Zanaga Project Update

RNS Number : 1087R
Zanaga Iron Ore Company Ltd
31 October 2011
 



31 October 2011

 

 

 

ZANAGA IRON ORE COMPANY LIMITED

("ZIOC" or the "Company")

Zanaga Project Update

 

 

Zanaga Iron Ore Company Limited (AIM:ZIOC) is pleased to announce the following update on the Zanaga Iron Ore Project (the "Zanaga Project") in the Republic of Congo (Congo Brazzaville)

 

Highlights

·      Value Engineering Exercise ("VEE") completed

results confirm the economic viability of the Zanaga Project

post VEE the projected cost of the 45 Mtpa railway option remains in line with IPO estimates

o    an alternative 30Mtpa slurry pipeline transportation option identified with potential to further enhance project economics

·      Xstrata intends to commit to a Pipeline Study shortly to refine the pipeline option and its economics

·      Feasibility Study ("FS") drilling and Environmental and Social Impact Assessment (ESIA) work continues on schedule

FS expected to conclude in Q1 2014

·      Joint search initiated with Xstrata for a strategic partner for the Zanaga Project

 

Clifford Elphick, Non-Executive Chairman of ZIOC, commented:

"Following the completion of the Value Engineering Exercise, ZIOC is pleased to provide an update on the Zanaga Project. It is extremely pleasing that the PFS and VEE work streams have confirmed the economic viability of the 45 Mtpa railway option. In addition, significant potential incremental value has been identified based on modifying the mode of transport to a slurry pipeline, producing a high grade pellet feed product. Xstrata intends to commit to a Pipeline Study shortly to refine this option and its costing, which will assist in determining which option to take through to final Feasibility Study. ZIOC and Xstrata have in addition begun to investigate strategic partner options"


Value Engineering Exercise

 

The VEE represents an important initial stage of the FS. Following ZIOC's announcement on 8 February 2011 a team of internal and external experts was assembled to conduct the VEE, based on the capital and operating cost reduction opportunities recognised in the draft PFS report. With Xstrata managing the Zanaga Project, the VEE focused on investigating a broad range of development opportunities for the Project to identify the most attractive final development option. During the VEE phase, the project team continued its resource, geotechnical and hydro-geological drilling, metallurgical test work and all other associated port and mine site engineering and ESIA FS work programs.

 

As part of the VEE the pipeline option was revisited to investigate several capex and opex optimisation possibilities as well as the fit with changing global iron ore market dynamics. The outcome of this review confirmed two viable transport options for the development of the Zanaga Project:

 

1) Railway Option:

The original railway option assumes that on average 118 Mtpa of ore will be treated through two processing plants to produce 30 Mtpa of magnetite concentrate and 15 Mtpa of Hematite sinter feed which will be transported to the port at Pointe Noire via a 350 km railway and exported from a new port facility 9 km north of Pointe Noire. Life of Mine (LOM) will be in the region of 30 years, although the resource base and its upside potential will support either increased production or a longer LOM. The design, development plan and costs for the railway option have not changed materially since IPO.

 

45 Mtpa Railway Option - Capital Cost Estimate (US$m)

 

Area

IPO
(Nov 2010)

Post VEE
(Oct 2011)

Minesite

2,644

3,170

-406

2,764

Transport Corridor

2,074

2,472

-462

2,010

Port

896

681

-108

573

Power

214

500

50

550

Total Direct

5,828

6,822

-926

5,896

Indirect costs1

634

915

0

915

Contingency2

986

734

0

734

TOTAL

7,448

8,471

-926

7,545

 

Notes: The Post VEE figures above include potential savings identified by the Xstrata managed VEE and have not been the subject of a formal capital re-estimate. . Figures exclude FS costs (funded by Xstrata) of an estimated US$249m and are in 2011 US$.

