Operations Update
Silvermere, the independent oil and gas company focused principally on appraisal and production opportunities in the US, is pleased to announce further progress with the tie-in of the I-1 well in its Mustang Island 818-L Field. This is based on information provided by the Operator, Dominion Production Company LLC ("Dominion").
Pile-driving to secure the legs of the off-shore platform to the sea floor was completed on 20 July and installation of the main deck section on top of the platform legs was completed yesterday, 29 July.
The remaining installation tasks include laying the 475 feet of 6-inch diameter pipeline between the platform and sub-sea tie-in point and then completing and testing the tie-in at both ends. Following this the well will be hooked up to the platform to establish flow. Initial flow will involve "unloading" the well contents and filling the pipeline with gas and condensate. The activities described are expected to take approximately two weeks, weather permitting.
Some days last week were lost due to sea swells outside safe operating tolerance, but as of last night, the outlook for sea and weather conditions is satisfactory for continuing operations.
Further updates will be provided as the work progresses.
--ENDS--
For further information please contact:
Silvermere Energy plc Andy Morrison, Chief Executive
|
+44 (0)7980 878 561 |
Merchant Securities Limited (Nominated Adviser and Broker) Lindsay Mair/Virginia Bull/Catherine Miles
|
+ 44(0)20 7628 2200 |
Peterhouse Corporate Finance Limited Jon Levinson
|
+44 (0)20 7469 0937 |
Bishopsgate Communications Nick Rome/ Anna Michniewicz/ Ivana Petkova |
+44(0)20 7562 3350 |
About Silvermere Energy PLC
The Company acquired its interest in the Mustang Asset on 30 August 2011. This comprises a 33.33 per cent. working interest and 20.83 per cent. net entitlement interest in the Mustang Licence Area, an area within the southern half of the north west quarter and northern half of the south west quarter of the Block 818-L field as defined in State of Texas Oil and Gas Lease numbers 108873 and 108874. The Mustang Island 818-L field, located in Kleberg County waters of the Gulf of Mexico, is a field re-habilitation project targeting bypassed or only partially produced gas-condensate.
Early in 2011 the Hercules Offshore 205 jack-up rig was contracted to re-enter the I-1 Well on the Mustang Licence Area which was considered to be the most likely of the historic well sites to provide 14 optimum re-entry conditions. The I-1Well re-entry and side-tracking operation was completed in March 2011 leaving it ready to complete in sand horizons I-1 to I-6. Production and flow testing was carried out during June 2011. The well re-entry programme was led by Dominion as the operator. Gas and oil produced from the I-1Well is proposed to be connected to pipeline infrastructure and tied in via a subsea assembly, constructed for the purpose and then transported to the Six Pigs gas facility.
Silvermere's strategy is to acquire a portfolio of US oil and gas licence interests onshore and in shallow offshore waters, characterised by relatively low risk and low cost with the potential for near term production.
Silvermere is quoted on the AIM Market of the London Stock Exchange plc (AIM: SLME) with its offices in London.