |
518 |
479 |
301 |
1360 |
594 |
932 |
|
|
|
|
|
|
|
PLF (%) |
|
|
|
|
|
|
Chennai I |
95 |
97 |
91 |
97 |
88 |
92 |
Chennai II |
105 |
101 |
96 |
101 |
96 |
99 |
Chennai III |
101 |
81 |
- |
88 |
- |
- |
Average (%) |
100 |
93 |
93 |
96 |
90 |
94 |
|
|
|
|
|
|
|
Tariff (Rs/kWh) |
5.54 |
5.52 |
5.53 |
5.55 |
5.52 |
5.58 |
Projects
Provided below is a quantified assessment of the progress of the Company's current and most significant projects. This is based purely on management's experience and not verified by any third party and is presented by reference to each of the key stages in a typical project in development. It is a management estimate at the date of this statement only and does not purport to quantify the risk of any project not commissioning.
Project stage |
Financing |
Civil Works and Foundations |
Chimney/Boiler related/Rest of plant |
Chennai IV |
100% |
90% |
50% |
Gujarat |
100% |
92% |
72% |
At Chennai IV, almost all civil works and foundations have been completed. The boiler drum has been erected and installed and the air cooling condensers are in advanced construction. A team of around 300 are working full time at the site, to be joined by a further 50 when turbine deliveries commence around June 2014. Balance of plant completion and equipment testing, including hydro tests, should follow in the subsequent quarter. Chennai IV shares its storage, power evacuation and water treatment facilities with Chennai II and III. Our leadership team for the delivery of Chennai IV is the same as on the previous three Chennai units and the project continues to be on track for commissioning in the current calendar year.
Our 300 (2x150) MW Gujarat project also continues to progress well. The installation and hydro testing of both boilers has been completed successfully. Turbines of both units are now at site and the turbine of one of the units has been installed. Chimney construction is complete. Construction of the balance of plant is ongoing and should finish in June 2014. Thereafter, we expect to commence test firing in the subsequent quarter and the project continues to be on track for commissioning around September 2014.
Our website at www.opgpower.com has been updated with recent photographs of all operations and projects.
Outlook
We remain positive as to the Company's prospects as both expansion projects are progressing well and we continue to expect to commission significant additional capacity in 2014. Due to the strong performance of our operating assets, we remain confident that the results for the current financial year will meet market expectations.
About OPG
OPG is operating and developing power projects in India under the group captive model with 235 MW in operations and a further 460 MW under development. In the six months ended 30th September 2013, Group revenues were £47.7m, EBITDA was £13.7m and profit before tax was £7.6m.
For further information, please visit www.opgpower.com or contact:
OPG Power Ventures PLC |
+91 (0) 44 429 11 211 |
Arvind Gupta |
|
V Narayan Swami |
|
|
|
Cenkos Securities (Nominated Adviser & Broker) |
|
Stephen Keys / Camilla Hume |
+44 (0) 20 7397 8900 |
|
|
Tavistock Communications |
|
Simon Hudson/James Collins |
+44 (0) 20 7920 3150 |
-ends-