1Indirect costs include Head Office costs, EPCM & other indirect costs

2 Contingency provision of US$734m (10% of total direct plus indirect costs) for the 45 Mtpa railway option was the result of a thorough quantitative risk analysis (QRA) performed by the project team on the pre VEE case

 

FOB operating cost for the 45 Mtpa rail option as estimated by the PFS workstreams is US$25 per dry metric tonne including a US$2/tonne contingency. In addition, approximately US$3/tonne of potential savings were then identified by the VEE. This represents a significant saving compared with the blended FOB operating cost presented at IPO of US$27/tonne.



2) Pipeline Option:

 

The pipeline option assumes that initially 30 Mtpa of pellet feed will be produced from an average 75 Mtpa of combined hematite/magnetite ore. Treatment of ore will be through a single integrated processing plant. The pellet feed product will be transported via a slurry pipeline to the port site to the north of Pointe Noire. LOM will be in excess of 30 years and significant potential exists to expand production.

 

The Pipeline Option has the potential to enhance the Zanaga Project's value by significantly reducing both capital expenditure and operating costs.

 

30 Mtpa Pipeline Option - Capital Cost Estimate (US$m)

 

Area

30 Mtpa Pipeline Option

Mine

1,203

Beneficiation plant

1,071

Transport Corridor

1,096

Port

484

Power

564

Total Direct

4,418

Head Office

273

Indirects

441

On-costs (EPCM)

502

Contingency

1,627

Total per Xstrata managed VEE

7,260

FS costs (funded by Xstrata)

(249)

ZIOC identified savings:


Indirects1

(322)

Contingency2

(629)

TOTAL- ZIOC guidance

6,060

Notes: ZIOC's technical team has identified potential savings to certain indirect costs and contingency provisions outlined below. Figures shown in 2011 US$.

1Comprises additional indirect costs included by Xstrata in the pipeline option but not included in the railway option

2Comprises additional contingency included by Xstrata consisting primarily of engineering rework and full costs associated with an assumed one year project delay

 

FOB operating cost for the 30 Mtpa slurry pipeline as estimated by the VEE is US$21 per dry metric tonne including a US$5/tonne contingency.

 

Pipeline Study

 

Xstrata intends to commit to a Pipeline Study shortly to refine this option and its costing, which will assist in determining which option to take through to final Feasibility Study.

 

Strategic Partner Process

 

Xstrata and ZIOC wish to explore whether there is a suitable strategic partner who can further enhance the long-term value of the Zanaga Project, including off-take on commercial terms, access to construction financing and construction expertise.  Accordingly Xstrata and ZIOC have embarked on a joint process, which is at an early stage, to identify a party to become a strategic partner in the development of this world class project.  Xstrata intends to fully retain its interest in the Zanaga Project. There can be no certainty that this process will result in any transaction being completed.

 

 

For further information please contact:

Zanaga UK Services Limited                                                                              

Corporate Development and                                                                                                                                                                                Andrew Trahar
Investor Relations Manager                                                                                                                                                                          +44 20 7399 1105

 

Liberum Capital Limited

Nominated Adviser, Financial                                                                                                                                        Chris Bowman, Christopher Britton
Adviser and Joint Corporate Broker                                                                                                                                                and Christopher Kololian

                                                                                                                                                                                                                            +44 20 3100 2000

 

Citigroup Global Markets Limited

Joint Corporate Broker                                                                                                                                                                                                Alex Carter

                                                                                                                                                                                                                            +44 20 7986 4000

 

Pelham Bell Pottinger

Financial PR                                                                                                                                                                                                    James MacFarlane
                                                                                                                                                                                                                       and Philippe Polman

                                                                                                                                                                                                                            +44 20 7861 3232

About us:

Zanaga Iron Ore Company Limited (AIM:ZIOC) is a BVI registered Company and the owner of 50% less one share interest in the Zanaga Iron Ore Project based in the Republic of Congo (Congo Brazzaville) through its joint venture partnership with Xstrata. The Zanaga Project is focused on the management, development and construction of a world-class iron ore mine and related, processing, transportationand port infrastructure


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDXBDGGDXBGBG
UK 100

Latest directors dealings