Turbine Foundations in Place

RNS Number : 8835R
Scottish & Southern Energy PLC
31 August 2010
 



TURBINE FOUNDATIONS IN PLACE AT GREATER GABBARD

 

SSE (Scottish and Southern Energy plc) and RWE npower renewables have announced that the installation of all of the 140 turbine foundations is now complete and 30 wind turbines are now in place at their Greater Gabbard offshore wind farm development.

 

The first offshore turbines are expected to start producing renewable energy later this year.  Greater Gabbard wind farm is scheduled to become fully operational in 2012 when it is expected to generate enough renewable electricity for over 500,000 homes*.

 

Colin Hood, SSE's Chief Operating Officer, said:

 

"This is a substantial milestone in the development of the Greater Gabbard wind farm, and demonstrates how well the project is progressing overall. When the wind farm becomes fully operational in 2012, it will help the UK meet tough targets for renewable electricity generation."

 

*based on site specific met mast data indicating a load factor of at least 40%, and based on household consumption of 3,300kWh a year.

 

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCMMGFRZMDGGZM

Companies

SSE (SSE)
UK 100

Latest directors dealings