Quarterly Activities Report for September 2026

AI SummaryClose X

Aura Energy Limited reported significant progress in its September 2026 quarter, particularly with the Tiris Uranium Project in Mauritania, where a new leadership team was appointed to oversee the transition from study to construction. The Bankable Feasibility Study for Tiris was released on October 16, 2026, revealing a post-tax Net Present Value of US$500.3 million. Construction of the Tiris pilot plant is underway, with commissioning expected in November 2026, and the company continues to pursue project financing and a Final Investment Decision by year-end. Aura also holds A$10.6 million in cash as of September 30, 2026, and has seen positive legislative changes in Sweden regarding uranium mining.